TxDOT contract A00063674 bid tabulation
Surfacing/Roadway Restoration, IH 37 (US 281 to Bexar/ Atascosa County Line). Let by Texas DOT on September 5, 2025, Atascosa, San Antonio District. 5 bids received; low bid $17,520,874 by Lone Star Paving Company, -30% against the engineer's estimate of $24,964,139.
- Owner
- Texas DOT
- Letting
- 05 SEP 2025
- Pay items
- 94
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Lone Star Paving Company | $17,520,874 | Low | -30% |
| 2 | Texas Materials Group, Inc. | $17,993,689 | +3.0% | -28% |
| 3 | Hunter Industries, LTD. | $18,839,936 | +8.0% | -25% |
| 4 | Clark Construction of Texas, Inc. | $19,664,227 | +12% | -21% |
| 5 | CK Newberry, LLC | $20,320,879 | +16% | -19% |
Engineer's estimate: $24,964,139.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Lone Star Paving Company | 2. Texas Materials Group, Inc. | 3. Hunter Industries, LTD. | 4. Clark Construction of Texas, Inc. | 5. CK Newberry, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 28 | $4,200.00 | $1,590.00 | $3,520.00 | $250.00 | $500.00 | |
| 2 | Removing concrete (mowstrip) (104-7005) | LF | 970 | $25.00 | $7.20 | $12.00 | $9.90 | $11.25 | $20.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 2,770 | $33.00 | $19.80 | $48.40 | $20.40 | $25.00 | |
| 4 | Embankment (final)(DC)(type C1) (132-7008) | CY | 12,291 | $23.00 | $17.25 | $28.36 | $17.56 | $28.00 | |
| 5 | Backfill (type A) (134-7001) | STA | 91 | $170.00 | $117.00 | $126.50 | $390.60 | $100.00 | |
| 6 | Furn & place topsoil (4") (160-7002) | SY | 9,405 | $3.00 | $3.00 | $0.88 | $6.75 | $2.50 | |
| 7 | Broadcast seed (temporary_warm) (164-7005) | SY | 4,720 | $0.20 | $0.18 | $0.18 | $1.50 | $0.15 | |
| 8 | Broadcast seed (temporary_cool) (164-7006) | SY | 4,720 | $0.20 | $0.18 | $0.18 | $1.50 | $0.15 | |
| 9 | Drill seed (permanent_rural_clay) (164-7010) | SY | 9,405 | $0.20 | $0.25 | $0.25 | $1.00 | $0.25 | |
| 10 | Vegetative watering (168-7001) | TGL | 149 | $200.00 | $40.00 | $22.89 | $50.00 | $20.00 | |
| 11 | FL BS(cip)(type D, GR 1-2 or 5)(final pos) (247-7192) | CY | 1,483 | $120.00 | $85.15 | $68.03 | $89.32 | $80.00 | |
| 12 | Prime coat (MC-30) (310-7004) | GAL | 2,407 | $4.00 | $5.00 | $4.08 | $9.50 | $4.50 | |
| 13 | D-GR HMA type-B PG64-22 (341-7001) | TON | 14,038 | $83.00 | $92.00 | $83.76 | $116.41 | $95.00 | |
| 14 | D-GR HMA type D PG76-22 (341-7056) | TON | 2,206 | $135.00 | $116.00 | $125.00 | $94.46 | $135.49 | $160.00 |
| 15 | Stone-MTRX-asphalt SMA-D sac-A PG76-22 (346-7009) | TON | 89,210 | $140.00 | $131.00 | $130.00 | $133.70 | $147.96 | $150.00 |
| 16 | Flexible pavement structure repair(4") (351-7003) | SY | 6,015 | $45.00 | $37.00 | $40.25 | $42.58 | $27.39 | $52.00 |
| 17 | Plane & text asphalt concrete pavement(0" to 2") (354-7002) | SY | 6,102 | $5.00 | $5.00 | $2.75 | $1.65 | $2.00 | $2.00 |
| 18 | Plane & text asphalt concrete pavement(2") (354-7019) | SY | 733,474 | $3.00 | $0.70 | $1.25 | $1.69 | $2.00 | $0.75 |
| 19 | Planing asphalt concrete pavement(9") (354-7058) | SY | 13,897 | $10.00 | $6.75 | $1.66 | $8.26 | $3.00 | |
