SCDOT contract 2970300 bid tabulation
S-47 bridge replacement over Baskins Crk. Let by South Carolina DOT on September 9, 2025, Lancaster, District 4. 5 bids received; low bid $1,999,395 by Reeves Construction Company.
- Owner
- South Carolina DOT
- Letting
- 09 SEP 2025
- Pay items
- 80
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Reeves Construction Company | $1,999,395 | Low |
| 2 | Dane Construction, LLC | $2,054,054 | +3.0% |
| 3 | Aos Specialty Contractors, Inc. | $2,181,663 | +9.0% |
| 4 | Eagle Construction Company | $2,231,653 | +12% |
| 5 | Lowcountry Sitework, LLC | $2,454,000 | +23% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Reeves Construction Company | 2. Dane Construction, LLC | 3. Aos Specialty Contractors, Inc. | 4. Eagle Construction Company | 5. Lowcountry Sitework, LLC |
|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $100,000 | $102,700 | $203,483 | $36,000 | $150,000 |
| 0020 | Mobilization - subcontractor (1031100) | LS | 1 | $80,000 | $102,700 | $32,467 | $61,000 | $67,134 |
| 0030 | Bonds and insurance (1032010) | LS | 1 | $60,000 | $41,080 | $32,379 | $24,000 | $75,000 |
| 0040 | Construction stakes, lines & grades (1050800) | EACH | 1 | $30,000 | $25,500 | $39,625 | $33,000 | $30,000 |
| 0050 | CPM progress schedule (1080300) | LS | 1 | $500.00 | $20,000 | $39,874 | $3,500.00 | $10,000 |
| 0060 | Clearing & grubbing within right of way (2011000) | LS | 1 | $70,000 | $12,500 | $33,879 | $61,500 | $25,000 |
| 0070 | Removal & disposal item no. 01 (2022000) | LS | 1 | $7,500.00 | $1,500.00 | $5,127.00 | $4,500.00 | $10,000 |
| 0080 | Removal & disposal of existing bridge (2028100) | LS | 1 | $150,000 | $136,045 | $191,582 | $120,000 | $100,000 |
| 0090 | Unclassified excavation (2031000) | CY | 427 | $65.00 | $28.50 | $57.00 | $60.00 | $70.00 |
| 0100 | Borrow excavation (2033000) | CY | 2,757 | $50.00 | $34.50 | $59.00 | $76.00 | $55.00 |
| 0110 | Muck excavation (2034000) | CY | 100 | $100.00 | $28.50 | $74.00 | $40.00 | $65.00 |
| 0120 | Fine grading (2081001) | SY | 1,665 | $25.00 | $10.00 | $11.00 | $2.00 | $12.00 |
| 0130 | Flowable fill (2103000) | CY | 10 | $500.00 | $750.00 | $1,238.00 | $475.00 | $250.00 |
| 0140 | Graded aggregate base course (8" uniform) (3050108) | SY | 120 | $45.00 | $35.00 | $110.00 | $56.00 | $75.00 |
| 0150 | Maintenance stone (3059900) | TON | 30 | $125.00 | $78.50 | $163.00 | $49.50 | $150.00 |
| 0160 | Prime coat (4010005) | GAL | 18 | $5.50 | $150.00 | $141.00 | $250.00 | $6.00 |
| 0170 | Liquid asphalt binder PG64-22 (4011004) | TON | 52 | $763.00 | $795.65 | $994.00 | $750.00 | $575.00 |
| 0180 | Milling existing asphalt pavement 1.5" (4013115) | SY | 305 | $32.00 | $26.37 | $28.00 | $55.00 | $20.00 |
| 0190 | Milling existing asphalt pavement (variable) (4013990) | SY | 400 | $32.00 | $21.50 | $23.00 | $44.00 | $20.00 |
| 0200 | Asphalt base course - type B (4020320) | TON | 613 | $135.00 | $147.61 | $133.00 | $210.00 | $200.00 |
| 0210 | Asphalt intermediate course type C (4030330) | TON | 195 | $143.00 | $153.87 | $130.00 | $300.00 | $200.00 |
| 0220 | Asphalt surface course type C (4040340) | TON | 209 | $143.00 | $138.48 | $130.00 | $300.00 | $200.00 |
