TDOT contract CNZ227 bid tabulation
The repair of bridges on i-269 over s.r. 57 (l.m. 1.23). Let by Tennessee DOT on August 15, 2025, Fayette County. 2 bids received; low bid $2,412,206 by Dement Construction Group, LLC.
- Owner
- Tennessee DOT
- Letting
- 15 AUG 2025
- Pay items
- 50
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Dement Construction Group, LLC | $2,412,206 | Low |
| 2 | Bell & Associates Construction, LLC | $2,633,669 | +9.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Dement Construction Group, LLC | 2. Bell & Associates Construction, LLC |
|---|---|---|---|---|---|
| 1 | Removal of asphalt pavement (202-03.01) | SY | 225 | $50.00 | $20.00 |
| 2 | Removal of structures (pavement and bridge ends) (202-04.01) | LS | 1 | $133,500 | $218,250 |
| 3 | Dry excavation (bridges) (204-02.01) | CY | 1,224 | $30.00 | $50.00 |
| 4 | Flowable fill (general) (204-06.01) | CY | 7 | $1,000.00 | $800.00 |
| 5 | Foundation fill material (204-08) | CY | 1,964 | $80.00 | $100.00 |
| 6 | Temporary silt fence (with backing) (209-08.02) | LF | 258 | $10.00 | $10.50 |
| 7 | Mineral aggregate (#57) (303-10.04) | TON | 1,775 | $55.00 | $100.00 |
| 8 | Treated permeable base (313-03) | SY | 450 | $114.50 | $115.00 |
| 9 | Saw cutting asphalt pavement (407-20.05) | LF | 81 | $50.00 | $5.00 |
| 10 | Concrete pavement removal (502-03.13) | SY | 225 | $200.00 | $60.00 |
| 11 | Full depth PCC pavement repair (502-03.20) | CY | 125 | $1,000.00 | $700.00 |
| 12 | Sawing concrete pavement (full depth) (502-04.01) | LF | 81 | $30.00 | $30.00 |
| 13 | Load transfer dowels (502-04.02) | EACH | 288 | $40.00 | $40.00 |
| 14 | Resealing joints (hot poured elastic) (502-08.01) | LF | 486 | $10.00 | $25.00 |
| 15 | Epoxy coated reinforcing steel (604-02.03) | LB | 4,594 | $3.00 | $6.50 |
| 16 | Pavement @ bridge ends (604-03.04) | SY | 451 | $500.00 | $525.00 |
| 17 | Class A concrete (wingwalls) (604-03.07) | CY | 16 | $1,500.00 | $3,150.00 |
| 18 | Bridge end drains(2'X8') (604-04.03) | EACH | 2 | $5,000.00 | $7,250.00 |
| 19 | Bridge deck grooving (mechanical) (604-05.31) | SY | 427 | $40.00 | $40.00 |
| 20 | Concrete (604-10.05) | SF | 5 | $1,500.00 | $1,750.00 |
| 21 | Bridge deck repairs (partial depth of slab) (604-10.50) | SY | 5 | $1,000.00 | $1,250.00 |
| 22 | Drill & grout steel bars (604-12.15) | EACH | 80 | $50.00 | $40.00 |
| 23 | Bridge deck drains (610-10.40) | LS | 1 | $2,000.00 | $2,500.00 |
| 24 | Type 1 thin epoxy overlay (epoxy-urethane) (617-04.01) | SY | 4,302 | $33.60 | $35.00 |
| 25 | Concrete parapet (at wingwalls) (620-03.10) | LF | 96 | $450.00 | $450.00 |
| 26 | Removal of guardrail & post for reuse (706-10.73) | LF | 120 | $30.00 | $70.00 |
| 27 | Rubble stone rip-rap (grouted) (709-02.01) | CY | 2 | $300.00 | $1,700.00 |
| 28 | Machined rip-rap (class A-3) (709-05.05) | TON | 80 | $80.00 | $150.00 |
| 29 | Machined rip-rap (class B) (709-05.08) | TON | 1,403 | $80.00 | $100.00 |
| 30 | Traffic control (712-01) | LS | 1 | $150,000 | $85,000 |
| 31 | Portable barrier rail (MASH TL-3) (712-02.10) | LF | 360 | $50.00 | $70.00 |
| 32 | Portable barrier rail, reduced deflection (MASH TL-3) (712-02.12) | LF | 1,078 | $100.00 | $85.00 |
| 33 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 1 | $6,900.00 | $12,000 |
| 34 | Flexible drums (channelizing) (712-04.01) | EACH | 319 | $41.50 | $43.50 |
| 35 | Barrier rail delineator (712-04.50) | EACH | 54 | $12.00 | $15.00 |
| 36 | Warning lights (type A) (712-05.01) | EACH | 20 | $25.00 | $25.00 |
| 37 | Signs (construction) (712-06) | SF | 709 | $7.00 | $10.00 |
| 38 | Temporary barricades (type III) (712-07.03) | LF | 104 | $13.00 | $15.00 |
| 39 | Arrow board (type C) (712-08.03) | EACH | 4 | $625.00 | $1,000.00 |
| 40 | Speed feedback sign assembly (712-08.08) | EACH | 2 | $3,500.00 | $5,000.00 |
| 41 | Portable queue warning system (712-08.14) | DAY | 196 | $825.00 | $800.00 |
| 42 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 39,970 | $7.00 | $7.00 |
| 43 | Changeable message sign unit (713-16.01) | EACH | 2 | $4,500.00 | $7,500.00 |
| 44 | Plastic pavement marking (24" barrier line) (716-02.07) | LF | 1,381 | $25.00 | $30.00 |
| 45 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 4.40 | $9,500.00 | $10,000 |
| 46 | Enhanced flatline thermo PVMT MRKNG (8IN barrier line) (716-12.03) | LF | 2,295 | $4.00 | $4.50 |
| 47 | Enhanced flatline thermo PVMT MRKNG (6IN dotted line) (716-12.05) | LF | 1,125 | $4.00 | $47.00 |
| 48 | Mobilization (717-01) | LS | 1 | $230,000 | $180,000 |
| 49 | Geogrid reinforcement type 2 (740-07.04) | SY | 3,060 | $5.00 | $7.00 |
| 50 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 776 | $5.00 | $10.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of August 15, 2025. Compiled by Mirage Metrics.