TxDOT contract A00063678 bid tabulation
Resurface Roadway, IH 35 (IH 410 to W. Mayfield Drive). Let by Texas DOT on February 4, 2026, Bexar, San Antonio District. 4 bids received; low bid $15,028,560 by Lone Star Paving Company, -19% against the engineer's estimate of $18,518,603.
- Owner
- Texas DOT
- Letting
- 04 FEB 2026
- Pay items
- 129
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Lone Star Paving Company | $15,028,560 | Low | -19% |
| 2 | Texas Materials Group, Inc. | $15,980,512 | +6.0% | -14% |
| 3 | Hunter Industries, LTD. | $16,117,333 | +7.0% | -13% |
| 4 | Clark Construction of Texas, Inc. | $18,219,172 | +21% | -2.0% |
Engineer's estimate: $18,518,603.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Lone Star Paving Company | 2. Texas Materials Group, Inc. | 3. Hunter Industries, LTD. | 4. Clark Construction of Texas, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7001) | ACRE | 0.31 | $15,000 | $50,000 | $82,600 | $43,632 | $0.10 |
| 2 | Removing concrete (mowstrip) (104-7005) | LF | 5,512.50 | $17.19 | $11.00 | $14.00 | $9.90 | $10.00 |
| 3 | Remove (0"-4") TRT/untrt base & asphalt pavement (105-7001) | SY | 140 | $17.05 | $30.00 | $6.00 | $6.60 | $20.00 |
| 4 | Remove (12"-30") TRT/untrt base & asphalt pavement (105-7121) | SY | 1,134 | $14.30 | $30.00 | $22.50 | $12.10 | $17.78 |
| 5 | Excavation (roadway) (110-7001) | CY | 1,360 | $18.80 | $15.00 | $24.25 | $23.10 | $21.38 |
| 6 | Embankment (final)(OC)(type B) (132-7003) | CY | 806 | $33.82 | $9.50 | $49.00 | $23.10 | $36.00 |
| 7 | Blading (150-7002) | HR | 24 | $137.00 | $125.00 | $170.00 | $110.00 | $240.00 |
| 8 | Compost manuf topsoil (4") (161-7002) | SY | 8,636 | $1.99 | $1.40 | $1.40 | $1.57 | $5.90 |
| 9 | Hydro mulch seed (permanent_rural_sandy) (164-7017) | SY | 8,636 | $0.61 | $0.68 | $0.68 | $0.76 | $0.70 |
| 10 | Vegetative watering (168-7001) | TGL | 135.19 | $29.27 | $30.00 | $50.00 | $36.30 | $50.00 |
| 11 | Soil ret BLKT(SL_mod_sand_short) (169-7003) | SY | 1,970 | $1.25 | $2.00 | $2.00 | $2.25 | $2.45 |
| 12 | FL BS (cip)(type A GR 1-2 or 5) final pos (247-7348) | CY | 2,222 | $83.85 | $80.00 | $72.00 | $67.48 | $60.07 |
| 13 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 228 | $4.68 | $7.00 | $9.60 | $6.60 | $47.16 |
| 14 | D-GR HMA type-C PG76-22 (341-7030) | TON | 913 | $111.13 | $118.00 | $98.00 | $108.90 | $182.34 |
| 15 | D-GR HMA type D PG76-22 (level-UP) (341-7059) | TON | 617 | $114.86 | $140.00 | $137.00 | $108.90 | $322.53 |
| 16 | Stone-MTRX-asphalt SMA-D sac-A HPG (346-7016) | TON | 45,420 | $197.84 | $162.50 | $172.50 | $159.50 | $198.00 |
| 17 | Flexible pavement structure repair(6") (351-7005) | SY | 71,051 | $39.45 | $39.50 | $37.75 | $44.59 | $43.28 |
| 18 | Flex. pave. structure repair 6" to 9" (351-7033) | SY | 2,981 | $78.90 | $45.00 | $54.45 | $66.42 | $80.78 |
| 19 | Planing asphalt concrete pavement(0" to 6") (354-7035) | SY | 47,972 | $6.75 | $2.50 | $3.60 | $4.62 | $5.87 |
| 20 | Planing asphalt concrete pavement(2") (354-7051) | SY | 346,881 | $1.50 | $1.90 | $2.00 | $1.98 | $1.70 |
