TxDOT contract A00014772 bid tabulation

Highway Improvement, SH 29 (RM 1174 SOUTH to WILLIAMSON COUNTY LINE). Let by Texas DOT on May 6, 2026, Burnet, Austin District. 8 bids received; low bid $10,910,072 by Texas Materials Group, Inc., +0.9% against the engineer's estimate of $10,815,462.

Owner
Texas DOT
Letting
06 MAY 2026
Pay items
108
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Texas Materials Group, Inc.$10,910,072Low+1.0%
2Joe Bland Construction LLC$11,221,481+3.0%+4.0%
3Hunter Industries, LTD.$12,382,171+13%+14%
4Allen Keller Company$12,420,418+14%+15%
5Aaron Concrete Contractors, LLC$12,759,133+17%+18%
6Capital Excavation Company$12,858,021+18%+19%
7Acme Bridge Company, Inc.$13,076,970+20%+21%
8Icos Management, LLC$14,697,351+35%+36%
TxDOT contract A00014772: bids by rank

Engineer's estimate: $10,815,462.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Texas Materials Group, Inc.2. Joe Bland Construction LLC3. Hunter Industries, LTD.4. Allen Keller Company5. Aaron Concrete Contractors, LLC6. Capital Excavation Company
1Preparing row (100-7002)STA210.18$1,500.00$496.00$775.00$854.70$2,273.83$1,919.00$850.00
2Removing concrete (riprap) (104-7006)SY721$15.00$18.00$25.00$29.70$14.32$17.00$20.00
3Removing concrete (driveways) (104-7011)SY1,235.80$29.00$15.69$40.00$34.10$20.88$25.00$31.00
4Remove (2"-6") TRT/untrt base & asphalt pavement (105-7002)SY1,831$7.00$12.50$6.00$8.16$1.48$11.00$20.00
5Remove (10"-14") TRT/untrt base & asphalt pavement (105-7010)SY274$12.00$9.75$14.00$16.50$6.10$22.00$52.70
6Remove (19"-23") TRT/untrt base & asphalt pavement (105-7019)SY21,095$10.50$8.39$16.00$15.25$10.28$23.00$10.50
7Remove (10") TRT/untrt base & asphalt pavement (105-7030)SY573$18.00$5.55$12.00$9.07$4.42$15.00$19.60
8Excavation (roadway) (110-7001)CY19,011$15.25$12.20$11.00$20.90$25.60$28.00$17.55
9Embankment (final)(OC)(type B) (132-7003)CY11,383$16.75$5.05$6.00$20.90$10.56$17.00$36.00
10Furn & place topsoil (4") (160-7002)SY58,779$1.25$3.20$1.50$1.80$2.78$2.00$2.50
11Drill seed (permanent_rural_clay) (164-7010)SY58,779$0.20$0.22$0.30$0.24$0.32$0.26$0.25
12Vegetative watering (168-7001)TGL2,941$24.00$35.00$4.00$26.40$33.00$55.00$34.00
13Soil ret BLKT(SL_steep_clay_long) (169-7006)SY58,779$1.50$0.89$1.45$0.97$1.24$1.00$0.97
14FL BS (compacted in place)(type A GR 5)(final pos) (247-7179)CY20,123$52.75$45.50$55.00$63.46$58.72$53.00$52.00
15Prime coat (multi option) (310-7015)GAL11,607$3.85$5.50$3.75$4.95$5.16$4.00$3.80
16D-GR HMA type-B PG64-22 (341-7001)TON21,819$82.50$93.00$100.00$100.10$103.74$100.00$93.00
17D-GR HMA type D PG76-22 (341-7056)TON8,488$102.50$113.00$124.00$108.90$110.18$129.00$117.00
18D-GR HMA type D PG 76-22 (exempt) (341-7065)TON849$120.00$113.00$126.00$117.70$113.50$127.00$119.00
19Tom-C PG76-22 sac-B (347-7002)TON9,094$120.00$136.00$145.00$133.10$119.63$149.00$137.00
20Flowable backfill (401-7001)CY709$215.00$230.00$255.00$250.00$173.74$189.00$221.00
21Trench excavation protection (402-7001)LF24$13.00$100.00$1,250.00$128.00$24.82$5.00$118.00