| 20 | Cut & restoring pavement (400-7006) | SY | 60 | $800.00 | $200.00 | $124.24 | $160.00 | $150.00 | |
| 21 | Trench excavation protection (402-7001) | LF | 90 | $36.00 | $35.00 | $32.41 | $25.00 | $35.00 | |
| 22 | Drilled shaft (42 in) (416-7007) | LF | 34 | $450.00 | $660.00 | $410.00 | $410.00 | $640.00 | $410.00 |
| 23 | Drilled shaft (sign mounts) (48 in) (416-7032) | LF | 44 | $800.00 | $670.00 | $415.00 | $415.00 | $650.00 | $415.00 |
| 24 | Riprap (concrete)(CL B) (432-7005) | CY | 6 | $800.00 | $1,600.00 | $1,000.00 | $777.85 | $550.00 | $950.00 |
| 25 | Riprap (mow strip)(4 in) (432-7013) | CY | 121 | $750.00 | $720.00 | $700.00 | $691.42 | $650.00 | $700.00 |
| 26 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 1,440 | $60.00 | $48.40 | $110.00 | $41.50 | $45.00 | $110.00 |
| 27 | RC pipe (CL III)(24 in) (464-7005) | LF | 101 | $160.00 | $155.00 | $486.15 | $85.00 | $155.00 | |
| 28 | Inlet (complete)(pazd)(SL)(3FTX3FT) (465-7149) | EACH | 2 | $5,613.50 | $5,555.00 | $8,642.74 | $14,000 | $5,500.00 | |
| 29 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 1 | $3,350.00 | $3,250.00 | $3,781.20 | $3,800.00 | $3,250.00 | |
| 30 | Clean existing culverts (480-7001) | EACH | 3 | $5,800.00 | $4,500.00 | $1,500.00 | $5,000.00 | $3,000.00 | |
| 31 | Removing structure (inlet) (496-7002) | EACH | 1 | $875.00 | $850.00 | $1,296.41 | $500.00 | $850.00 | |
| 32 | Removing structure (set) (496-7004) | EACH | 1 | $257.00 | $250.00 | $1,296.41 | $500.00 | $250.00 | |
| 33 | Removing structure (pipe) (496-7007) | LF | 80 | $10.00 | $10.00 | $32.41 | $30.00 | $10.00 | |
| 34 | Mobilization (500-7001) | LS | 1 | $2,678,742 | $800,000 | $1,120,000 | $1,078,674 | $350,000 | $1,000,000 |
| 35 | Barricades, signs and traffic handling (502-7001) | MO | 10 | $15,000 | $5,000.00 | $8,300.00 | $5,909.52 | $2,222.00 | $40,000 |
| 36 | Portable changeable message sign (503-7002) | EACH | 4 | $12,000 | $5,500.00 | $10,000 | $7,500.00 | $12,000 | $20,000 |
| 37 | TMA (stationary) (505-7001) | DAY | 96 | $350.00 | $300.00 | $200.00 | $150.00 | $100.00 | $200.00 |
| 38 | TMA (mobile operation) (505-7003) | DAY | 20 | $400.00 | $250.00 | $200.00 | $250.00 | $100.00 | $200.00 |
| 39 | Rock filter dams (install) (type 3) (506-7003) | LF | 351 | $82.00 | $80.00 | $80.00 | $65.00 | $80.00 | |
| 40 | Rock filter dams (remove) (506-7011) | LF | 351 | $10.30 | $10.00 | $10.00 | $10.00 | $10.00 | |
| 41 | Temporary sediment control fence (install) (506-7039) | LF | 16,729 | $2.80 | $2.75 | $2.75 | $3.75 | $2.75 | |
| 42 | Temporary sediment control fence (remove) (506-7041) | LF | 16,729 | $0.90 | $0.85 | $0.85 | $0.50 | $0.85 | |
| 43 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 156 | $5.00 | $5.00 | $5.00 | $8.00 | $5.00 | |
| 44 | Biodegradable erosion control logs (remove) (506-7046) | LF | 156 | $1.00 | $1.00 | $1.00 | $2.00 | $1.00 | |
| 45 | Concrete sidewalks (4") (531-7001) | SY | 16 | $270.00 | $265.00 | $432.14 | $285.00 | $250.00 | |
