SCDOT contract 3856130 bid tabulation
Improve Corridor along SC 4 (Stonewall Jackson St). Let by South Carolina DOT on August 12, 2025, Orangeburg, District 7. 5 bids received; low bid $2,056,234 by Palmetto Sitework Services, LLC.
- Owner
- South Carolina DOT
- Letting
- 12 AUG 2025
- Pay items
- 84
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Palmetto Sitework Services, LLC | $2,056,234 | Low |
| 2 | Site-Prep, Inc. of NC | $2,196,706 | +7.0% |
| 3 | Aos Specialty Contractors, Inc. | $2,241,410 | +9.0% |
| 4 | Palmetto Corp. of Conway | $2,388,658 | +16% |
| 5 | Cherokee, Inc. | $2,541,315 | +24% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Palmetto Sitework Services, LLC | 2. Site-Prep, Inc. of NC | 3. Aos Specialty Contractors, Inc. | 4. Palmetto Corp. of Conway | 5. Cherokee, Inc. |
|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $102,000 | $81,725 | $206,000 | $115,000 | $127,066 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $45,000 | $30,000 | $25,000 | $46,000 | $50,826 |
| 0030 | Railroad insurance 01 (1033000) | LS | 1 | $10,000 | $10,000 | $50,000 | $35,000 | $15,000 |
| 0040 | Construction stakes, lines & grades (1050800) | EACH | 1 | $40,000 | $10,560 | $27,000 | $20,000 | $50,000 |
| 0045 | Large public water relocation no. ____ 001 (1052110) | EACH | 1 | $65,000 | $54,615 | $57,000 | $56,900 | $65,000 |
| 0050 | CPM progress schedule (1080300) | LS | 1 | $13,500 | $6,930.00 | $10,500 | $4,500.00 | $10,000 |
| 0060 | Clearing & grubbing within roadway (2012000) | LS | 1 | $105,000 | $121,000 | $130,000 | $375,000 | $205,000 |
| 0070 | Unclassified excavation (2031000) | CY | 7,416 | $25.48 | $33.00 | $30.25 | $18.75 | $30.00 |
| 0080 | Muck excavation (2034000) | CY | 680 | $65.00 | $53.25 | $57.00 | $35.00 | $35.00 |
| 0090 | Fine grading (2081001) | SY | 9,900 | $3.00 | $7.25 | $4.50 | $3.45 | $6.00 |
| 0100 | Graded aggregate base course (6" uniform) (3050106) | SY | 80 | $56.00 | $54.00 | $25.00 | $52.00 | $85.00 |
| 0110 | Liquid asphalt binder PG64-22 (4011004) | TON | 1 | $780.00 | $500.00 | $1,065.00 | $675.00 | $950.00 |
| 0120 | Asphalt surface course type D (4040350) | TON | 10 | $170.00 | $382.00 | $360.00 | $1,000.00 | $900.00 |
| 0130 | Traffic control (6011000) | LS | 1 | $239,000 | $290,000 | $200,000 | $285,960 | $500,000 |
| 0140 | Permanent construction signs (ground mounted) (6051120) | SF | 152 | $7.70 | $6.00 | $15.00 | $7.40 | $9.75 |
| 0150 | 8" white solid lines thermoplastic - 125 mil. (6271015) | LF | 460 | $5.25 | $3.30 | $6.00 | $5.00 | $6.00 |
| 0160 | 24" white solid lines (stop/diag lines)-thermo.-125 mil (6271025) | LF | 140 | $15.75 | $11.00 | $17.00 | $15.00 | $16.50 |