22Temporary special shoring (403-7001)SF789$40.00$65.00$50.00$10.00$19.86$12.00$22.70
23Riprap (concrete)(5 in) (432-7002)CY1,392$435.00$540.00$395.00$649.98$471.57$587.00$675.00
24Riprap (mow strip)(4 in) (432-7013)CY345$585.00$585.00$495.00$724.23$699.91$647.00$1,050.00
25Rirrap (stone common)(dry)(15 in) (432-7032)CY25$230.00$300.00$325.00$235.00$195.82$205.00$630.00
26Concrete box culvert (3 FT X 3 FT)(extend) (462-7057)LF22$700.00$865.00$750.00$950.00$729.69$605.00$590.00
27Concrete box culvert (4 FT X 3 FT)(extend) (462-7059)LF29$1,000.00$920.00$775.00$750.00$764.44$635.00$640.00
28Concrete box culvert (5 FT X 2 FT)(extend) (462-7061)LF27$1,000.00$845.00$825.00$1,110.00$828.97$633.00$630.00
29Concrete box culvert (6 FT X 5 FT)(extend) (462-7068)LF20$1,100.00$1,330.00$2,000.00$1,700.00$1,129.78$1,076.00$900.00
30Concrete box culvert (8 FT X 5 FT)(extend) (462-7077)LF39$1,510.00$2,200.00$1,450.00$898.46$1,220.00$1,060.00
31RC pipe (CL III)(18 in) (464-7003)LF2,552$72.50$61.00$115.00$70.00$106.23$93.00$78.90
32RC pipe (CL III)(24 in) (464-7005)LF1,710$100.00$79.00$135.00$80.00$122.11$114.00$107.00
33RC pipe (CL III)(30 in) (464-7007)LF60$150.00$127.00$165.00$110.00$109.21$192.00$148.00
34RC pipe (CL III)(36 in) (464-7009)LF48$250.00$180.00$220.00$165.00$178.70$252.00$191.00
35RC pipe (CL V)(24 in) (464-7034)LF10$225.00$120.00$240.00$225.00$129.06$694.00$450.00
36Headwall (CH - PW - 0) (diameter= 24 in) (466-7101)EACH1$8,300.00$6,000.00$4,000.00$5,500.00$6,055.95$5,182.00$6,000.00
37Wingwall (PW - 1) (HW=3 FT) (466-7173)EACH1$12,000$11,400$8,000.00$7,750.00$9,530.67$10,649$6,900.00
38Wingwall (PW - 1) (HW=4 FT) (466-7174)EACH1$18,000$17,100$9,500.00$12,750$11,045$13,947$11,400
39Wingwall (PW - 1) (HW=5 FT) (466-7175)EACH3$19,000$17,700$10,500$14,600$12,906$12,642$11,400
40Wingwall (PW - 1) (HW=6 FT) (466-7176)EACH4$22,500$16,150$17,500$25,250$13,159$26,099$20,800
41Wingwall (PW - 1) (HW=11 FT) (466-7181)EACH1$60,000$154,000$65,000$160,000$87,806$141,143$120,276
42Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH102$1,700.00$1,050.00$2,250.00$1,600.00$1,742.33$2,405.00$2,700.00
43Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325)EACH2$2,200.00$1,000.00$2,500.00$1,300.00$2,591.16$2,507.00$2,470.00
44Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326)EACH1$2,600.00$1,110.00$2,500.00$1,700.00$3,588.90$2,503.00$3,030.00
45Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH55$1,650.00$1,390.00$2,750.00$2,200.00$1,945.85$2,810.00$3,090.00
46Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348)EACH2$3,900.00$2,320.00$4,500.00$2,650.00$3,310.92$3,254.00$3,560.00
47Set (type II) (36 in) (RCP) (6: 1) (P) (467-7368)EACH1$6,000.00$4,100.00$9,000.00$5,800.00$9,431.40$6,277.00$5,900.00
48Set(type II)(24 in)(RCP)(4:1)(P) (467-7468)EACH7$2,000.00$2,300.00$2,500.00$1,700.00$2,164.26$2,600.00$3,030.00
49Set(type II)(24 in)(RCP)(3:1)(P) (467-7469)EACH2$2,000.00$2,100.00$2,500.00$1,550.00$1,548.73$2,555.00$2,470.00