| 46 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 300,186 | $0.20 | $0.11 | $0.11 | $0.23 | $0.10 | |
| 47 | Metal W-beam guard fence (timber post) (540-7001) | LF | 1,425 | $32.00 | $27.00 | $27.25 | $25.00 | $28.50 | $26.00 |
| 48 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 16 | $2,700.00 | $1,990.00 | $2,660.00 | $2,500.00 | $2,500.00 | $2,000.00 |
| 49 | Downstream anchor terminal section (540-7015) | EACH | 8 | $1,700.00 | $1,350.00 | $1,150.00 | $1,300.00 | $1,500.00 | $1,500.00 |
| 50 | Metal beam guard fence trans (anchor plate) (540-7029) | EACH | 16 | $1,000.00 | $1,290.00 | $980.00 | $900.00 | $1,150.00 | $1,100.00 |
| 51 | Remove metal beam guard fence (542-7001) | LF | 1,325 | $5.00 | $6.00 | $3.00 | $2.50 | $2.50 | $3.50 |
| 52 | Remove downstream anchor terminal (542-7003) | EACH | 8 | $350.00 | $215.00 | $230.00 | $250.00 | $250.00 | $250.00 |
| 53 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 16 | $400.00 | $327.00 | $260.00 | $250.00 | $250.00 | $250.00 |
| 54 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $3,600.00 | $3,700.00 | $3,240.00 | $3,100.00 | $3,500.00 | $3,400.00 |
| 55 | Guardrail end treatment (remove) (544-7003) | EACH | 8 | $600.00 | $440.00 | $330.00 | $250.00 | $250.00 | $250.00 |
| 56 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 755 | $19.50 | $14.50 | $12.00 | $12.00 | $14.00 | $12.00 |
| 57 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 240 | $28.00 | $56.00 | $35.00 | $35.00 | $54.00 | $35.00 |
| 58 | Conduit (RM) (2") (618-7078) | LF | 200 | $55.00 | $9.00 | $25.00 | $25.00 | $9.00 | $25.00 |
| 59 | Electrical conductor (no.8) bare (620-7007) | LF | 995 | $2.33 | $2.00 | $2.00 | $2.00 | $2.25 | $2.00 |
| 60 | Electrical conductor (no.8) insulated (620-7008) | LF | 1,990 | $2.48 | $2.00 | $2.50 | $2.50 | $2.25 | $2.50 |
| 61 | Ground box type A (122311)W/apron (624-7002) | EACH | 8 | $1,863.00 | $1,650.00 | $1,100.00 | $1,100.00 | $1,600.00 | $1,100.00 |
| 62 | Elc SRV type D 120/240 060(NS)SS(N)SP(O) (628-7156) | EACH | 3 | $10,150 | $8,400.00 | $7,400.00 | $7,400.00 | $8,100.00 | $7,500.00 |
| 63 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 3 | $500.00 | $560.00 | $850.00 | $1,350.00 | $2,500.00 | $2,500.00 |
| 64 | Remove SM RD SN sup&AM (644-7073) | EACH | 3 | $60.00 | $100.00 | $110.00 | $125.00 | $85.00 | $2,500.00 |
| 65 | Replace lrsa (647-7009) | EACH | 1 | $3,500.00 | $9,700.00 | $9,350.00 | $9,350.00 | $500.00 | $10,000 |
| 66 | Install overhead sign support(30 FT bal tee) (650-7028) | EACH | 2 | $73,335 | $39,000 | $47,000 | $47,000 | $37,900 | $50,000 |
| 67 | Replace delineator assembly (D-SW)SZ 1(WFLX)GNDHH (658-7163) | EACH | 4 | $65.00 | $130.00 | $183.00 | $425.00 | $185.00 | $100.00 |
| 68 | Replace delineator assembly (D-SY)SZ 1(yflx)GNDHH (658-7189) | EACH | 4 | $80.00 | $130.00 | $183.00 | $425.00 | $185.00 | $100.00 |
| 69 | Install object marker assembly (OM-2Y)(WC)GNDLL(BI) (658-7247) | EACH | 2 | $75.00 | $100.00 | $71.00 | $150.00 | $185.00 | $50.00 |
| 70 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 39,452 | $1.00 | $0.20 | $0.19 | $0.52 | $0.15 | $0.25 |
