ODOT contract 268002 bid tabulation
LAW-SR 7-13.63 (CULVERT REPLACEMENT). Let by Ohio DOT on March 12, 2026, LAW. 4 bids received; low bid $228,621 by Fillmore Construction, -0.6% against the engineer's estimate of $230,000.
- Owner
- Ohio DOT
- Letting
- 12 MAR 2026
- Pay items
- 43
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Fillmore Construction | $228,621 | Low | -1.0% |
| 2 | Axis Civil Construction LLC | $319,333 | +40% | +39% |
| 3 | Stanley Miller Construction Company | $367,512 | +61% | +60% |
| 4 | R C Construction Company and Son Inc | $444,364 | +94% | +93% |
Engineer's estimate: $230,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Fillmore Construction | 2. Axis Civil Construction LLC | 3. Stanley Miller Construction Company | 4. R C Construction Company and Son Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $1,500.00 | $3,500.00 | $1,000.00 | $20,000 |
| 2 | Pavement removed (202E23000) | SY | 78 | $50.00 | $20.00 | $30.00 | $35.00 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 104 | $50.00 | $200.00 | $100.00 | $100.00 |
| 4 | Guardrail removed (202E38000) | FT | 192 | $10.00 | $6.00 | $10.00 | $5.00 |
| 5 | Catch basin removed (202E58100) | EACH | 1 | $500.00 | $4,200.00 | $1,000.00 | $1,500.00 |
| 6 | Excavation (203E10000) | CY | 51 | $100.00 | $35.00 | $125.00 | $25.00 |
| 7 | Embankment (203E20000) | CY | 2 | $1,000.00 | $120.00 | $150.00 | $65.00 |
| 8 | Subgrade compaction (204E10000) | SY | 85 | $10.00 | $4.41 | $5.00 | $2.00 |
| 9 | Proof rolling (204E45000) | HR | 1 | $150.00 | $250.00 | $80.00 | $100.00 |
| 10 | Guardrail, type MGS with long posts (606E15100) | FT | 125 | $52.00 | $38.00 | $50.00 | $65.00 |
| 11 | Anchor assembly, MGS type E (606E26150) | EACH | 1 | $2,800.00 | $2,500.00 | $3,000.00 | $3,500.00 |
| 12 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,500.00 | $1,200.00 | $2,500.00 | $2,500.00 |
| 13 | Rock channel protection, type B with geotextile fabric (601E32104) | CY | 3 | $1,000.00 | $326.00 | $750.00 | $750.00 |
| 14 | Seeding and mulching (659E10000) | SY | 200 | $8.50 | $10.00 | $30.00 | $20.00 |
| 15 | Commercial fertilizer (659E20000) | TON | 0.03 | $1,800.00 | $1,250.00 | $800.00 | $2,800.00 |
| 16 | Lime (659E31000) | ACRE | 0.04 | $800.00 | $150.00 | $150.00 | $2,200.00 |
| 17 | Water (659E35000) | MGAL | 2 | $10.00 | $1.00 | $1.00 | $1.00 |
| 18 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 19 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $10,000 | $34,000 | $2,500.00 | $35,000 |
| 20 | Concrete masonry (602E20000) | CY | 1 | $1,000.00 | $4,200.00 | $3,500.00 | $4,000.00 |
| 21 | 12" conduit, type C (611E04600) | FT | 12 | $300.00 | $140.00 | $500.00 | $400.00 |
| 22 | 36" conduit, type B, as per plan (611E16401) | FT | 90 | $1,000.00 | $1,150.00 | $595.00 | $450.00 |
| 23 | Catch basin, no. 2-4 (611E98540) | EACH | 1 | $9,500.00 | $15,000 | $9,000.00 | $25,000 |
| 24 | Full depth pavement sawing (252E01500) | FT | 61 | $10.00 | $6.00 | $25.00 | $100.00 |
| 25 | Pavement repair (253E01000) | SY | 50 | $100.00 | $120.00 | $300.00 | $25.00 |
| 26 | Pavement planing, asphalt concrete (T=1.5") (254E01000) | SY | 145 | $40.00 | $25.00 | $45.00 | $65.00 |
| 27 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 18 | $300.00 | $420.00 | $1,250.00 | $1,000.00 |
| 28 | Aggregate base (304E20000) | CY | 14 | $100.00 | $165.00 | $160.00 | $195.00 |
| 29 | Tack coat (407E10000) | GAL | 77 | $10.00 | $7.00 | $50.00 | $10.00 |
| 30 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 38 | $400.00 | $400.00 | $1,250.00 | $1,000.00 |
| 31 | Barrier reflector, type 3 (two-way) (626E00112) | EACH | 4 | $12.50 | $12.00 | $50.00 | $25.00 |
| 32 | Ground mounted support, no. 3 post (630E03100) | FT | 50 | $18.50 | $12.00 | $50.00 | $25.00 |
| 33 | Removal of ground mounted sign and reerection (630E85100) | EACH | 6 | $150.00 | $40.00 | $50.00 | $300.00 |
| 34 | Removal of ground mounted post support and disposal (630E86002) | EACH | 4 | $25.00 | $15.00 | $50.00 | $1,000.00 |
| 35 | Edge line, 6" (644E00104) | MI | 0.02 | $83,000 | $25,000 | $200,000 | $95,000 |
| 36 | Center line (644E00300) | MI | 0.01 | $83,000 | $42,000 | $200,000 | $110,000 |
| 37 | Detour signing (614E12420) | LS | 1 | $4,450.00 | $5,000.00 | $10,000 | $35,000 |
| 38 | Asphalt concrete for maintaining traffic (614E13000) | CY | 25 | $300.00 | $330.00 | $150.00 | $25.00 |
| 39 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,500.00 | $4,500.00 | $12,000 | $35,000 |
| 40 | Maintaining traffic (614E11000) | LS | 1 | $2,500.00 | $5,500.00 | $8,000.00 | $35,000 |
| 41 | Field office, type A (619E16000) | MNTH | 2 | $100.00 | $2,200.00 | $1,000.00 | $100.00 |
| 42 | Construction layout stakes and surveying (623E10000) | LS | 1 | $1,500.00 | $5,500.00 | $25,000 | $25,000 |
| 43 | Mobilization (624E10000) | LS | 1 | $14,500 | $40,000 | $75,000 | $55,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 12, 2026. Compiled by Mirage Metrics.