50Set (type II) (18") (RCP) (4:1) (P) (467-7474)EACH2$1,800.00$2,000.00$2,250.00$1,750.00$1,499.09$2,242.00$2,300.00
51Set (type II)(36 in)(4:1)(P) (467-7480)EACH1$5,000.00$5,200.00$7,500.00$5,200.00$9,083.93$5,959.00$5,700.00
52Clean existing culverts (480-7001)EACH8$3,800.00$3,100.00$2,000.00$3,000.00$4,963.89$3,410.00$760.00
53Mobilization (500-7001)LS1$791,200$665,000$225,000$953,039$1,180,000$505,826$603,000
54Barricades, signs and traffic handling (502-7001)MO8$9,000.00$1,500.00$7,250.00$10,060$13,438$2,911.00$7,500.00
55Portable changeable message sign (503-7002)EACH2$15,000$6,400.00$13,500$3,811.29$6,822.60$11,709$21,400
56TMA (stationary) (505-7001)DAY70$250.00$11.00$200.00$136.12$291.80$352.00$330.00
57TMA (mobile operation) (505-7003)DAY75$400.00$600.00$1,100.00$272.24$832.63$59.00$1,070.00
58Rock filter dams (install) (type 2) (506-7002)LF715$45.00$63.99$50.00$69.39$41.70$75.00$69.45
59Rock filter dams (remove) (506-7011)LF715$16.00$14.04$25.00$15.24$9.93$16.00$15.25
60Temporary sediment control fence (install) (506-7039)LF6,957$3.60$4.67$5.00$5.06$4.47$5.00$5.05
61Temporary sediment control fence (remove) (506-7041)LF6,957$0.90$0.92$1.00$1.00$0.99$1.00$1.00
62Biodegradable erosion control logs (install) (12") (506-7044)LF2,620$6.00$7.80$6.00$8.46$5.46$9.00$8.45
63Biodegradable erosion control logs (remove) (506-7046)LF2,620$1.40$0.92$2.00$1.00$0.99$1.00$1.00
64Intersections (ACP) (530-7002)SY1,364$55.00$129.00$90.00$71.50$103.22$103.00$120.00
65Driveways (concrete) (530-7006)SY1,237$100.00$152.00$145.00$116.52$124.87$141.00$130.00
66Driveways (ACP) (530-7010)SY5,698$57.50$87.00$55.00$66.00$53.43$61.00$95.00
67Turnouts (ACP) (530-7018)SY291$140.00$174.00$80.00$52.80$60.27$57.00$168.00
68Metal W-beam guard fence (timber post) (540-7001)LF6,250$22.50$25.50$30.00$25.20$23.82$34.00$25.75
69Downstream anchor terminal section (540-7015)EACH1$1,600.00$1,600.00$1,500.00$1,364.96$1,290.62$2,198.00$1,400.00
70Metal beam guard fence (long span system) (540-7027)EACH2$1,400.00$1,450.00$1,500.00$1,417.46$1,340.25$1,810.00$1,450.00
71Remove metal beam guard fence (542-7001)LF1,380$3.10$3.00$3.00$2.62$2.48$3.00$2.70
72Guardrail end treatment (install) (544-7001)EACH29$3,000.00$3,060.00$4,250.00$3,307.40$3,127.25$3,880.00$3,380.00
73Guardrail end treatment (remove) (544-7003)EACH7$280.00$275.00$200.00$262.49$248.19$259.00$270.00
74Wire fence (type C) (552-7003)LF150$45.00$55.60$16.00$21.00$24.82$29.00$33.15
75Wire fence (remove) (552-7011)LF150$3.00$21.20$8.00$5.25$1.99$4.00$12.65
76Mailbox install-S (TWW-post) type 4 (560-7008)EACH29$380.00$250.00$275.00$453.59$248.19$293.00$270.00
77Mailbox install-D (TWW-post) type 4 (560-7009)EACH3$380.00$275.00$305.00$510.28$273.01$322.00$300.00
78Mailbox install-M (TWW-post) type 4 (560-7010)EACH6$800.00$550.00$615.00$881.97$546.03$644.00$600.00
79Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH32$750.00$650.00$725.00$734.98$645.30$761.00$710.00
80Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH4$800.00$750.00$825.00$906.12$744.58$878.00$810.00
