TxDOT contract A00014772 bid tabulation
Highway Improvement, SH 29 (RM 1174 SOUTH to WILLIAMSON COUNTY LINE). Let by Texas DOT on May 6, 2026, Burnet, Austin District. 8 bids received; low bid $10,910,072 by Texas Materials Group, Inc., +0.9% against the engineer's estimate of $10,815,462.
- Owner
- Texas DOT
- Letting
- 06 MAY 2026
- Pay items
- 108
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Texas Materials Group, Inc. | $10,910,072 | Low | +1.0% |
| 2 | Joe Bland Construction LLC | $11,221,481 | +3.0% | +4.0% |
| 3 | Hunter Industries, LTD. | $12,382,171 | +13% | +14% |
| 4 | Allen Keller Company | $12,420,418 | +14% | +15% |
| 5 | Aaron Concrete Contractors, LLC | $12,759,133 | +17% | +18% |
| 6 | Capital Excavation Company | $12,858,021 | +18% | +19% |
| 7 | Acme Bridge Company, Inc. | $13,076,970 | +20% | +21% |
| 8 | Icos Management, LLC | $14,697,351 | +35% | +36% |
Engineer's estimate: $10,815,462.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Texas Materials Group, Inc. | 2. Joe Bland Construction LLC | 3. Hunter Industries, LTD. | 4. Allen Keller Company | 5. Aaron Concrete Contractors, LLC | 6. Capital Excavation Company |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 210.18 | $1,500.00 | $496.00 | $775.00 | $854.70 | $2,273.83 | $1,919.00 | $850.00 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 721 | $15.00 | $18.00 | $25.00 | $29.70 | $14.32 | $17.00 | $20.00 |
| 3 | Removing concrete (driveways) (104-7011) | SY | 1,235.80 | $29.00 | $15.69 | $40.00 | $34.10 | $20.88 | $25.00 | $31.00 |
| 4 | Remove (2"-6") TRT/untrt base & asphalt pavement (105-7002) | SY | 1,831 | $7.00 | $12.50 | $6.00 | $8.16 | $1.48 | $11.00 | $20.00 |
| 5 | Remove (10"-14") TRT/untrt base & asphalt pavement (105-7010) | SY | 274 | $12.00 | $9.75 | $14.00 | $16.50 | $6.10 | $22.00 | $52.70 |
| 6 | Remove (19"-23") TRT/untrt base & asphalt pavement (105-7019) | SY | 21,095 | $10.50 | $8.39 | $16.00 | $15.25 | $10.28 | $23.00 | $10.50 |
| 7 | Remove (10") TRT/untrt base & asphalt pavement (105-7030) | SY | 573 | $18.00 | $5.55 | $12.00 | $9.07 | $4.42 | $15.00 | $19.60 |
| 8 | Excavation (roadway) (110-7001) | CY | 19,011 | $15.25 | $12.20 | $11.00 | $20.90 | $25.60 | $28.00 | $17.55 |
| 9 | Embankment (final)(OC)(type B) (132-7003) | CY | 11,383 | $16.75 | $5.05 | $6.00 | $20.90 | $10.56 | $17.00 | $36.00 |
| 10 | Furn & place topsoil (4") (160-7002) | SY | 58,779 | $1.25 | $3.20 | $1.50 | $1.80 | $2.78 | $2.00 | $2.50 |
| 11 | Drill seed (permanent_rural_clay) (164-7010) | SY | 58,779 | $0.20 | $0.22 | $0.30 | $0.24 | $0.32 | $0.26 | $0.25 |
| 12 | Vegetative watering (168-7001) | TGL | 2,941 | $24.00 | $35.00 | $4.00 | $26.40 | $33.00 | $55.00 | $34.00 |
| 13 | Soil ret BLKT(SL_steep_clay_long) (169-7006) | SY | 58,779 | $1.50 | $0.89 | $1.45 | $0.97 | $1.24 | $1.00 | $0.97 |
| 14 | FL BS (compacted in place)(type A GR 5)(final pos) (247-7179) | CY | 20,123 | $52.75 | $45.50 | $55.00 | $63.46 | $58.72 | $53.00 | $52.00 |
| 15 | Prime coat (multi option) (310-7015) | GAL | 11,607 | $3.85 | $5.50 | $3.75 | $4.95 | $5.16 | $4.00 | $3.80 |
