TxDOT contract A00063678 bid tabulation

Resurface Roadway, IH 35 (IH 410 to W. Mayfield Drive). Let by Texas DOT on February 4, 2026, Bexar, San Antonio District. 4 bids received; low bid $15,028,560 by Lone Star Paving Company, -19% against the engineer's estimate of $18,518,603.

Owner
Texas DOT
Letting
04 FEB 2026
Pay items
129
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Lone Star Paving Company$15,028,560Low-19%
2Texas Materials Group, Inc.$15,980,512+6.0%-14%
3Hunter Industries, LTD.$16,117,333+7.0%-13%
4Clark Construction of Texas, Inc.$18,219,172+21%-2.0%
TxDOT contract A00063678: bids by rank

Engineer's estimate: $18,518,603.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Lone Star Paving Company2. Texas Materials Group, Inc.3. Hunter Industries, LTD.4. Clark Construction of Texas, Inc.
1Preparing row (100-7001)ACRE0.31$15,000$50,000$82,600$43,632$0.10
2Removing concrete (mowstrip) (104-7005)LF5,512.50$17.19$11.00$14.00$9.90$10.00
3Remove (0"-4") TRT/untrt base & asphalt pavement (105-7001)SY140$17.05$30.00$6.00$6.60$20.00
4Remove (12"-30") TRT/untrt base & asphalt pavement (105-7121)SY1,134$14.30$30.00$22.50$12.10$17.78
5Excavation (roadway) (110-7001)CY1,360$18.80$15.00$24.25$23.10$21.38
6Embankment (final)(OC)(type B) (132-7003)CY806$33.82$9.50$49.00$23.10$36.00
7Blading (150-7002)HR24$137.00$125.00$170.00$110.00$240.00
8Compost manuf topsoil (4") (161-7002)SY8,636$1.99$1.40$1.40$1.57$5.90
9Hydro mulch seed (permanent_rural_sandy) (164-7017)SY8,636$0.61$0.68$0.68$0.76$0.70
10Vegetative watering (168-7001)TGL135.19$29.27$30.00$50.00$36.30$50.00
11Soil ret BLKT(SL_mod_sand_short) (169-7003)SY1,970$1.25$2.00$2.00$2.25$2.45
12FL BS (cip)(type A GR 1-2 or 5) final pos (247-7348)CY2,222$83.85$80.00$72.00$67.48$60.07
13Prime coat(MC-30 or AE-P) (310-7013)GAL228$4.68$7.00$9.60$6.60$47.16
14D-GR HMA type-C PG76-22 (341-7030)TON913$111.13$118.00$98.00$108.90$182.34
15D-GR HMA type D PG76-22 (level-UP) (341-7059)TON617$114.86$140.00$137.00$108.90$322.53
16Stone-MTRX-asphalt SMA-D sac-A HPG (346-7016)TON45,420$197.84$162.50$172.50$159.50$198.00
17Flexible pavement structure repair(6") (351-7005)SY71,051$39.45$39.50$37.75$44.59$43.28
18Flex. pave. structure repair 6" to 9" (351-7033)SY2,981$78.90$45.00$54.45$66.42$80.78
19Planing asphalt concrete pavement(0" to 6") (354-7035)SY47,972$6.75$2.50$3.60$4.62$5.87
20Planing asphalt concrete pavement(2") (354-7051)SY346,881$1.50$1.90$2.00$1.98$1.70
21Riprap (mow strip)(4 in) (432-7013)CY1,023.80$630.29$515.00$723.00$660.40$585.00
22Cleaning existing joints (438-7008)LF3,966$17.77$12.00$12.00$13.65$8.50
23Header type expansion joint (454-7009)CF661.20$576.72$289.00$289.00$335.96$383.87
24Joint sealant (454-7010)LF4,034$23.74$10.00$10.00$11.55$10.50
25Clean existing culverts (480-7001)EACH2$4,300.00$2,850.00$3,500.00$2,200.00$5,000.00
26Mobilization (500-7001)LS1$1,345,000$400,000$720,000$989,389$1,000,000
27Barricades, signs and traffic handling (502-7001)MO17$13,715$6,800.00$10,700$9,473.41$2,200.00
28Portable changeable message sign (503-7001)DAY532$80.57$80.00$50.00$80.11$75.00
29TMA (stationary) (505-7001)DAY304$102.72$300.00$100.00$106.81$75.00
30TMA (mobile operation) (505-7003)DAY126$141.08$300.00$100.00$267.02$75.00
31Biodegradable erosion control logs (install) (8") (506-7043)LF21,686$3.80$3.80$3.80$4.27$3.75
32Biodegradable erosion control logs (remove) (506-7046)LF21,686$0.85$0.80$0.80$0.90$1.00
33Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001)LF1,920$58.27$65.00$24.00$30.00$65.00
34Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049)LF1,920$14.35$40.00$24.00$15.00$40.00
35Mill rumble strips (asphalt) (shoulder) (533-7001)LF86,864$0.32$0.30$0.14$0.20$0.28
36Metal W-beam guard fence (timber post) (540-7001)LF17,550$24.54$20.25$24.25$21.52$21.50
37Metal beam guard fence trans (thrie-beam) (540-7005)EACH31$2,269.79$2,015.00$3,200.00$2,141.13$2,000.00
38Downstream anchor terminal section (540-7015)EACH34$1,136.87$1,125.00$1,250.00$1,195.42$1,200.00
39Metal beam guard fence (long span system) (540-7027)EACH1$1,226.93$1,250.00$1,500.00$1,328.25$600.00
40Metal beam guard fence trans (anchor plate) (540-7029)EACH10$706.52$875.00$1,000.00$929.77$800.00
41Remove metal beam guard fence (542-7001)LF17,422$3.41$2.00$2.00$2.13$2.00
42Remove terminal anchor section (542-7002)EACH32$267.72$200.00$200.00$212.52$225.00
43Remove downstream anchor terminal (542-7003)EACH1$164.48$200.00$200.00$212.52$225.00
44RM metal beam guard fence trans (thrie-beam) (542-7004)EACH2$320.73$200.00$200.00$212.52$225.00
45Guardrail end treatment (install) (544-7001)EACH31$2,966.87$2,725.00$3,000.00$2,895.58$3,200.00
46Guardrail end treatment (remove) (544-7003)EACH30$273.71$200.00$200.00$212.52$250.00
47Crash cushion attenuator (remove) (545-7004)EACH2$1,139.63$800.00$650.00$1,275.12$800.00
48Cca (install)(N)(TL3)(work zone) (545-7018)EACH2$11,420$5,100.00$8,000.00$9,563.37$5,100.00
49Replace luminaire W/(250W EQ) LED (610-7012)EACH6$623.12$1,100.00$1,100.00$1,154.86$1,100.00
50Replace luminaire W/(400W EQ) LED (610-7013)EACH8$945.00$1,200.00$1,200.00$1,259.85$1,200.00
51Replace LED HI MST IL(6 fixt) (type S) (614-7005)EACH4$7,432.90$12,800$12,800$13,438$12,800
52Conduit (PVC) (schedule 80) (2") (618-7054)LF40$19.46$56.00$56.00$58.79$56.00
53Conduit (PVC) (schedule 80) (3") (618-7060)LF40$24.63$56.00$56.00$58.79$56.00
54Conduit (PVC) (schedule 80) (3") (bore) (618-7061)LF100$32.11$100.00$100.00$104.99$100.00
55Conduit (PVC) (schedule 80) (4") (bore) (618-7065)LF80$43.23$120.00$120.00$125.98$120.00
56Electrical conductor (no.14) insulated (620-7002)LF260$1.20$2.20$2.20$2.31$2.20
57Ground box type D (162922)W/apron (624-7008)EACH4$1,805.79$2,700.00$2,700.00$2,834.66$2,700.00
58Remove ground box (624-7013)EACH4$421.33$180.00$180.00$188.98$180.00
59Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH63$730.55$550.00$550.00$577.43$850.00
60Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH100$789.35$730.00$730.00$766.41$885.00
61Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007)EACH2$896.39$800.00$800.00$839.90$800.00
62Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009)EACH1$771.78$650.00$650.00$682.42$865.00
63Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH22$952.79$850.00$850.00$892.39$1,050.00
64In bridge MNT clearance sign assembly(type N) (644-7061)EACH2$2,201.56$3,400.00$3,400.00$3,569.57$1,200.00
65In bridge MNT clearance sign assembly(type S) (644-7062)EACH3$1,742.50$3,500.00$3,500.00$3,674.55$1,200.00
66Remove SM RD SN sup&AM (644-7073)EACH165$100.61$100.00$100.00$104.99$120.00
67Remove BRDG MNT clearance sign assembly (644-7074)EACH5$223.33$350.00$350.00$367.46$100.00
68Remove SM RD SN sup&AM (sign only) (644-7075)EACH5$52.19$25.00$25.00$26.25$50.00
69Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012)EACH79$23.76$20.00$20.00$21.00$78.00
70Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018)EACH214$30.40$28.00$45.00$29.40$85.00
71Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031)EACH40$24.01$20.00$20.00$21.00$85.00
72Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036)EACH104$28.00$28.00$45.00$29.40$60.00
73Install delineator assembly (D-SY)SZ 1(BRF)GF2(BI) (658-7037)EACH50$30.00$28.00$45.00$29.40$75.00
74Install OM SM RD sign (1-OM-PW)Y (658-7317)EACH154$10.00$10.00$10.00$10.50$125.00
75Install OM SM RD sign (1-OM-PW)R (658-7318)EACH34$10.00$10.00$10.00$10.50$125.00
76Work zone pavement marking non-removing (W)6"(broken) (662-7005)LF24,219$0.41$0.21$0.21$0.22$0.50
77Work zone pavement marking non-removing (W)6"(DOT) (662-7006)LF2,324$1.19$0.30$0.30$0.31$0.50
78Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF84,290$0.45$0.19$0.19$0.20$0.50
79Work zone pavement marking non-removing (W)8"(solid) (662-7012)LF2,877$1.16$0.40$0.40$0.42$0.60
80Work zone pavement marking non-removing (W)12"(DOT) (662-7013)LF321$1.79$1.75$1.75$1.84$3.00
81Work zone pavement marking non-removing (W)12"(solid) (662-7015)LF2,053$3.79$1.00$1.00$1.05$3.00
82Work zone pavement marking non-removing (W)24"(solid) (662-7017)LF604$6.19$2.00$2.00$2.10$6.00
83Work zone pavement marking non-removing (W)(arrow) (662-7018)EACH3$88.05$40.00$40.00$41.99$100.00
84Work zone pavement marking non-removing (W)(entr gore) (662-7020)EACH18$300.00$500.00$500.00$524.94$500.00
85Work zone pavement marking non-removing (W)(exit gore) (662-7021)EACH19$300.00$500.00$500.00$524.94$800.00
86Work zone pavement marking non-removing(W)(word) (662-7030)EACH14$157.25$45.00$45.00$47.24$125.00
87Work zone pavement marking non-removing(W)36"(yld tri) (662-7032)EACH39$21.59$10.00$10.00$10.50$20.00
88Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF86,197$0.37$0.19$0.19$0.20$0.50
89Work zone pavement marking removing (W)6"(solid) (662-7068)LF7,080$0.79$0.50$0.50$0.52$5.00
90Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH7,266$1.65$0.75$1.65$1.72$1.00
91Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009)LF2,324$1.29$0.60$0.60$0.63$2.50
92Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF2,877$1.00$0.80$0.80$0.84$1.25
93Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030)LF2,053$2.98$2.60$2.60$2.73$3.50
94Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF604$6.52$6.25$6.25$6.56$7.50
95Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042)EACH3$139.31$150.00$150.00$157.48$125.00
96Reflectorized pavement marking type I (W)(number)(100MIL) (666-7063)EACH11$63.31$200.00$200.00$209.97$50.00
97Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066)EACH3$173.39$156.00$156.00$163.78$150.00
98Reflectorized pavement marking type I(W)(entr gore)(100MIL) (666-7069)EACH18$700.00$1,200.00$1,200.00$1,259.85$750.00
99Reflectorized pavement marking type I(W)(exit gore)(100MIL) (666-7072)EACH19$790.87$1,500.00$1,500.00$1,574.81$1,500.00
100Ref pavement marking type I(W)36"(yld tri)(100MIL) (666-7090)EACH39$51.03$27.00$27.00$28.35$25.00
101Pavement sler 6" (666-7347)LF192,100$0.26$0.10$0.10$0.10$0.30
102Pavement sler 8" (666-7348)LF2,877$0.40$0.13$0.13$0.14$0.35
103Pavement sler 12" (666-7350)LF2,374$1.99$0.40$0.40$0.42$1.50
104Pavement sler 24" (666-7352)LF604$2.78$0.70$0.70$0.73$3.00
105Pavement sler (arrow) (666-7353)EACH3$52.27$10.00$10.00$10.50$65.00
106Pavement sler (word) (666-7354)EACH3$56.13$10.00$10.00$10.50$75.00
107Pavement sler (entr gore) (666-7361)EACH18$106.16$100.00$100.00$104.99$200.00
108Pavement sler (exit gore) (666-7362)EACH19$130.65$100.00$100.00$104.99$500.00
109Pavement sler (yld tri) (666-7365)EACH39$17.06$10.00$10.00$10.50$20.00
110Pavement sler (number) (666-7367)EACH11$5.00$10.00$10.00$10.50$50.00
111Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF23,489$0.55$0.53$0.53$0.56$0.85
112Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF80,090$0.50$0.53$0.53$0.56$0.85
113Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF86,197$0.51$0.53$0.53$0.56$0.85
114Reflectorized pavement marking type I (W)12"(DOT)(100MIL) (666-7424)LF321$3.00$1.00$1.00$1.05$1.75
115Reflectorized pavement marker type I-C (672-7002)EACH89$3.63$4.00$4.00$4.20$5.00
116Reflectorized pavement marker type II-C-R (672-7006)EACH2,477$3.59$3.65$3.65$3.83$5.00
117Eliminating existing PM & markers (6") (677-7002)LF4,930$0.71$0.80$0.80$0.84$1.00
118Vehicle LP detect (sawcut) (688-7004)LF365$17.10$37.00$37.00$38.85$37.00
119Replace luminaire pole (690-7126)EACH5$2,510.25$1,700.00$1,700.00$1,784.78$1,700.00
120Maintain roadway illumination (690-7184)EACH10$600.00$440.00$440.00$461.94$440.00
121Replace transformer base (690-7197)EACH5$829.69$1,600.00$1,600.00$1,679.80$1,600.00
122Replace fuse (690-7218)EACH5$56.59$120.00$120.00$125.98$120.00
123Replace luminaire (LED) (690-7264)EACH10$500.00$540.00$540.00$566.93$540.00
124Debris removal (spot debris) (735-7072)MI1.29$55,115$8,000.00$10,000$500.00$69,054
125Underseal course (3006-7001)GAL16,842$3.50$4.80$0.05$3.68$0.01
126Bonding course (3007-7001)GAL79,277$4.25$3.00$3.55$3.30$3.55
127Relocate backlit LED RDSD sign (6030-7005)EACH1$2,000.00$530.00$530.00$556.43$530.00
128Loop installation (6041-7001)LF625$35.00$13.00$13.00$13.65$13.00
129Sensor installation (6041-7002)EACH4$20,000$2,000.00$2,000.00$2,099.74$2,000.00
TxDOT contract A00063678: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of February 4, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy