SCDOT contract 4071450 bid tabulation
Install sidewalk and bike lane on Bluff Rd. Let by South Carolina DOT on January 14, 2025, Richland, District 1. 6 bids received; low bid $1,633,130 by Aos Specialty Contractors, Inc..
- Owner
- South Carolina DOT
- Letting
- 14 JAN 2025
- Pay items
- 63
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Aos Specialty Contractors, Inc. | $1,633,130 | Low |
| 2 | L-J, Inc. | $1,658,349 | +2.0% |
| 3 | Eagle Construction Company | $1,674,127 | +3.0% |
| 4 | Cherokee, Inc. | $1,714,160 | +5.0% |
| 5 | Palmetto Sitework Services, LLC | $1,745,984 | +7.0% |
| 6 | Palmetto Corp. of Conway | $1,871,637 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Aos Specialty Contractors, Inc. | 2. L-J, Inc. | 3. Eagle Construction Company | 4. Cherokee, Inc. | 5. Palmetto Sitework Services, LLC | 6. Palmetto Corp. of Conway |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $145,000 | $80,000 | $83,000 | $85,708 | $90,000 | $78,000 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $20,000 | $15,150 | $33,000 | $34,283 | $58,500 | $30,500 |
| 0030 | Construction stakes, lines & grades (1050800) | EACH | 1 | $30,500 | $34,650 | $44,000 | $35,000 | $68,100 | $22,000 |
| 0040 | CPM progress schedule (1080300) | LS | 1 | $7,500.00 | $7,750.00 | $2,000.00 | $8,500.00 | $14,700 | $4,500.00 |
| 0050 | Clearing & grubbing within roadway (2012000) | LS | 1 | $17,000 | $192,920 | $62,000 | $95,000 | $82,600 | $210,875 |
| 0060 | Removal & disposal of existing pavement (2023000) | SY | 50 | $30.00 | $42.00 | $15.00 | $35.00 | $50.00 | $78.50 |
| 0070 | Removal & disposal of existing asphalt pavement (2025000) | SY | 100 | $77.50 | $34.50 | $12.00 | $35.00 | $50.00 | $47.80 |
| 0080 | Unclassified excavation (2031000) | CY | 1,242 | $61.00 | $52.00 | $73.00 | $35.00 | $55.00 | $46.20 |
| 0090 | Borrow excavation (2033000) | CY | 712 | $40.00 | $63.50 | $39.50 | $35.00 | $59.00 | $55.90 |
| 0100 | Fine grading (2081001) | SY | 3,736 | $5.25 | $5.75 | $3.00 | $8.00 | $12.00 | $5.75 |
| 0110 | Flowable fill (2103000) | CY | 530 | $135.00 | $175.00 | $285.00 | $325.00 | $250.00 | $260.00 |
| 0120 | Maintenance stone (3059900) | TON | 250 | $55.00 | $68.55 | $50.00 | $50.00 | $75.00 | $85.00 |
| 0130 | Liquid asphalt binder PG64-22 (4011004) | TON | 28 | $950.00 | $1,295.00 | $950.00 | $700.00 | $670.00 | $715.00 |
| 0140 | Milling existing asphalt pavement 1.5" (4013115) | SY | 1,292 | $12.50 | $12.75 | $15.00 | $8.00 | $5.60 | $6.45 |
| 0150 | Asphalt surface course type B (4040320) | TON | 455 | $180.00 | $261.65 | $325.00 | $220.00 | $188.00 | $160.50 |
| 0160 | Driveway paving-surface type D (4047230) | TON | 40 | $180.00 | $375.00 | $625.00 | $300.00 | $245.00 | $289.00 |
| 0170 | Traffic control (6011000) | LS | 1 | $256,000 | $109,184 | $187,000 | $300,000 | $275,000 | $381,500 |
