Vizcaino, L.P.: TxDOT bid record
Vizcaino, L.P. submitted 37 bids on Texas DOT contracts in the data, from 10 JAN 2020 to 07 OCT 2026, and was the low bidder on 13 of them (35%). When it was not low, its total sat a median +12% above the low bid.
- Owner
- Texas DOT
- Low bid volume
- $20,053,727
- Latest bid
- 07 OCT 2026
- Data through
- 19 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 3 | 3 | 100% |
| 2021 | 1 | 0 | 0% |
| 2022 | 5 | 1 | 20% |
| 2023 | 6 | 1 | 17% |
| 2024 | 1 | 0 | 0% |
| 2025 | 8 | 5 | 63% |
| 2026 | 13 | 3 | 23% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Odessa District | 12 | 8 | 67% |
| San Angelo District | 6 | 1 | 17% |
| Lubbock District | 5 | 1 | 20% |
| Laredo District | 5 | 2 | 40% |
| El Paso District | 2 | 0 | 0% |
| San Antonio District | 2 | 0 | 0% |
| Corpus Christi District | 2 | 0 | 0% |
| Houston District | 1 | 0 | 0% |
| Waco District | 1 | 0 | 0% |
| Abilene District | 1 | 1 | 100% |
Pay items where it is most often lowest
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Stripe-A-Zone, LLC | 25 | 7 of 25 |
| L&L Company | 24 | 9 of 24 |
| Centerline Technologies, LLC | 16 | 8 of 16 |
| TRP Construction Group, LLC | 15 | 2 of 15 |
| TRP Infrastructure Services, LLC | 15 | 4 of 15 |
| Pmi Pavement Marking, LLC | 12 | 3 of 12 |
| Pavement Markings Inc. | 12 | 4 of 12 |
| Interstate Barricades & Markings, Inc. | 11 | 0 of 11 |
| D. I. J. Construction, Inc. | 7 | 1 of 7 |
| Stripe Lines, Inc. | 7 | 0 of 7 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 07 OCT 2026 | A00131942 | San Angelo District | Highway Improvement, Various (Various Locations in SJT District to .) | 2 of 7 | $2,821,484 | +11% |
| 02 SEP 2026 | A00223211 | Laredo District | DEBRIS REMOVAL, IH0035 (Various to Various) | 2 of 4 | $1,488,846 | +20% |
| 18 AUG 2026 | A00222255 | San Angelo District | CLEANING AND SWEEPING HIGHWAYS, SH0208 (VARIOUS LOCATION IN TOM GREEN COUNTY to VARIOUS LOCATION IN TOM GREEN COUNTY) | 3 of 4 | $625,670 | +28% |
| 05 AUG 2026 | A00188161 | Corpus Christi District | Highway Improvement, Various (AT VARIOUS LOCATIONS IN CC DISTRICT to .) | 6 of 6 | $6,154,215 | +29% |
| 05 AUG 2026 | A00222959 | Corpus Christi District | PAVEMENT MARKINGS, US0281 (VARIOUS to .) | 3 of 3 | $2,783,031 | +60% |
| 01 JUL 2026 | A00187817 | Odessa District | Preventive Maintenance, Various (Districtwide to .) | 1 of 8 | $5,487,908 | Low, 7.0% under the second |
| 02 JUN 2026 | A00196424 | San Antonio District | Preventive Maintenance, Various (Various Locations Districtwide to .) | 4 of 9 | $2,915,943 | +21% |
| 21 APR 2026 | A00219871 | Odessa District | REFLECTIVE PAVEMENT MARKINGS (LONG LINE), IH0020 (VARIOUS to VARIOUS) | 2 of 6 | $218,680 | +6.0% |
| 26 MAR 2026 | A00214505 | San Angelo District | PAVEMENT MARKINGS, US0377 (VARIOUS LOCATIONS IN THE SAN ANGELO DIST to VARIOUS LOCATIONS IN THE SAN ANGELO DIST) | 2 of 5 | $291,750 | +46% |
| 26 MAR 2026 | A00219846 | Abilene District | DEBRIS REMOVAL, IH0020 (Various Locations to in the Abilene District) | 1 of 4 | $624,648 | Low, 5.0% under the second |
| 24 MAR 2026 | A00214227 | San Angelo District | PAVEMENT MARKINGS, SH0208 (VARIOUS LOCATIONS IN THE SAN ANGELO DIST to VARIOUS LOCATIONS IN THE SAN ANGELO DIST) | 5 of 6 | $159,596 | +105% |
| 10 MAR 2026 | A00219871 | Odessa District | REFLECTIVE PAVEMENT MARKINGS (LONG LINE), IH0020 (VARIOUS to VARIOUS) | 1 of 7 | $239,578 | Low, 45% under the second |
| 05 FEB 2026 | A00187101 | Lubbock District | Hazard Elimination & Safety, Various (VARIOUS LOCATIONS IN to THE LUBBOCK DISTRICT) | 4 of 10 | $7,273,691 | +12% |
| 02 DEC 2025 | A00212548 | Laredo District | Hazard Elimination & Safety, US 57 (FM 481 to 2.887 Miles East of FM 481) | 5 of 5 | $1,894,045 | +58% |
| 02 DEC 2025 | A00059060 | El Paso District | Preventive Maintenance, Various (DISTRICTWIDE (STRIPING) to .) | 2 of 4 | $3,275,947 | +10% |
| 28 OCT 2025 | A00217991 | Laredo District | CLEANING AND SWEEPING HIGHWAYS, US0277 (Various to Various) | 1 of 1 | $363,296 | Low |
| 23 OCT 2025 | A00217979 | Laredo District | CLEANING AND SWEEPING HIGHWAYS, US0277 (Various to Various) | 1 of 1 | $694,203 | Low |
| 08 AUG 2025 | A00178217 | Odessa District | Preventive Maintenance, Various (Districtwide to .) | 1 of 8 | $2,898,157 | Low, 3.0% under the second |
| 08 APR 2025 | A00214411 | Odessa District | REFLECTIVE PAVEMENT MARKINGS (LONG LINE), IH0020 (VARIOUS to VARIOUS) | 1 of 6 | $462,533 | Low, 8.0% under the second |
| 11 MAR 2025 | A00212969 | Odessa District | REFLECTIVE PAVEMENT MARKINGS (LONG LINE), IH0020 (VARIOUS to VARIOUS) | 1 of 7 | $393,225 | Low, 1.0% under the second |
| 07 FEB 2025 | A00212598 | Laredo District | Preventive Maintenance, Various (DISTRICTWIDE to -) | 5 of 9 | $1,824,744 | +26% |
| 06 MAR 2024 | 03243217 | Odessa District | VA Preventive maintenance from DISTRICTWIDE | 3 of 8 | $766,276 | +9.0% |
| 03 AUG 2023 | 08233243 | Waco District | VA Maintenance & operations project from VARIOUS to VARIOUS | 2 of 8 | $2,571,923 | +7.0% |
| 02 JUN 2023 | 06233217 | San Antonio District | VA Preventive maintenance from VARIOUS LOCATIONS DISTRICTWIDE | 2 of 6 | $5,643,520 | +9.0% |
| 02 JUN 2023 | 06234207 | Houston District | IH0610 Sweeping and debris removal from VARIOUS HWYS IN HOUSTON METRO AREA to VARIOUS HWYS IN HOUSTON METRO AREA | 3 of 4 | $3,440,850 | +31% |
How this record was read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; TxDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.