| 0230 | Asphalt surface course type E (4040360) | TON | 5 | $800.00 | $810.70 | $130.00 | $500.00 | $200.00 |
| 0240 | Traffic control (6011000) | LS | 1 | $25,000 | $12,500 | $22,891 | $36,000 | $15,000 |
| 0250 | Barricade - type III (6041200) | LF | 84 | $22.00 | $22.00 | $24.00 | $60.00 | $45.00 |
| 0260 | Permanent construction signs (ground mounted) (6051120) | SF | 128 | $7.00 | $7.00 | $9.00 | $12.00 | $25.00 |
| 0270 | Permanent construction signs (barricade mounted) (6051125) | SF | 70 | $7.00 | $7.00 | $9.00 | $15.00 | $25.00 |
| 0280 | Type B - flashing light (608100B) | EACH | 16 | $200.00 | $150.00 | $141.00 | $150.00 | $100.00 |
| 0290 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 1,640 | $1.50 | $1.50 | $1.70 | $1.80 | $1.50 |
| 0300 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 1,640 | $1.50 | $1.50 | $1.70 | $1.80 | $1.50 |
| 0310 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 21 | $7.50 | $7.50 | $8.50 | $10.00 | $15.00 |
| 0320 | Milled-in rumble strip (6321000) | MI | 0.50 | $500.00 | $500.00 | $2,823.00 | $15,000 | $20,000 |
| 0330 | Pref.flex.retro.PVMT.mark(T- 1)perm.(60MIL)4"WH.solid (6351150) | LF | 170 | $5.00 | $5.00 | $5.60 | $6.00 | $7.50 |
| 0340 | Pref.flex.retro.PVMT.mark(T- 1)perm.(60MIL)4"yel.sol. (6351450) | LF | 170 | $5.00 | $5.00 | $5.60 | $6.00 | $7.50 |
| 0350 | Flat sheet, type III, fixed SZ. & MSG. sign (6510105) | SF | 18 | $13.00 | $13.00 | $30.00 | $50.00 | $55.00 |
| 0360 | U-section post for sign supports - 3P (6531210) | LF | 54 | $7.50 | $7.50 | $17.00 | $20.00 | $40.00 |
| 0370 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 504 | $35.00 | $16.00 | $28.00 | $25.00 | $16.50 |
| 0380 | Conc. for structures - class 4000 (7011400) | CY | 201.50 | $1,500.00 | $1,950.00 | $1,241.00 | $1,550.00 | $2,500.00 |
| 0390 | Grooved surface finish (7023200) | SY | 243 | $40.00 | $12.50 | $35.00 | $35.00 | $45.00 |
| 0400 | Reinf. steel for structures (bridge) (7031200) | LB | 53,308 | $1.75 | $2.00 | $2.12 | $3.00 | $1.50 |
| 0410 | Prestressed conc. beam (type III) (7043000) | LF | 419.20 | $540.00 | $740.00 | $509.00 | $650.00 | $400.00 |
| 0420 | 42" MASH concrete barrier parapet/railing wall (7051050) | LF | 250 | $150.00 | $150.00 | $202.00 | $195.00 | $250.00 |
| 0430 | Pile driving set-UP (7110010) | EACH | 10 | $650.00 | $4,100.00 | $6,384.00 | $5,300.00 | $16,500 |
| 0440 | Reinf. pile tips (HP12 X 53) (7111520) | EACH | 10 | $225.00 | $550.00 | $400.00 | $270.00 | $150.00 |
| 0450 | Steel H bearing piling (HP12 X 53) (7112140) | LF | 426 | $75.00 | $50.00 | $59.00 | $95.00 | $50.00 |
| 0460 | 18" RC pipe cul.-class V (7141133) | LF | 56 | $305.00 | $82.50 | $227.00 | $111.00 | $300.00 |
| 0470 | Cleaning existing pipe (7149999) | LF | 50 | $40.00 | $37.00 | $85.00 | $80.00 | $100.00 |
| 0480 | Beveling of pipe end (7199100) | EACH | 2 | $500.00 | $250.00 | $1,427.00 | $1,000.00 | $2,000.00 |
| 0490 | 4' slope flume (6" curb style with cutoffs) (7199200) | LF | 74 | $300.00 | $260.00 | $335.00 | $325.00 | $350.00 |
| 0500 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 132 | $75.00 | $48.00 | $108.00 | $59.00 | $90.00 |
| 0510 | Elastomeric bearing (7243100) | EACH | 10 | $400.00 | $500.00 | $610.00 | $590.00 | $500.00 |