| 0180 | 6" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271007) | LF | 100 | $1.00 | $1.75 | $1.25 | $0.94 | $0.95 | $0.85 |
| 0190 | 6" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271012) | LF | 5,800 | $1.00 | $1.15 | $1.20 | $0.94 | $0.95 | $0.85 |
| 0200 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 6,800 | $0.75 | $0.90 | $0.90 | $0.75 | $0.75 | $0.65 |
| 0210 | White bike symbol - hot applied preformed thermoplastic - 90 mils (6280051) | EACH | 6 | $280.00 | $290.00 | $325.00 | $275.00 | $278.00 | $250.00 |
| 0220 | White bike lane arrow - hot applied preformed thermoplastic - 90 mils (6280052) | EACH | 11 | $175.00 | $175.00 | $200.00 | $165.00 | $167.00 | $150.00 |
| 0230 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 60 | $10.00 | $11.55 | $11.00 | $10.00 | $8.40 | $7.50 |
| 0240 | Flat sheet, type III, fixed SZ. & MSG. sign (6510105) | SF | 22.50 | $35.00 | $35.00 | $35.00 | $30.00 | $30.00 | $22.50 |
| 0250 | U-section post for sign supports - 3P (6531210) | LF | 46 | $12.00 | $17.00 | $20.00 | $12.00 | $10.50 | $12.00 |
| 0260 | 18" smooth wall pipe (7143618) | LF | 928 | $138.00 | $127.50 | $65.50 | $100.00 | $84.50 | $117.50 |
| 0270 | 24" smooth wall pipe (7143624) | LF | 24 | $168.00 | $217.75 | $91.00 | $115.00 | $117.15 | $156.35 |
| 0280 | 30" smooth wall pipe (7143630) | LF | 160 | $240.00 | $206.00 | $130.00 | $210.00 | $136.20 | $182.10 |
| 0290 | Catch basin -type 16 (7191605) | EACH | 11 | $8,700.00 | $7,050.00 | $9,000.00 | $7,500.00 | $9,000.00 | $6,500.00 |
| 0300 | Drop inlet (24" X 36") (7192020) | EACH | 1 | $5,800.00 | $4,550.00 | $8,000.00 | $4,000.00 | $8,000.00 | $4,600.00 |
| 0310 | Manhole (7192105) | EACH | 2 | $6,000.00 | $5,045.00 | $8,700.00 | $6,000.00 | $6,100.00 | $4,800.00 |
| 0320 | 30" X 30" junction box (7192225) | EACH | 1 | $7,300.00 | $5,045.00 | $8,000.00 | $5,500.00 | $5,750.00 | $5,300.00 |
| 0330 | Beveling of pipe end (7199100) | EACH | 22 | $1,100.00 | $425.00 | $800.00 | $500.00 | $560.00 | $390.00 |
| 0340 | 4' slope flume (6" curb style with cutoffs) (7199200) | LF | 8 | $285.00 | $245.00 | $550.00 | $418.00 | $112.00 | $697.20 |
| 0350 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 3,020 | $37.00 | $44.00 | $44.00 | $38.00 | $28.75 | $36.80 |
| 0360 | Concrete sidewalk(4" uniform) (7204100) | SY | 1,350 | $70.00 | $80.85 | $83.00 | $66.00 | $73.50 | $63.30 |
| 0370 | Detectable warning material (7204900) | SF | 100 | $45.00 | $48.50 | $50.00 | $55.00 | $72.50 | $40.00 |
| 0380 | Concrete driveway(6" uniform) (7205000) | SY | 396 | $120.00 | $93.50 | $102.00 | $80.00 | $126.00 | $149.50 |
| 0390 | Pedestrian ramp construction (7209000) | SY | 200 | $145.00 | $140.00 | $165.00 | $175.00 | $115.60 | $148.40 |
| 0400 | Rip-rap (class B) (8041020) | TON | 824 | $100.00 | $95.00 | $67.50 | $85.00 | $103.80 | $135.00 |
