SCDOT contract 3872110 bid tabulation
Orangeburg SC 389 @ SC 394 Int. Improvement. Let by South Carolina DOT on April 14, 2026, Orangeburg, District 7. 6 bids received; low bid $2,038,982 by Aos Specialty Contractors, Inc..
- Owner
- South Carolina DOT
- Letting
- 14 APR 2026
- Pay items
- 77
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Aos Specialty Contractors, Inc. | $2,038,982 | Low |
| 2 | Site-Prep, Inc. of NC | $2,065,366 | +1.0% |
| 3 | Satterfield Construction Company, Inc. | $2,389,908 | +17% |
| 4 | Palmetto Sitework Services, LLC | $2,746,089 | +35% |
| 5 | Cherokee, Inc. | $2,820,486 | +38% |
| 6 | Palmetto Corp. of Conway | $3,131,044 | +54% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Aos Specialty Contractors, Inc. | 2. Site-Prep, Inc. of NC | 3. Satterfield Construction Company, Inc. | 4. Palmetto Sitework Services, LLC | 5. Cherokee, Inc. | 6. Palmetto Corp. of Conway |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $138,701 | $104,725 | $110,000 | $245,000 | $141,024 | $135,000 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $28,871 | $28,500 | $45,000 | $82,000 | $56,410 | $60,000 |
| 0030 | Construction stakes, lines & grades (1050800) | EACH | 1 | $17,654 | $12,725 | $85,000 | $124,000 | $50,000 | $41,000 |
| 0040 | CPM progress schedule (1080300) | LS | 1 | $17,178 | $10,780 | $22,000 | $44,500 | $15,500 | $6,000.00 |
| 0050 | Clearing & grubbing within right of way (2011000) | LS | 1 | $54,860 | $46,054 | $51,500 | $155,000 | $200,000 | $295,000 |
| 0060 | Removal & disposal of existing pavement (2023000) | SY | 150 | $142.00 | $12.54 | $41.00 | $65.00 | $35.00 | $77.75 |
| 0070 | Unclassified excavation (2031000) | CY | 1,883 | $38.00 | $19.25 | $65.00 | $39.00 | $60.00 | $78.00 |
| 0080 | Borrow excavation (2033000) | CY | 3,373 | $26.00 | $39.57 | $52.00 | $50.00 | $35.00 | $78.50 |
| 0090 | Muck excavation (2034000) | CY | 190 | $77.00 | $29.60 | $65.00 | $61.00 | $45.00 | $63.85 |
| 0100 | Fine grading (2081001) | SY | 3,930 | $8.00 | $9.89 | $8.60 | $7.00 | $22.00 | $8.70 |
| 0110 | Maintenance stone (3059900) | TON | 25 | $117.00 | $100.00 | $85.00 | $90.00 | $70.00 | $265.00 |
| 0120 | Liquid asphalt binder PG64-22 (4011004) | TON | 172 | $1,031.00 | $871.25 | $815.00 | $880.00 | $897.00 | $800.00 |
| 0130 | Milling existing asphalt pavement (variable) (4013990) | SY | 7,110 | $7.00 | $7.95 | $6.40 | $8.10 | $8.25 | $14.35 |
| 0140 | Asphalt base course - type A (4020310) | TON | 1,720 | $112.00 | $122.96 | $116.00 | $125.00 | $128.00 | $151.80 |
| 0150 | Asphalt intermediate course type B (4030320) | TON | 300 | $112.00 | $121.90 | $115.00 | $124.00 | $127.00 | $294.50 |
| 0160 | Asphalt surface course type B (4040320) | TON | 860 | $112.00 | $112.36 | $106.00 | $114.00 | $117.00 | $178.00 |
| 0170 | Asphalt surface course type E (4040360) | TON | 500 | $112.00 | $124.02 | $117.00 | $126.00 | $129.00 | $166.50 |
| 0180 | Driveway paving-surface type C (4047220) | TON | 10 | $260.00 | $323.30 | $305.00 | $328.00 | $336.00 | $675.00 |
| 0190 | Stained concrete pavement (8" uniform) (5019010) | SY | 610 | $184.00 | $204.50 | $257.00 | $211.50 | $210.00 | $158.00 |
| 0200 | Traffic control (6011000) | LS | 1 | $199,777 | $189,900 | $225,000 | $295,000 | $528,000 | $420,000 |
| 0210 | Permanent construction signs (ground mounted) (6051120) | SF | 310 | $8.50 | $7.12 | $7.55 | $7.50 | $9.00 | $6.00 |
| 0220 | Pavement markings (temporary paint) 24"X36" white triangle yield bar (609138A) | LF | 128 | $2.00 | $2.20 | $5.75 | $5.60 | $5.50 | $5.00 |