| 0520 | Waterproofing (7282000) | SY | 22.80 | $175.00 | $120.00 | $133.00 | $60.00 | $225.00 |
| 0530 | Aggregate underdrain (aggr.no. 57) (8011300) | LF | 100 | $75.00 | $110.00 | $203.00 | $90.00 | $200.00 |
| 0540 | 4" perf pipe underdrain W/ geotextile (8021204) | LF | 100 | $15.00 | $38.50 | $32.00 | $90.00 | $20.00 |
| 0550 | Rip-rap (class B) (8041020) | TON | 842 | $80.00 | $125.00 | $86.00 | $75.00 | $200.00 |
| 0560 | Geotextile for erosion control under riprap(class 2)type C (8048210) | SY | 689 | $5.00 | $7.50 | $16.00 | $4.50 | $7.00 |
| 0570 | MT3 leading end treatment TL3 (8051151) | EACH | 4 | $3,200.00 | $3,400.00 | $3,840.00 | $3,500.00 | $3,000.00 |
| 0580 | MGS3 GR standard shoulder (8052100) | LF | 75 | $25.00 | $26.00 | $30.00 | $35.00 | $30.00 |
| 0590 | MTBBC3 MASH thrie-beam barrier connector TL3 (8053253) | EACH | 4 | $2,750.00 | $3,200.00 | $3,614.00 | $3,500.00 | $3,000.00 |
| 0600 | Flume inlet at guardrail (handwork) (8053257) | EACH | 4 | $4,200.00 | $5,000.00 | $5,174.00 | $8,000.00 | $2,500.00 |
| 0610 | Non-mow strip under guardrail (8055250) | SY | 100 | $160.00 | $120.00 | $202.00 | $175.00 | $155.00 |
| 0620 | Barbed wire fence - 6 strands (8062600) | LF | 950 | $30.00 | $18.00 | $21.00 | $45.00 | $18.00 |
| 0630 | Temporary barrier fence (orange) (8068301) | LF | 315 | $4.00 | $2.97 | $3.50 | $6.00 | $6.00 |
| 0640 | Moving item no. 01 (8081000) | LS | 1 | $2,500.00 | $750.00 | $6,101.00 | $750.00 | $12,000 |
| 0650 | Moving item no. 02 (8081000) | LS | 1 | $5,000.00 | $2,500.00 | $11,472 | $3,500.00 | $10,000 |
| 0660 | Right of way marker(rebar and cap) (8091010) | EACH | 11 | $340.00 | $215.00 | $225.00 | $180.00 | $500.00 |
| 0670 | Right of way plat (8091050) | LS | 1 | $5,000.00 | $8,750.00 | $6,211.00 | $4,000.00 | $4,000.00 |
| 0680 | Permanent cover (8100100) | ACRE | 1.50 | $2,000.00 | $1,704.50 | $2,823.00 | $1,850.00 | $1,500.00 |
| 0690 | Temporary cover (8100200) | ACRE | 3 | $1,400.00 | $1,076.02 | $1,863.00 | $1,625.00 | $1,300.00 |
| 0700 | Fertilizer (nitrogen) (8104005) | LB | 150 | $5.00 | $1.82 | $3.39 | $6.00 | $5.00 |
| 0710 | Fertilizer (phosphoric acid) (8104010) | LB | 150 | $5.00 | $1.82 | $3.39 | $6.00 | $5.00 |
| 0720 | Fertilizer (potash) (8104015) | LB | 150 | $5.00 | $1.82 | $3.39 | $6.00 | $5.00 |
| 0730 | Agricultural granular lime (8105005) | LB | 3,000 | $0.12 | $0.95 | $1.25 | $0.60 | $0.50 |
| 0740 | Selective watering (8109050) | GAL | 54,300 | $0.10 | $0.10 | $0.20 | $0.10 | $0.10 |
| 0750 | Mowing (8109901) | ACRE | 9 | $300.00 | $100.00 | $960.00 | $780.00 | $700.00 |
| 0760 | Temporary erosion control blanket (ecb) (8151110) | MSY | 0.53 | $2,000.00 | $2,459.10 | $2,823.00 | $3,000.00 | $2,250.00 |
| 0770 | Silt fence (8153000) | LF | 1,430 | $5.00 | $4.43 | $3.15 | $4.80 | $5.00 |
| 0780 | Cleaning silt basins (8154010) | CY | 270 | $35.50 | $50.00 | $94.00 | $25.00 | $75.00 |
| 0790 | Aggregate no.5 or 57 for erosion control (8156410) | TON | 25 | $150.00 | $84.50 | $78.00 | $67.00 | $150.00 |
| 0800 | Stabilized construction entrance (8156490) | SY | 550 | $23.00 | $14.00 | $15.00 | $29.00 | $40.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of September 9, 2025. Compiled by Mirage Metrics.