| 0170 | Railroad crossing symbols - thermoplastic - 125 mil. (6271045) | EACH | 2 | $682.50 | $550.00 | $735.00 | $650.00 | $800.00 |
| 0180 | Flat sheet, type III, fixed SZ. & MSG. sign (6510105) | SF | 70 | $28.35 | $55.00 | $34.00 | $50.00 | $60.00 |
| 0190 | Flat sheet, type III, size determined by MSG (6510106) | SF | 60 | $52.50 | $55.00 | $36.00 | $27.00 | $88.00 |
| 0200 | F&I mounting assembly for F.S. sign erctd on mast arm (6513020) | EACH | 2 | $367.50 | $385.00 | $450.00 | $350.00 | $340.00 |
| 0210 | Furnish & install 1.0" schedule 80 PVC conduit (6750275) | LF | 250 | $11.55 | $12.10 | $20.00 | $11.00 | $22.00 |
| 0220 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 535 | $15.75 | $16.50 | $20.50 | $15.00 | $20.00 |
| 0230 | Furnish & install 3.0" schedule 80 PVC conduit (675027C) | LF | 45 | $16.80 | $17.60 | $27.25 | $16.00 | $89.00 |
| 0240 | Furnish & install 2" schedule 80 HDPE conduit (directional bored) (6760065) | LF | 990 | $31.50 | $33.00 | $34.00 | $30.00 | $40.00 |
| 0250 | Furnish & install no. 14 copper wire, 4 conductor - black (6770388) | LF | 270 | $3.41 | $3.58 | $5.50 | $3.25 | $6.00 |
| 0260 | Furnish & install no. 14 copper wire, 4 conductor - gray (6770389) | LF | 1,265 | $3.41 | $3.58 | $5.75 | $3.25 | $6.00 |
| 0270 | Furnish & install no. 14 copper wire, 8 conductor (black) (6770393) | LF | 1,045 | $4.73 | $4.95 | $6.25 | $4.50 | $7.00 |
| 0280 | Furnish & instl no. 14 copper wire,1-conductor for loop wire (6770413) | LF | 2,005 | $0.79 | $0.83 | $1.50 | $0.75 | $1.36 |
| 0290 | Furnish & install fiber optic interconnect center (6770476) | EACH | 1 | $3,675.00 | $3,850.00 | $3,280.00 | $3,500.00 | $4,000.00 |
| 0300 | Sawcut for loop detector (6780495) | LF | 715 | $7.88 | $8.25 | $10.00 | $7.50 | $13.00 |
| 0310 | Furnish & install electrical service for traffic signal (6800499) | EACH | 1 | $2,625.00 | $2,750.00 | $1,870.00 | $2,500.00 | $1,900.00 |
| 0320 | F&I-13"X24"X18"D.elec.flush undgrd.enclos- (STR.poly.conc.)HD (6800518) | EACH | 7 | $682.50 | $715.00 | $905.00 | $650.00 | $950.00 |
| 0330 | F&I-17"X30"X24"D.elec.flush undgrd.enclos- (STR.poly.conc.)HD (680052C) | EACH | 1 | $971.78 | $1,018.05 | $1,190.00 | $925.50 | $1,200.00 |
| 0340 | Furnish & install 4' break- away aluminum pedestal pole (6825480) | EACH | 2 | $1,050.00 | $1,100.00 | $1,100.00 | $1,000.00 | $1,800.00 |
| 0350 | F&I - contr 332/336 cabinet assembly - base mounted 002 (6845511) | EACH | 1 | $26,250 | $27,500 | $20,950 | $25,000 | $28,000 |
| 0360 | Furnish & install - 12" 3 (6865723) | EACH | 8 | $1,575.00 | $1,650.00 | $960.00 | $1,500.00 | $1,800.00 |
| 0370 | F&I - countdown pedestrian signal head (6865781) | EACH | 4 | $787.50 | $825.00 | $990.00 | $750.00 | $1,200.00 |