| 16 | D-GR HMA type-B PG64-22 (341-7001) | TON | 21,819 | $82.50 | $93.00 | $100.00 | $100.10 | $103.74 | $100.00 | $93.00 |
| 17 | D-GR HMA type D PG76-22 (341-7056) | TON | 8,488 | $102.50 | $113.00 | $124.00 | $108.90 | $110.18 | $129.00 | $117.00 |
| 18 | D-GR HMA type D PG 76-22 (exempt) (341-7065) | TON | 849 | $120.00 | $113.00 | $126.00 | $117.70 | $113.50 | $127.00 | $119.00 |
| 19 | Tom-C PG76-22 sac-B (347-7002) | TON | 9,094 | $120.00 | $136.00 | $145.00 | $133.10 | $119.63 | $149.00 | $137.00 |
| 20 | Flowable backfill (401-7001) | CY | 709 | $215.00 | $230.00 | $255.00 | $250.00 | $173.74 | $189.00 | $221.00 |
| 21 | Trench excavation protection (402-7001) | LF | 24 | $13.00 | $100.00 | $1,250.00 | $128.00 | $24.82 | $5.00 | $118.00 |
| 22 | Temporary special shoring (403-7001) | SF | 789 | $40.00 | $65.00 | $50.00 | $10.00 | $19.86 | $12.00 | $22.70 |
| 23 | Riprap (concrete)(5 in) (432-7002) | CY | 1,392 | $435.00 | $540.00 | $395.00 | $649.98 | $471.57 | $587.00 | $675.00 |
| 24 | Riprap (mow strip)(4 in) (432-7013) | CY | 345 | $585.00 | $585.00 | $495.00 | $724.23 | $699.91 | $647.00 | $1,050.00 |
| 25 | Rirrap (stone common)(dry)(15 in) (432-7032) | CY | 25 | $230.00 | $300.00 | $325.00 | $235.00 | $195.82 | $205.00 | $630.00 |
| 26 | Concrete box culvert (3 FT X 3 FT)(extend) (462-7057) | LF | 22 | $700.00 | $865.00 | $750.00 | $950.00 | $729.69 | $605.00 | $590.00 |
| 27 | Concrete box culvert (4 FT X 3 FT)(extend) (462-7059) | LF | 29 | $1,000.00 | $920.00 | $775.00 | $750.00 | $764.44 | $635.00 | $640.00 |
| 28 | Concrete box culvert (5 FT X 2 FT)(extend) (462-7061) | LF | 27 | $1,000.00 | $845.00 | $825.00 | $1,110.00 | $828.97 | $633.00 | $630.00 |
| 29 | Concrete box culvert (6 FT X 5 FT)(extend) (462-7068) | LF | 20 | $1,100.00 | $1,330.00 | $2,000.00 | $1,700.00 | $1,129.78 | $1,076.00 | $900.00 |
| 30 | Concrete box culvert (8 FT X 5 FT)(extend) (462-7077) | LF | 39 | $1,510.00 | $2,200.00 | $1,450.00 | $898.46 | $1,220.00 | $1,060.00 | |
| 31 | RC pipe (CL III)(18 in) (464-7003) | LF | 2,552 | $72.50 | $61.00 | $115.00 | $70.00 | $106.23 | $93.00 | $78.90 |
| 32 | RC pipe (CL III)(24 in) (464-7005) | LF | 1,710 | $100.00 | $79.00 | $135.00 | $80.00 | $122.11 | $114.00 | $107.00 |
| 33 | RC pipe (CL III)(30 in) (464-7007) | LF | 60 | $150.00 | $127.00 | $165.00 | $110.00 | $109.21 | $192.00 | $148.00 |
| 34 | RC pipe (CL III)(36 in) (464-7009) | LF | 48 | $250.00 | $180.00 | $220.00 | $165.00 | $178.70 | $252.00 | $191.00 |
| 35 | RC pipe (CL V)(24 in) (464-7034) | LF | 10 | $225.00 | $120.00 | $240.00 | $225.00 | $129.06 | $694.00 | $450.00 |
| 36 | Headwall (CH - PW - 0) (diameter= 24 in) (466-7101) | EACH | 1 | $8,300.00 | $6,000.00 | $4,000.00 | $5,500.00 | $6,055.95 | $5,182.00 | $6,000.00 |
| 37 | Wingwall (PW - 1) (HW=3 FT) (466-7173) | EACH | 1 | $12,000 | $11,400 | $8,000.00 | $7,750.00 | $9,530.67 | $10,649 | $6,900.00 |
| 38 | Wingwall (PW - 1) (HW=4 FT) (466-7174) | EACH | 1 | $18,000 | $17,100 | $9,500.00 | $12,750 | $11,045 | $13,947 | $11,400 |
| 39 | Wingwall (PW - 1) (HW=5 FT) (466-7175) | EACH | 3 | $19,000 | $17,700 | $10,500 | $14,600 | $12,906 | $12,642 | $11,400 |