| 0410 | Geotextile for erosion control under riprap(class 2)type C (8048210) | SY | 1,032 | $0.50 | $7.00 | $4.00 | $5.00 | $5.00 | $4.00 |
| 0420 | Temporary barrier fence (orange) (8068301) | LF | 2,000 | $4.00 | $5.75 | $4.00 | $4.25 | $2.10 | $1.80 |
| 0430 | Right of way marker(rebar and cap) (8091010) | EACH | 28 | $175.00 | $205.00 | $170.00 | $200.00 | $170.00 | $71.43 |
| 0440 | Right of way plat (8091050) | LS | 1 | $5,900.00 | $5,195.00 | $3,000.00 | $7,000.00 | $5,000.00 | $2,000.00 |
| 0450 | Permanent cover (8100100) | ACRE | 1.37 | $2,200.00 | $1,735.00 | $1,900.00 | $1,600.00 | $1,950.00 | $1,700.00 |
| 0460 | Temporary cover (8100200) | ACRE | 0.68 | $1,900.00 | $2,655.00 | $3,000.00 | $2,200.00 | $1,560.00 | $2,200.00 |
| 0470 | Fertilizer (nitrogen) (8104005) | LB | 136.50 | $1.00 | $5.75 | $6.50 | $5.50 | $3.50 | $2.50 |
| 0480 | Fertilizer (phosphoric acid) (8104010) | LB | 136.50 | $1.00 | $5.75 | $6.50 | $5.50 | $3.50 | $2.50 |
| 0490 | Fertilizer (potash) (8104015) | LB | 136.50 | $1.00 | $5.75 | $6.50 | $5.50 | $3.50 | $2.50 |
| 0500 | Agricultural granular lime (8105005) | LB | 2,730 | $0.25 | $0.50 | $0.80 | $0.45 | $0.40 | $0.35 |
| 0510 | Selective watering (8109050) | GAL | 54,300 | $0.08 | $0.10 | $0.09 | $0.09 | $0.03 | $0.05 |
| 0520 | Mowing (8109901) | ACRE | 4.10 | $675.00 | $535.00 | $600.00 | $450.00 | $850.00 | $450.00 |
| 0530 | Hydraulic erosion control product (hecp) - type 1 (8151201) | ACRE | 0.63 | $3,200.00 | $2,425.00 | $2,700.00 | $2,250.00 | $2,120.00 | $2,400.00 |
| 0540 | Hydraulic erosion control product (hecp) - type 3 (8151203) | ACRE | 3.47 | $3,600.00 | $3,465.00 | $3,900.00 | $3,300.00 | $4,280.00 | $3,300.00 |
| 0550 | Inlet structure filter - type F (weighted) (8152004) | LF | 112 | $20.00 | $17.00 | $13.00 | $12.50 | $18.50 | $16.25 |
| 0560 | Inlet structure filter- type F (non-weighted) (8152006) | LF | 80 | $15.00 | $14.00 | $13.00 | $12.00 | $12.80 | $4.56 |
| 0570 | Sediment tubes for ditch checks (8152007) | LF | 110 | $10.00 | $14.00 | $12.00 | $12.00 | $13.90 | $9.75 |
| 0580 | Silt fence (8153000) | LF | 6,401 | $5.00 | $3.50 | $3.50 | $5.00 | $2.85 | $2.32 |
| 0590 | Replace/repair silt fence (8153090) | LF | 641 | $6.00 | $4.65 | $8.00 | $5.00 | $2.25 | $1.60 |
| 0600 | Cleaning silt basins (8154010) | CY | 90 | $6.25 | $26.30 | $40.00 | $15.00 | $83.50 | $58.40 |
| 0610 | Removal of silt retained by silt fence (8154050) | LF | 1,601 | $6.50 | $4.75 | $5.00 | $5.00 | $13.90 | $3.15 |
| 0620 | Inlet filter cleaning (8154155) | EACH | 11 | $175.00 | $455.00 | $250.00 | $175.00 | $335.00 | $263.00 |
| 0630 | Stabilized construction entrance (8156490) | SY | 550 | $6.00 | $13.50 | $26.00 | $23.00 | $15.50 | $28.45 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of January 14, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.