| 71 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 270,437 | $1.00 | $0.20 | $0.19 | $0.52 | $0.15 | $0.25 |
| 72 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 56,970 | $2.00 | $1.00 | $1.50 | $1.63 | $1.00 | $0.55 |
| 73 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 1,012 | $2.00 | $1.00 | $1.00 | $1.10 | $1.00 | $2.50 |
| 74 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 11,502 | $2.00 | $1.00 | $0.84 | $0.88 | $0.85 | $1.00 |
| 75 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 250 | $10.00 | $3.00 | $3.00 | $2.00 | $2.50 | $4.50 |
| 76 | Reflectorized pavement marking type I(W)(entr gore)(100MIL) (666-7069) | EACH | 21 | $1,000.00 | $620.00 | $1,000.00 | $1,250.00 | $1,250.00 | $750.00 |
| 77 | Reflectorized pavement marking type II (W) 18" (yld tri) (666-7200) | EACH | 2 | $25.00 | $10.30 | $20.00 | $50.00 | $20.00 | $50.00 |
| 78 | Reflectorized pavement marking type I (W)4"(solid)(100MIL) (666-7405) | LF | 101 | $0.45 | $1.00 | $2.00 | $3.00 | $1.00 | $1.00 |
| 79 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 39,452 | $0.65 | $0.60 | $0.54 | $0.72 | $0.50 | $0.60 |
| 80 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 270,437 | $0.65 | $0.60 | $0.53 | $0.62 | $0.50 | $0.60 |
| 81 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 180,332 | $0.85 | $0.60 | $0.53 | $0.66 | $0.50 | $0.60 |
| 82 | Pre PM type B (WHT)(acc PRK)(symbol only) (668-7070) | EACH | 2 | $800.00 | $310.00 | $300.00 | $1,500.00 | $300.00 | $250.00 |
| 83 | Prefabricated PM type C (white)(evac sym) (668-7139) | EACH | 41 | $450.00 | $410.00 | $400.00 | $750.00 | $400.00 | $600.00 |
| 84 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 2,187 | $7.00 | $4.00 | $3.80 | $7.50 | $5.00 | $5.00 |
| 85 | Underseal course (3006-7001) | GAL | 116,345 | $6.00 | $3.80 | $3.80 | $4.50 | $4.35 | $4.50 |
| 86 | Bonding course (3007-7001) | GAL | 100,151 | $5.00 | $0.50 | $0.10 | $1.07 | $0.10 | $3.50 |
| 87 | Install DMS (pole MTD cabinet) (6004-7001) | EACH | 2 | $12,000 | $12,500 | $9,000.00 | $9,000.00 | $12,100 | $10,000 |
| 88 | ITS com CBL (ethernet) (6005-7001) | LF | 400 | $3.50 | $2.00 | $2.75 | $2.75 | $1.75 | $3.00 |
| 89 | ITS pole MNT cab (type 2)(conf 2) (6011-7002) | EACH | 2 | $6,000.00 | $5,800.00 | $2,735.00 | $2,735.00 | $5,700.00 | $3,000.00 |
| 90 | ITS pole (40 FT)(90 MPH) (6011-7020) | EACH | 2 | $13,232 | $14,000 | $17,760 | $17,760 | $13,700 | $18,000 |
| 91 | Installation of cellular modem (6015-7001) | EACH | 4 | $1,200.00 | $550.00 | $530.00 | $530.00 | $540.00 | $550.00 |
| 92 | CCTV field equipment (digital) (6018-7002) | EACH | 2 | $6,938.92 | $10,000 | $9,800.00 | $9,800.00 | $10,500 | $10,000 |
| 93 | CCTV mount (pole) (6018-7003) | EACH | 2 | $673.00 | $130.00 | $100.00 | $100.00 | $130.00 | $100.00 |
| 94 | Ethernet switch (install only) (6036-7001) | EACH | 4 | $1,000.00 | $580.00 | $400.00 | $400.00 | $570.00 | $400.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 5, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.