| 0380 | F&I-ped push button micro assembly(9"X15")and sign(R-10- 3E or R10-4A) (6865794) | EACH | 4 | $525.00 | $550.00 | $850.00 | $500.00 | $400.00 |
| 0390 | Backplate W/ retrorefl.borders for traff. sig. (6865834) | EACH | 8 | $315.00 | $330.00 | $335.00 | $300.00 | $380.00 |
| 0400 | Removal,salvage,&disp.of existing traf. signal equipment (6885990) | LS | 1 | $10,500 | $11,000 | $4,525.00 | $10,000 | $6,000.00 |
| 0410 | Temporary adjustment of traffic signal equipment (6885993) | EACH | 1 | $2,625.00 | $2,750.00 | $5,095.00 | $2,500.00 | $4,000.00 |
| 0420 | Furnish & install concrete cabinet foundation (6887951) | EACH | 1 | $1,575.00 | $1,650.00 | $1,530.00 | $1,500.00 | $1,800.00 |
| 0430 | Furnish & install factory terminated patch panel (6888082) | EACH | 1 | $2,100.00 | $2,200.00 | $3,200.00 | $2,000.00 | $3,200.00 |
| 0440 | Design, furnish & install steel pole with twin mast arms including foundation 004 (6888177) | EACH | 2 | $110,250 | $115,500 | $75,000 | $105,000 | $75,000 |
| 0450 | Straight headwall for 24" circular pipe-1 line (7016135) | EACH | 1 | $4,640.00 | $3,300.00 | $3,930.00 | $3,990.00 | $3,000.00 |
| 0460 | Straight headwall for 36" circular pipe-1 line (7016155) | EACH | 1 | $5,700.00 | $4,665.00 | $7,085.00 | $7,790.00 | $4,000.00 |
| 0470 | Straight headwall for 48" circular pipe-1 line (7016175) | EACH | 1 | $7,700.00 | $7,200.00 | $10,175 | $8,660.00 | $7,500.00 |
| 0480 | 18" R. C. pipe cul. beveled end sectn-CL 3 (7142513) | EACH | 2 | $1,700.00 | $150.00 | $1,330.00 | $2,425.00 | $1,000.00 |
| 0490 | 24" R. C. pipe cul. beveled end sectn-CL 3 (7142514) | EACH | 3 | $1,900.00 | $150.00 | $1,800.00 | $3,735.00 | $1,000.00 |
| 0500 | 36" R. C. pipe cul. beveled end sectn-CL 3 (7142516) | EACH | 1 | $2,800.00 | $275.00 | $3,400.00 | $4,825.00 | $1,000.00 |
| 0510 | 18" smooth wall pipe (7143618) | LF | 16 | $158.00 | $140.00 | $136.00 | $242.00 | $200.00 |
| 0520 | 24" smooth wall pipe (7143624) | LF | 100 | $130.00 | $130.00 | $116.00 | $198.00 | $135.00 |
| 0530 | 30" smooth wall pipe (7143630) | LF | 380 | $178.00 | $161.00 | $148.00 | $215.00 | $225.00 |
| 0540 | 36" smooth wall pipe (7143636) | LF | 12 | $215.00 | $288.00 | $517.00 | $733.00 | $630.00 |
| 0550 | 48" smooth wall pipe (7143648) | LF | 8 | $510.00 | $475.00 | $1,325.00 | $649.00 | $850.00 |
| 0560 | Drop inlet (24" X 36") (7192020) | EACH | 5 | $6,500.00 | $4,950.00 | $7,880.00 | $6,670.00 | $6,000.00 |
| 0570 | Concrete sidewalk(6" uniform) (7204600) | SY | 5,740 | $75.00 | $81.40 | $90.75 | $74.25 | $80.00 |
| 0580 | Detectable warning material (7204900) | SF | 190 | $45.00 | $44.00 | $50.00 | $45.00 | $60.00 |
| 0590 | Pedestrian ramp construction (7209000) | SY | 380 | $76.00 | $140.80 | $107.00 | $143.50 | $145.00 |