| 21 | Riprap (mow strip)(4 in) (432-7013) | CY | 1,023.80 | $630.29 | $515.00 | $723.00 | $660.40 | $585.00 |
| 22 | Cleaning existing joints (438-7008) | LF | 3,966 | $17.77 | $12.00 | $12.00 | $13.65 | $8.50 |
| 23 | Header type expansion joint (454-7009) | CF | 661.20 | $576.72 | $289.00 | $289.00 | $335.96 | $383.87 |
| 24 | Joint sealant (454-7010) | LF | 4,034 | $23.74 | $10.00 | $10.00 | $11.55 | $10.50 |
| 25 | Clean existing culverts (480-7001) | EACH | 2 | $4,300.00 | $2,850.00 | $3,500.00 | $2,200.00 | $5,000.00 |
| 26 | Mobilization (500-7001) | LS | 1 | $1,345,000 | $400,000 | $720,000 | $989,389 | $1,000,000 |
| 27 | Barricades, signs and traffic handling (502-7001) | MO | 17 | $13,715 | $6,800.00 | $10,700 | $9,473.41 | $2,200.00 |
| 28 | Portable changeable message sign (503-7001) | DAY | 532 | $80.57 | $80.00 | $50.00 | $80.11 | $75.00 |
| 29 | TMA (stationary) (505-7001) | DAY | 304 | $102.72 | $300.00 | $100.00 | $106.81 | $75.00 |
| 30 | TMA (mobile operation) (505-7003) | DAY | 126 | $141.08 | $300.00 | $100.00 | $267.02 | $75.00 |
| 31 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 21,686 | $3.80 | $3.80 | $3.80 | $4.27 | $3.75 |
| 32 | Biodegradable erosion control logs (remove) (506-7046) | LF | 21,686 | $0.85 | $0.80 | $0.80 | $0.90 | $1.00 |
| 33 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 1,920 | $58.27 | $65.00 | $24.00 | $30.00 | $65.00 |
| 34 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 1,920 | $14.35 | $40.00 | $24.00 | $15.00 | $40.00 |
| 35 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 86,864 | $0.32 | $0.30 | $0.14 | $0.20 | $0.28 |
| 36 | Metal W-beam guard fence (timber post) (540-7001) | LF | 17,550 | $24.54 | $20.25 | $24.25 | $21.52 | $21.50 |
| 37 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 31 | $2,269.79 | $2,015.00 | $3,200.00 | $2,141.13 | $2,000.00 |
| 38 | Downstream anchor terminal section (540-7015) | EACH | 34 | $1,136.87 | $1,125.00 | $1,250.00 | $1,195.42 | $1,200.00 |
| 39 | Metal beam guard fence (long span system) (540-7027) | EACH | 1 | $1,226.93 | $1,250.00 | $1,500.00 | $1,328.25 | $600.00 |
| 40 | Metal beam guard fence trans (anchor plate) (540-7029) | EACH | 10 | $706.52 | $875.00 | $1,000.00 | $929.77 | $800.00 |
| 41 | Remove metal beam guard fence (542-7001) | LF | 17,422 | $3.41 | $2.00 | $2.00 | $2.13 | $2.00 |
| 42 | Remove terminal anchor section (542-7002) | EACH | 32 | $267.72 | $200.00 | $200.00 | $212.52 | $225.00 |
| 43 | Remove downstream anchor terminal (542-7003) | EACH | 1 | $164.48 | $200.00 | $200.00 | $212.52 | $225.00 |
| 44 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 2 | $320.73 | $200.00 | $200.00 | $212.52 | $225.00 |
| 45 | Guardrail end treatment (install) (544-7001) | EACH | 31 | $2,966.87 | $2,725.00 | $3,000.00 | $2,895.58 | $3,200.00 |
| 46 | Guardrail end treatment (remove) (544-7003) | EACH | 30 | $273.71 | $200.00 | $200.00 | $212.52 | $250.00 |
| 47 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $1,139.63 | $800.00 | $650.00 | $1,275.12 | $800.00 |
| 48 | Cca (install)(N)(TL3)(work zone) (545-7018) | EACH | 2 | $11,420 | $5,100.00 | $8,000.00 | $9,563.37 | $5,100.00 |