| 0230 | 4" white solid lines (PVT. edge lines)-fast dry paint (6240010) | LF | 4,860 | $0.16 | $0.17 | $0.17 | $0.17 | $0.20 | $0.15 |
| 0240 | 8"white solid lines (crosswalk& channelization)fast dry paint (6240015) | LF | 460 | $0.52 | $0.55 | $0.17 | $0.17 | $0.20 | $0.15 |
| 0250 | 4"yellow solid line(PVT.edge&no passing zone)-fast dry paint (6240110) | LF | 8,140 | $0.16 | $0.17 | $0.17 | $0.17 | $0.20 | $0.15 |
| 0260 | 6"yel solid lines on 6"conc.curb(top&side)-fast dry PNT (6240113) | LF | 1,580 | $1.10 | $1.10 | $0.85 | $0.85 | $1.00 | $0.75 |
| 0270 | 12IN X 18IN white triang. yield bar (gaps exc)perm.PVMT.mark (6251023) | LF | 65 | $10.50 | $11.00 | $17.25 | $16.70 | $20.00 | $15.00 |
| 0280 | 8" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271008) | LF | 50 | $3.75 | $3.85 | $5.75 | $5.60 | $6.00 | $5.00 |
| 0290 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 2,430 | $0.88 | $0.94 | $0.85 | $0.85 | $0.85 | $0.75 |
| 0300 | 8" white solid lines thermoplastic - 125 mil. (6271015) | LF | 230 | $3.75 | $3.85 | $3.40 | $3.30 | $3.30 | $2.95 |
| 0310 | 24IN X 36IN white triang. yield bar (gaps exc)thermo-125MIL (6271024) | LF | 65 | $10.50 | $11.00 | $17.25 | $16.70 | $18.00 | $15.00 |
| 0320 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 4,070 | $0.88 | $0.94 | $0.85 | $0.85 | $0.85 | $0.75 |
| 0330 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 30 | $10.50 | $11.00 | $11.50 | $11.15 | $11.00 | $10.00 |
| 0340 | Flat sheet, type III, fixed SZ. & MSG. sign (6510105) | SF | 310 | $26.00 | $15.44 | $28.75 | $28.90 | $16.00 | $13.00 |
| 0350 | Flat sheet, type III, size determined by MSG (6510106) | SF | 130 | $26.00 | $10.70 | $32.20 | $31.40 | $17.00 | $9.00 |
| 0360 | U-section post for sign supports - 3P (6531210) | LF | 352 | $14.50 | $10.70 | $23.00 | $9.65 | $10.00 | $9.00 |
| 0370 | Reflective sign post panels (6531500) | LF | 352 | $13.50 | $14.26 | $13.80 | $8.50 | $8.00 | $12.00 |
| 0380 | Design & installation of rdwy. lighting electrical system 001 (6581000) | EACH | 1 | $36,890 | $81,375 | $112,930 | $83,500 | $45,000 | $33,500 |
| 0390 | SGL.light STD.35'HT.AL.pole- incl top tenon MT. (6581145) | EACH | 10 | $7,082.00 | $15,590 | $12,420 | $16,125 | $22,000 | $16,500 |
| 0400 | 24" R. C. pipe cul. beveled end sectn-CL 3 (7142514) | EACH | 2 | $2,672.00 | $677.50 | $1,355.65 | $1,600.00 | $850.00 | $2,615.00 |
| 0410 | 30" R. C. pipe cul. beveled end sectn-CL 3 (7142515) | EACH | 4 | $3,756.00 | $677.50 | $1,656.59 | $1,600.00 | $1,200.00 | $2,980.00 |
| 0420 | 42" R. C. pipe cul. beveled end sectn-CL 3 (7142517) | EACH | 2 | $5,311.00 | $948.50 | $2,577.55 | $3,050.00 | $1,600.00 | $3,115.00 |
| 0430 | 24" smooth wall pipe (7143624) | LF | 92 | $227.00 | $155.50 | $185.00 | $365.00 | $260.00 | $249.50 |
| 0440 | 30" smooth wall pipe (7143630) | LF | 172 | $281.00 | $201.00 | $178.00 | $380.00 | $275.00 | $305.50 |
| 0450 | 42" smooth wall pipe (7143642) | LF | 68 | $456.00 | $368.50 | $302.00 | $540.00 | $450.00 | $457.50 |
| 0460 | 4' slope flume (6" curb style with cutoffs) (7199200) | LF | 265 | $95.00 | $193.45 | $228.15 | $190.00 | $186.00 | $326.20 |
| 0470 | Concrete curb (9" X 15") (7201000) | LF | 204 | $70.00 | $56.58 | $56.00 | $47.00 | $46.00 | $63.25 |
| 0480 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 1,730 | $48.00 | $44.90 | $42.46 | $35.00 | $35.00 | $62.05 |
| 0490 | Concrete median (7206000) | SY | 630 | $100.00 | $106.50 | $131.96 | $109.00 | $110.00 | $121.05 |