| 0600 | Rip-rap (class B) (8041020) | TON | 57 | $110.00 | $140.00 | $130.00 | $349.50 | $150.00 |
| 0610 | Geotextile for erosion control under riprap(class 2)type C (8048210) | SY | 87 | $2.50 | $4.00 | $9.00 | $60.00 | $10.00 |
| 0620 | MT2 leading end treatment TL2 (8051155) | EACH | 1 | $3,700.00 | $3,904.00 | $4,100.00 | $4,200.00 | $4,000.00 |
| 0630 | MB trailing end treatment (8051710) | EACH | 1 | $2,625.00 | $2,750.00 | $2,900.00 | $2,500.00 | $3,000.00 |
| 0640 | MGS3 GR standard shoulder (8052100) | LF | 25 | $42.00 | $44.00 | $45.00 | $40.00 | $44.00 |
| 0645 | Temporary barrier fence (orange) (8068301) | LF | 350 | $3.20 | $3.30 | $6.00 | $3.06 | $4.00 |
| 0650 | Right of way marker(rebar and cap) (8091010) | EACH | 8 | $210.00 | $220.00 | $400.00 | $100.00 | $225.00 |
| 0660 | Right of way plat (8091050) | LS | 1 | $4,200.00 | $4,400.00 | $4,000.00 | $4,700.00 | $6,000.00 |
| 0670 | Permanent cover (8100100) | ACRE | 3.26 | $1,847.00 | $1,936.00 | $2,375.00 | $1,765.49 | $1,800.00 |
| 0680 | Temporary cover (8100200) | ACRE | 1.63 | $1,159.00 | $1,215.00 | $2,150.00 | $1,107.59 | $1,400.00 |
| 0690 | Compost (8101105) | CY | 881.26 | $21.00 | $22.00 | $60.00 | $10.00 | $38.00 |
| 0700 | Straw or hay mulch with tackifier (8101110) | ACRE | 9.79 | $3,500.00 | $3,684.00 | $1,900.00 | $3,359.71 | $1,550.00 |
| 0710 | Fertilizer (nitrogen) (8104005) | LB | 326.39 | $2.00 | $2.20 | $2.00 | $1.96 | $5.00 |
| 0720 | Fertilizer (phosphoric acid) (8104010) | LB | 326.39 | $2.00 | $2.20 | $2.00 | $1.96 | $5.00 |
| 0730 | Fertilizer (potash) (8104015) | LB | 326.39 | $2.00 | $2.20 | $2.00 | $1.96 | $5.00 |
| 0740 | Agricultural granular lime (8105005) | LB | 6,527.87 | $1.00 | $1.10 | $0.50 | $1.96 | $0.50 |
| 0750 | Selective watering (8109050) | GAL | 54,300 | $0.01 | $0.01 | $0.15 | $0.09 | $0.05 |
| 0760 | Mowing (8109901) | ACRE | 9.79 | $1,510.00 | $1,583.00 | $700.00 | $1,630.43 | $450.00 |
| 0770 | Temporary erosion control blanket (ecb) (8151110) | MSY | 3.22 | $2,560.00 | $2,688.00 | $1,870.00 | $2,449.97 | $2,000.00 |
| 0780 | Hydraulic erosion control product (hecp) - type 3 (8151203) | ACRE | 10 | $3,955.00 | $4,144.00 | $2,950.00 | $3,779.27 | $3,200.00 |
| 0790 | Sediment tubes for ditch checks (8152007) | LF | 365 | $12.00 | $9.25 | $9.00 | $11.29 | $14.00 |
| 0800 | Silt fence (8153000) | LF | 1,400 | $4.80 | $3.80 | $6.00 | $2.44 | $5.00 |
| 0810 | Cleaning inlet structure filters (8156200) | EACH | 10 | $300.00 | $182.50 | $295.00 | $250.00 | $200.00 |
| 0820 | Stabilized construction entrance (8156490) | SY | 550 | $14.00 | $27.00 | $8.00 | $38.00 | $20.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of August 12, 2025. Compiled by Mirage Metrics.