| 49 | Replace luminaire W/(250W EQ) LED (610-7012) | EACH | 6 | $623.12 | $1,100.00 | $1,100.00 | $1,154.86 | $1,100.00 |
| 50 | Replace luminaire W/(400W EQ) LED (610-7013) | EACH | 8 | $945.00 | $1,200.00 | $1,200.00 | $1,259.85 | $1,200.00 |
| 51 | Replace LED HI MST IL(6 fixt) (type S) (614-7005) | EACH | 4 | $7,432.90 | $12,800 | $12,800 | $13,438 | $12,800 |
| 52 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 40 | $19.46 | $56.00 | $56.00 | $58.79 | $56.00 |
| 53 | Conduit (PVC) (schedule 80) (3") (618-7060) | LF | 40 | $24.63 | $56.00 | $56.00 | $58.79 | $56.00 |
| 54 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 100 | $32.11 | $100.00 | $100.00 | $104.99 | $100.00 |
| 55 | Conduit (PVC) (schedule 80) (4") (bore) (618-7065) | LF | 80 | $43.23 | $120.00 | $120.00 | $125.98 | $120.00 |
| 56 | Electrical conductor (no.14) insulated (620-7002) | LF | 260 | $1.20 | $2.20 | $2.20 | $2.31 | $2.20 |
| 57 | Ground box type D (162922)W/apron (624-7008) | EACH | 4 | $1,805.79 | $2,700.00 | $2,700.00 | $2,834.66 | $2,700.00 |
| 58 | Remove ground box (624-7013) | EACH | 4 | $421.33 | $180.00 | $180.00 | $188.98 | $180.00 |
| 59 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 63 | $730.55 | $550.00 | $550.00 | $577.43 | $850.00 |
| 60 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 100 | $789.35 | $730.00 | $730.00 | $766.41 | $885.00 |
| 61 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 2 | $896.39 | $800.00 | $800.00 | $839.90 | $800.00 |
| 62 | Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009) | EACH | 1 | $771.78 | $650.00 | $650.00 | $682.42 | $865.00 |
| 63 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 22 | $952.79 | $850.00 | $850.00 | $892.39 | $1,050.00 |
| 64 | In bridge MNT clearance sign assembly(type N) (644-7061) | EACH | 2 | $2,201.56 | $3,400.00 | $3,400.00 | $3,569.57 | $1,200.00 |
| 65 | In bridge MNT clearance sign assembly(type S) (644-7062) | EACH | 3 | $1,742.50 | $3,500.00 | $3,500.00 | $3,674.55 | $1,200.00 |
| 66 | Remove SM RD SN sup&AM (644-7073) | EACH | 165 | $100.61 | $100.00 | $100.00 | $104.99 | $120.00 |
| 67 | Remove BRDG MNT clearance sign assembly (644-7074) | EACH | 5 | $223.33 | $350.00 | $350.00 | $367.46 | $100.00 |
| 68 | Remove SM RD SN sup&AM (sign only) (644-7075) | EACH | 5 | $52.19 | $25.00 | $25.00 | $26.25 | $50.00 |
| 69 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 79 | $23.76 | $20.00 | $20.00 | $21.00 | $78.00 |
| 70 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 214 | $30.40 | $28.00 | $45.00 | $29.40 | $85.00 |
| 71 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 40 | $24.01 | $20.00 | $20.00 | $21.00 | $85.00 |
| 72 | Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036) | EACH | 104 | $28.00 | $28.00 | $45.00 | $29.40 | $60.00 |
| 73 | Install delineator assembly (D-SY)SZ 1(BRF)GF2(BI) (658-7037) | EACH | 50 | $30.00 | $28.00 | $45.00 | $29.40 | $75.00 |
| 74 | Install OM SM RD sign (1-OM-PW)Y (658-7317) | EACH | 154 | $10.00 | $10.00 | $10.00 | $10.50 | $125.00 |