| 0500 | Rip-rap (class B) (8041020) | TON | 152 | $92.00 | $159.00 | $120.00 | $100.00 | $125.00 | $194.50 |
| 0510 | Geotextile for erosion control under riprap(class 1)type B (8048105) | SY | 113 | $6.50 | $6.77 | $6.00 | $2.50 | $6.00 | $4.70 |
| 0520 | Geotextile for erosion control under riprap(class 2)type C (8048210) | SY | 384 | $6.50 | $6.77 | $6.50 | $2.50 | $6.00 | $2.85 |
| 0530 | Temporary barrier fence (orange) (8068301) | LF | 91 | $3.00 | $2.60 | $3.45 | $7.25 | $5.00 | $2.04 |
| 0540 | Right of way marker(rebar and cap) (8091010) | EACH | 28 | $156.00 | $165.00 | $250.00 | $167.00 | $210.00 | $214.29 |
| 0550 | Right of way plat (8091050) | LS | 1 | $8,850.00 | $3,110.00 | $5,000.00 | $3,200.00 | $6,000.00 | $5,000.00 |
| 0560 | Permanent cover (8100100) | ACRE | 2.72 | $1,405.00 | $1,520.00 | $2,300.00 | $1,512.00 | $1,600.00 | $1,700.00 |
| 0570 | Temporary cover (8100200) | ACRE | 5.44 | $1,770.00 | $958.00 | $1,955.00 | $1,225.00 | $1,000.00 | $1,500.00 |
| 0580 | Compost (8101105) | CY | 734.40 | $72.00 | $5.43 | $31.05 | $34.50 | $6.70 | $22.00 |
| 0590 | Straw or hay mulch with tackifier (8101110) | ACRE | 7.10 | $1,926.00 | $1,942.00 | $3,162.50 | $1,475.00 | $2,100.00 | $1,200.00 |
| 0600 | Seeding - eragrostis curvula - weeping lovegrass (8102520) | MSY | 0.19 | $3,748.00 | $5,425.00 | $4,600.00 | $2,280.00 | $5,500.00 | $35,000 |
| 0610 | Fertilizer (nitrogen) (8104005) | LB | 272 | $2.50 | $2.13 | $2.88 | $4.50 | $2.20 | $2.50 |
| 0620 | Fertilizer (phosphoric acid) (8104010) | LB | 272 | $2.50 | $2.13 | $2.88 | $4.50 | $2.20 | $2.50 |
| 0630 | Fertilizer (potash) (8104015) | LB | 272 | $2.50 | $2.13 | $2.88 | $4.50 | $2.20 | $2.50 |
| 0640 | Agricultural granular lime (8105005) | LB | 5,440 | $0.36 | $2.13 | $2.88 | $0.50 | $2.20 | $0.35 |
| 0650 | Selective watering (8109050) | GAL | 54,300 | $0.04 | $0.13 | $0.12 | $0.10 | $0.09 | $0.05 |
| 0660 | Mowing (8109901) | ACRE | 8.16 | $572.00 | $446.00 | $805.00 | $500.00 | $450.00 | $450.00 |
| 0670 | Landscaping item no. no. 1 (8110003) | EACH | 14 | $182.00 | $2,386.00 | $287.50 | $362.00 | $60.00 | $200.00 |
| 0680 | Double-shredded hardwood mulch (8110220) | SF | 113.10 | $95.00 | $20.90 | $34.50 | $10.00 | $13.50 | $15.00 |
| 0690 | Temporary erosion control blanket (ecb) (8151110) | MSY | 2.68 | $1,927.00 | $2,545.00 | $2,702.50 | $1,780.00 | $2,700.00 | $1,180.00 |
| 0700 | Hydraulic erosion control product (hecp) - type 1 (8151201) | ACRE | 1.88 | $1,770.00 | $1,209.00 | $1,955.00 | $1,475.00 | $1,300.00 | $1,500.00 |
| 0710 | Hydraulic erosion control product (hecp) - type 2 (8151202) | ACRE | 0.20 | $2,030.00 | $2,712.00 | $2,530.00 | $3,950.00 | $3,200.00 | $16,500 |
| 0720 | Hydraulic erosion control product (hecp) - type 3 (8151203) | ACRE | 0.80 | $3,800.00 | $3,700.00 | $4,197.50 | $5,450.00 | $4,000.00 | $4,125.00 |
| 0730 | Sediment tubes for ditch checks (8152007) | LF | 409 | $11.00 | $11.56 | $13.80 | $15.00 | $12.50 | $9.75 |
| 0740 | Silt fence (8153000) | LF | 1,415 | $3.00 | $3.96 | $4.45 | $3.65 | $6.00 | $2.32 |
| 0750 | Replace/repair silt fence (8153090) | LF | 141.50 | $2.75 | $3.96 | $10.00 | $7.50 | $5.00 | $1.60 |
| 0760 | Removal of silt retained by silt fence (8154050) | LF | 355 | $12.00 | $3.95 | $15.00 | $5.00 | $5.00 | $2.00 |
| 0770 | Stabilized construction entrance (8156490) | SY | 550 | $18.00 | $17.00 | $19.20 | $21.00 | $25.00 | $17.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of April 14, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.