| 40 | Wingwall (PW - 1) (HW=6 FT) (466-7176) | EACH | 4 | $22,500 | $16,150 | $17,500 | $25,250 | $13,159 | $26,099 | $20,800 |
| 41 | Wingwall (PW - 1) (HW=11 FT) (466-7181) | EACH | 1 | $60,000 | $154,000 | $65,000 | $160,000 | $87,806 | $141,143 | $120,276 |
| 42 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 102 | $1,700.00 | $1,050.00 | $2,250.00 | $1,600.00 | $1,742.33 | $2,405.00 | $2,700.00 |
| 43 | Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325) | EACH | 2 | $2,200.00 | $1,000.00 | $2,500.00 | $1,300.00 | $2,591.16 | $2,507.00 | $2,470.00 |
| 44 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 1 | $2,600.00 | $1,110.00 | $2,500.00 | $1,700.00 | $3,588.90 | $2,503.00 | $3,030.00 |
| 45 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 55 | $1,650.00 | $1,390.00 | $2,750.00 | $2,200.00 | $1,945.85 | $2,810.00 | $3,090.00 |
| 46 | Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348) | EACH | 2 | $3,900.00 | $2,320.00 | $4,500.00 | $2,650.00 | $3,310.92 | $3,254.00 | $3,560.00 |
| 47 | Set (type II) (36 in) (RCP) (6: 1) (P) (467-7368) | EACH | 1 | $6,000.00 | $4,100.00 | $9,000.00 | $5,800.00 | $9,431.40 | $6,277.00 | $5,900.00 |
| 48 | Set(type II)(24 in)(RCP)(4:1)(P) (467-7468) | EACH | 7 | $2,000.00 | $2,300.00 | $2,500.00 | $1,700.00 | $2,164.26 | $2,600.00 | $3,030.00 |
| 49 | Set(type II)(24 in)(RCP)(3:1)(P) (467-7469) | EACH | 2 | $2,000.00 | $2,100.00 | $2,500.00 | $1,550.00 | $1,548.73 | $2,555.00 | $2,470.00 |
| 50 | Set (type II) (18") (RCP) (4:1) (P) (467-7474) | EACH | 2 | $1,800.00 | $2,000.00 | $2,250.00 | $1,750.00 | $1,499.09 | $2,242.00 | $2,300.00 |
| 51 | Set (type II)(36 in)(4:1)(P) (467-7480) | EACH | 1 | $5,000.00 | $5,200.00 | $7,500.00 | $5,200.00 | $9,083.93 | $5,959.00 | $5,700.00 |
| 52 | Clean existing culverts (480-7001) | EACH | 8 | $3,800.00 | $3,100.00 | $2,000.00 | $3,000.00 | $4,963.89 | $3,410.00 | $760.00 |
| 53 | Mobilization (500-7001) | LS | 1 | $791,200 | $665,000 | $225,000 | $953,039 | $1,180,000 | $505,826 | $603,000 |
| 54 | Barricades, signs and traffic handling (502-7001) | MO | 8 | $9,000.00 | $1,500.00 | $7,250.00 | $10,060 | $13,438 | $2,911.00 | $7,500.00 |
| 55 | Portable changeable message sign (503-7002) | EACH | 2 | $15,000 | $6,400.00 | $13,500 | $3,811.29 | $6,822.60 | $11,709 | $21,400 |
| 56 | TMA (stationary) (505-7001) | DAY | 70 | $250.00 | $11.00 | $200.00 | $136.12 | $291.80 | $352.00 | $330.00 |
| 57 | TMA (mobile operation) (505-7003) | DAY | 75 | $400.00 | $600.00 | $1,100.00 | $272.24 | $832.63 | $59.00 | $1,070.00 |
| 58 | Rock filter dams (install) (type 2) (506-7002) | LF | 715 | $45.00 | $63.99 | $50.00 | $69.39 | $41.70 | $75.00 | $69.45 |
| 59 | Rock filter dams (remove) (506-7011) | LF | 715 | $16.00 | $14.04 | $25.00 | $15.24 | $9.93 | $16.00 | $15.25 |
| 60 | Temporary sediment control fence (install) (506-7039) | LF | 6,957 | $3.60 | $4.67 | $5.00 | $5.06 | $4.47 | $5.00 | $5.05 |
| 61 | Temporary sediment control fence (remove) (506-7041) | LF | 6,957 | $0.90 | $0.92 | $1.00 | $1.00 | $0.99 | $1.00 | $1.00 |
| 62 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 2,620 | $6.00 | $7.80 | $6.00 | $8.46 | $5.46 | $9.00 | $8.45 |
| 63 | Biodegradable erosion control logs (remove) (506-7046) | LF | 2,620 | $1.40 | $0.92 | $2.00 | $1.00 | $0.99 | $1.00 | $1.00 |
| 64 | Intersections (ACP) (530-7002) | SY | 1,364 | $55.00 | $129.00 | $90.00 | $71.50 | $103.22 | $103.00 | $120.00 |
| 65 | Driveways (concrete) (530-7006) | SY | 1,237 | $100.00 | $152.00 | $145.00 | $116.52 | $124.87 | $141.00 | $130.00 |
| 66 | Driveways (ACP) (530-7010) | SY | 5,698 | $57.50 | $87.00 | $55.00 | $66.00 | $53.43 | $61.00 | $95.00 |
| 67 | Turnouts (ACP) (530-7018) | SY | 291 | $140.00 | $174.00 | $80.00 | $52.80 | $60.27 | $57.00 | $168.00 |
| 68 | Metal W-beam guard fence (timber post) (540-7001) | LF | 6,250 | $22.50 | $25.50 | $30.00 | $25.20 | $23.82 | $34.00 | $25.75 |
| 69 | Downstream anchor terminal section (540-7015) | EACH | 1 | $1,600.00 | $1,600.00 | $1,500.00 | $1,364.96 | $1,290.62 | $2,198.00 | $1,400.00 |
| 70 | Metal beam guard fence (long span system) (540-7027) | EACH | 2 | $1,400.00 | $1,450.00 | $1,500.00 | $1,417.46 | $1,340.25 | $1,810.00 | $1,450.00 |
| 71 | Remove metal beam guard fence (542-7001) | LF | 1,380 | $3.10 | $3.00 | $3.00 | $2.62 | $2.48 | $3.00 | $2.70 |
| 72 | Guardrail end treatment (install) (544-7001) | EACH | 29 | $3,000.00 | $3,060.00 | $4,250.00 | $3,307.40 | $3,127.25 | $3,880.00 | $3,380.00 |
| 73 | Guardrail end treatment (remove) (544-7003) | EACH | 7 | $280.00 | $275.00 | $200.00 | $262.49 | $248.19 | $259.00 | $270.00 |
| 74 | Wire fence (type C) (552-7003) | LF | 150 | $45.00 | $55.60 | $16.00 | $21.00 | $24.82 | $29.00 | $33.15 |
| 75 | Wire fence (remove) (552-7011) | LF | 150 | $3.00 | $21.20 | $8.00 | $5.25 | $1.99 | $4.00 | $12.65 |
| 76 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 29 | $380.00 | $250.00 | $275.00 | $453.59 | $248.19 | $293.00 | $270.00 |
| 77 | Mailbox install-D (TWW-post) type 4 (560-7009) | EACH | 3 | $380.00 | $275.00 | $305.00 | $510.28 | $273.01 | $322.00 | $300.00 |
| 78 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 6 | $800.00 | $550.00 | $615.00 | $881.97 | $546.03 | $644.00 | $600.00 |
| 79 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 32 | $750.00 | $650.00 | $725.00 | $734.98 | $645.30 | $761.00 | $710.00 |
| 80 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 4 | $800.00 | $750.00 | $825.00 | $906.12 | $744.58 | $878.00 | $810.00 |
| 81 | Install small roadside sign support and assembly TYS80(1)SA(U-WC) (644-7035) | EACH | 1 | $1,600.00 | $950.00 | $1,050.00 | $1,326.11 | $943.15 | $1,112.00 | $1,030.00 |
| 82 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 5 | $500.00 | $400.00 | $450.00 | $625.78 | $397.11 | $468.00 | $430.00 |
| 83 | Remove SM RD SN sup&AM (644-7073) | EACH | 37 | $110.00 | $85.00 | $95.00 | $134.40 | $84.39 | $100.00 | $159.00 |
| 84 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 91 | $45.00 | $55.00 | $30.00 | $48.30 | $22.83 | $59.00 | $27.10 |
| 85 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 11 | $110.00 | $90.00 | $135.00 | $85.05 | $124.10 | $146.00 | $136.00 |
| 86 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 44,686 | $0.25 | $0.21 | $0.25 | $0.23 | $0.21 | $0.25 | $0.20 |
| 87 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 10,730 | $0.27 | $0.21 | $0.25 | $0.23 | $0.21 | $0.25 | $0.20 |
| 88 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 44,116 | $0.29 | $0.21 | $0.25 | $0.23 | $0.21 | $0.25 | $0.20 |
| 89 | Work zone pavement marking removing (traffic BTN) type W (662-7057) | EACH | 87 | $3.00 | $7.35 | $8.00 | $8.02 | $7.29 | $9.00 | $5.25 |
| 90 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 17,874 | $1.00 | $0.95 | $1.25 | $1.72 | $3.61 | $2.00 | $8.95 |
| 91 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 28,376 | $1.00 | $0.95 | $1.25 | $1.72 | $3.64 | $2.00 | $8.95 |
| 92 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 530 | $1.05 | $1.05 | $1.25 | $1.15 | $1.04 | $1.00 | $1.10 |
| 93 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 164 | $8.50 | $11.00 | $12.25 | $12.00 | $10.92 | $13.00 | $7.05 |
| 94 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 13 | $180.00 | $200.00 | $225.00 | $218.18 | $198.56 | $234.00 | $217.00 |
| 95 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 3 | $240.00 | $250.00 | $275.00 | $272.72 | $248.19 | $293.00 | $217.00 |
| 96 | Reflectorized profile pavement marking type I(W)6"(solid)(090MIL) (666-7265) | LF | 41,206 | $0.70 | $0.81 | $1.00 | $0.88 | $0.81 | $1.00 | $0.90 |
| 97 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 9,802 | $0.70 | $0.55 | $0.75 | $0.60 | $0.55 | $1.00 | $0.65 |
| 98 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 9,681 | $0.60 | $0.55 | $0.75 | $0.60 | $0.55 | $1.00 | $0.65 |
| 99 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 40,878 | $0.60 | $0.55 | $0.75 | $0.60 | $0.55 | $1.00 | $0.65 |
| 100 | PRFB rumble strip (BLK)(1')(edgeline) (668-7137) | LF | 41,108 | $4.00 | $0.81 | $1.00 | $0.88 | $0.81 | $1.00 | $3.80 |
| 101 | Reflectorized pavement marker type I-C (672-7002) | EACH | 150 | $4.00 | $7.00 | $8.00 | $7.64 | $6.95 | $8.00 | $3.80 |
| 102 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,066 | $4.00 | $7.00 | $8.00 | $7.64 | $6.95 | $8.00 | $3.80 |
| 103 | Eliminating existing PM & markers (4") (677-7001) | LF | 101,490 | $0.35 | $0.10 | $0.15 | $0.11 | $0.10 | $0.12 | $0.43 |
| 104 | Eliminating existing PM & markers (8") (677-7004) | LF | 120 | $1.00 | $1.00 | $1.25 | $1.09 | $0.99 | $1.00 | $0.55 |
| 105 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 1 | $70.00 | $175.00 | $195.00 | $190.91 | $173.74 | $205.00 | $108.00 |
| 106 | Eliminating existing PM & markers (word) (677-7015) | EACH | 1 | $90.00 | $175.00 | $195.00 | $190.91 | $173.74 | $205.00 | $108.00 |
| 107 | Bonding course (3007-7001) | GAL | 29,227 | $3.25 | $4.75 | $4.00 | $3.52 | $4.38 | $4.00 | $3.80 |
| 108 | Subsurface util locate (non-paved area) (5061-7001) | EACH | 50 | $1,000.00 | $315.00 | $1,750.00 | $2,500.00 | $493.95 | $1,983.00 | $610.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 6, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.