| 75 | Install OM SM RD sign (1-OM-PW)R (658-7318) | EACH | 34 | $10.00 | $10.00 | $10.00 | $10.50 | $125.00 |
| 76 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 24,219 | $0.41 | $0.21 | $0.21 | $0.22 | $0.50 |
| 77 | Work zone pavement marking non-removing (W)6"(DOT) (662-7006) | LF | 2,324 | $1.19 | $0.30 | $0.30 | $0.31 | $0.50 |
| 78 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 84,290 | $0.45 | $0.19 | $0.19 | $0.20 | $0.50 |
| 79 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 2,877 | $1.16 | $0.40 | $0.40 | $0.42 | $0.60 |
| 80 | Work zone pavement marking non-removing (W)12"(DOT) (662-7013) | LF | 321 | $1.79 | $1.75 | $1.75 | $1.84 | $3.00 |
| 81 | Work zone pavement marking non-removing (W)12"(solid) (662-7015) | LF | 2,053 | $3.79 | $1.00 | $1.00 | $1.05 | $3.00 |
| 82 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 604 | $6.19 | $2.00 | $2.00 | $2.10 | $6.00 |
| 83 | Work zone pavement marking non-removing (W)(arrow) (662-7018) | EACH | 3 | $88.05 | $40.00 | $40.00 | $41.99 | $100.00 |
| 84 | Work zone pavement marking non-removing (W)(entr gore) (662-7020) | EACH | 18 | $300.00 | $500.00 | $500.00 | $524.94 | $500.00 |
| 85 | Work zone pavement marking non-removing (W)(exit gore) (662-7021) | EACH | 19 | $300.00 | $500.00 | $500.00 | $524.94 | $800.00 |
| 86 | Work zone pavement marking non-removing(W)(word) (662-7030) | EACH | 14 | $157.25 | $45.00 | $45.00 | $47.24 | $125.00 |
| 87 | Work zone pavement marking non-removing(W)36"(yld tri) (662-7032) | EACH | 39 | $21.59 | $10.00 | $10.00 | $10.50 | $20.00 |
| 88 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 86,197 | $0.37 | $0.19 | $0.19 | $0.20 | $0.50 |
| 89 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 7,080 | $0.79 | $0.50 | $0.50 | $0.52 | $5.00 |
| 90 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 7,266 | $1.65 | $0.75 | $1.65 | $1.72 | $1.00 |
| 91 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 2,324 | $1.29 | $0.60 | $0.60 | $0.63 | $2.50 |
| 92 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 2,877 | $1.00 | $0.80 | $0.80 | $0.84 | $1.25 |
| 93 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 2,053 | $2.98 | $2.60 | $2.60 | $2.73 | $3.50 |
| 94 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 604 | $6.52 | $6.25 | $6.25 | $6.56 | $7.50 |
| 95 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 3 | $139.31 | $150.00 | $150.00 | $157.48 | $125.00 |
| 96 | Reflectorized pavement marking type I (W)(number)(100MIL) (666-7063) | EACH | 11 | $63.31 | $200.00 | $200.00 | $209.97 | $50.00 |
| 97 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 3 | $173.39 | $156.00 | $156.00 | $163.78 | $150.00 |
| 98 | Reflectorized pavement marking type I(W)(entr gore)(100MIL) (666-7069) | EACH | 18 | $700.00 | $1,200.00 | $1,200.00 | $1,259.85 | $750.00 |
| 99 | Reflectorized pavement marking type I(W)(exit gore)(100MIL) (666-7072) | EACH | 19 | $790.87 | $1,500.00 | $1,500.00 | $1,574.81 | $1,500.00 |
| 100 | Ref pavement marking type I(W)36"(yld tri)(100MIL) (666-7090) | EACH | 39 | $51.03 | $27.00 | $27.00 | $28.35 | $25.00 |
| 101 | Pavement sler 6" (666-7347) | LF | 192,100 | $0.26 | $0.10 | $0.10 | $0.10 | $0.30 |
| 102 | Pavement sler 8" (666-7348) | LF | 2,877 | $0.40 | $0.13 | $0.13 | $0.14 | $0.35 |
| 103 | Pavement sler 12" (666-7350) | LF | 2,374 | $1.99 | $0.40 | $0.40 | $0.42 | $1.50 |
| 104 | Pavement sler 24" (666-7352) | LF | 604 | $2.78 | $0.70 | $0.70 | $0.73 | $3.00 |
| 105 | Pavement sler (arrow) (666-7353) | EACH | 3 | $52.27 | $10.00 | $10.00 | $10.50 | $65.00 |
| 106 | Pavement sler (word) (666-7354) | EACH | 3 | $56.13 | $10.00 | $10.00 | $10.50 | $75.00 |
| 107 | Pavement sler (entr gore) (666-7361) | EACH | 18 | $106.16 | $100.00 | $100.00 | $104.99 | $200.00 |
| 108 | Pavement sler (exit gore) (666-7362) | EACH | 19 | $130.65 | $100.00 | $100.00 | $104.99 | $500.00 |
| 109 | Pavement sler (yld tri) (666-7365) | EACH | 39 | $17.06 | $10.00 | $10.00 | $10.50 | $20.00 |
| 110 | Pavement sler (number) (666-7367) | EACH | 11 | $5.00 | $10.00 | $10.00 | $10.50 | $50.00 |
| 111 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 23,489 | $0.55 | $0.53 | $0.53 | $0.56 | $0.85 |
| 112 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 80,090 | $0.50 | $0.53 | $0.53 | $0.56 | $0.85 |
| 113 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 86,197 | $0.51 | $0.53 | $0.53 | $0.56 | $0.85 |
| 114 | Reflectorized pavement marking type I (W)12"(DOT)(100MIL) (666-7424) | LF | 321 | $3.00 | $1.00 | $1.00 | $1.05 | $1.75 |
| 115 | Reflectorized pavement marker type I-C (672-7002) | EACH | 89 | $3.63 | $4.00 | $4.00 | $4.20 | $5.00 |
| 116 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 2,477 | $3.59 | $3.65 | $3.65 | $3.83 | $5.00 |
| 117 | Eliminating existing PM & markers (6") (677-7002) | LF | 4,930 | $0.71 | $0.80 | $0.80 | $0.84 | $1.00 |
| 118 | Vehicle LP detect (sawcut) (688-7004) | LF | 365 | $17.10 | $37.00 | $37.00 | $38.85 | $37.00 |
| 119 | Replace luminaire pole (690-7126) | EACH | 5 | $2,510.25 | $1,700.00 | $1,700.00 | $1,784.78 | $1,700.00 |
| 120 | Maintain roadway illumination (690-7184) | EACH | 10 | $600.00 | $440.00 | $440.00 | $461.94 | $440.00 |
| 121 | Replace transformer base (690-7197) | EACH | 5 | $829.69 | $1,600.00 | $1,600.00 | $1,679.80 | $1,600.00 |
| 122 | Replace fuse (690-7218) | EACH | 5 | $56.59 | $120.00 | $120.00 | $125.98 | $120.00 |
| 123 | Replace luminaire (LED) (690-7264) | EACH | 10 | $500.00 | $540.00 | $540.00 | $566.93 | $540.00 |
| 124 | Debris removal (spot debris) (735-7072) | MI | 1.29 | $55,115 | $8,000.00 | $10,000 | $500.00 | $69,054 |
| 125 | Underseal course (3006-7001) | GAL | 16,842 | $3.50 | $4.80 | $0.05 | $3.68 | $0.01 |
| 126 | Bonding course (3007-7001) | GAL | 79,277 | $4.25 | $3.00 | $3.55 | $3.30 | $3.55 |
| 127 | Relocate backlit LED RDSD sign (6030-7005) | EACH | 1 | $2,000.00 | $530.00 | $530.00 | $556.43 | $530.00 |
| 128 | Loop installation (6041-7001) | LF | 625 | $35.00 | $13.00 | $13.00 | $13.65 | $13.00 |
| 129 | Sensor installation (6041-7002) | EACH | 4 | $20,000 | $2,000.00 | $2,000.00 | $2,099.74 | $2,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 4, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.