81Install small roadside sign support and assembly TYS80(1)SA(U-WC) (644-7035)EACH1$1,600.00$950.00$1,050.00$1,326.11$943.15$1,112.00$1,030.00
82Relocate SM RD SN sup&AM type 10BWG (644-7065)EACH5$500.00$400.00$450.00$625.78$397.11$468.00$430.00
83Remove SM RD SN sup&AM (644-7073)EACH37$110.00$85.00$95.00$134.40$84.39$100.00$159.00
84Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018)EACH91$45.00$55.00$30.00$48.30$22.83$59.00$27.10
85Install object marker assembly (OM-2Z)(WFLX)GND (658-7058)EACH11$110.00$90.00$135.00$85.05$124.10$146.00$136.00
86Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF44,686$0.25$0.21$0.25$0.23$0.21$0.25$0.20
87Work zone pavement marking non-removing (Y)6"(broken) (662-7036)LF10,730$0.27$0.21$0.25$0.23$0.21$0.25$0.20
88Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF44,116$0.29$0.21$0.25$0.23$0.21$0.25$0.20
89Work zone pavement marking removing (traffic BTN) type W (662-7057)EACH87$3.00$7.35$8.00$8.02$7.29$9.00$5.25
90Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH17,874$1.00$0.95$1.25$1.72$3.61$2.00$8.95
91Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH28,376$1.00$0.95$1.25$1.72$3.64$2.00$8.95
92Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF530$1.05$1.05$1.25$1.15$1.04$1.00$1.10
93Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF164$8.50$11.00$12.25$12.00$10.92$13.00$7.05
94Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042)EACH13$180.00$200.00$225.00$218.18$198.56$234.00$217.00
95Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066)EACH3$240.00$250.00$275.00$272.72$248.19$293.00$217.00
96Reflectorized profile pavement marking type I(W)6"(solid)(090MIL) (666-7265)LF41,206$0.70$0.81$1.00$0.88$0.81$1.00$0.90
97Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF9,802$0.70$0.55$0.75$0.60$0.55$1.00$0.65
98Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF9,681$0.60$0.55$0.75$0.60$0.55$1.00$0.65
99Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF40,878$0.60$0.55$0.75$0.60$0.55$1.00$0.65
100PRFB rumble strip (BLK)(1')(edgeline) (668-7137)LF41,108$4.00$0.81$1.00$0.88$0.81$1.00$3.80
101Reflectorized pavement marker type I-C (672-7002)EACH150$4.00$7.00$8.00$7.64$6.95$8.00$3.80
102Reflectorized pavement marker type II-A-A (672-7004)EACH1,066$4.00$7.00$8.00$7.64$6.95$8.00$3.80
103Eliminating existing PM & markers (4") (677-7001)LF101,490$0.35$0.10$0.15$0.11$0.10$0.12$0.43
104Eliminating existing PM & markers (8") (677-7004)LF120$1.00$1.00$1.25$1.09$0.99$1.00$0.55
105Eliminating existing PM & markers (arrow) (677-7009)EACH1$70.00$175.00$195.00$190.91$173.74$205.00$108.00
106Eliminating existing PM & markers (word) (677-7015)EACH1$90.00$175.00$195.00$190.91$173.74$205.00$108.00
107Bonding course (3007-7001)GAL29,227$3.25$4.75$4.00$3.52$4.38$4.00$3.80
108Subsurface util locate (non-paved area) (5061-7001)EACH50$1,000.00$315.00$1,750.00$2,500.00$493.95$1,983.00$610.00
TxDOT contract A00014772: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of May 6, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy