TxDOT contract A00064919 bid tabulation
Highway Improvement, US 96 (FM 83 to 0.15 mi N of SS 414). Let by Texas DOT on July 1, 2025, Sabine, Lufkin District. 5 bids received; low bid $14,650,398 by Pinto Construction Co., Inc., -15% against the engineer's estimate of $17,242,219.
- Owner
- Texas DOT
- Letting
- 01 JUL 2025
- Pay items
- 142
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Pinto Construction Co., Inc. | $14,650,398 | Low | -15% |
| 2 | A. L. Helmcamp, Inc. | $15,672,119 | +7.0% | -9.0% |
| 3 | Drewery Construction Company, Incorporated | $16,577,599 | +13% | -4.0% |
| 4 | Longview Bridge and Road, LTD. | $17,826,489 | +22% | +3.0% |
| 5 | Isi Contracting, Inc. | $23,545,440 | +61% | +37% |
Engineer's estimate: $17,242,219.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Pinto Construction Co., Inc. | 2. A. L. Helmcamp, Inc. | 3. Drewery Construction Company, Incorporated | 4. Longview Bridge and Road, LTD. | 5. Isi Contracting, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 126.89 | $2,000.00 | $2,205.00 | $2,800.00 | $1,750.00 | $5,000.00 | $1,787.06 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 1,568 | $35.00 | $24.15 | $27.00 | $28.00 | $33.25 | $31.52 |
| 3 | Excavation (roadway) (110-7001) | CY | 14,810 | $15.00 | $13.75 | $13.00 | $22.00 | $20.00 | $42.00 |
| 4 | Excavation (special) (110-7003) | CY | 2,000 | $20.00 | $12.32 | $20.00 | $30.00 | $30.00 | $45.98 |
| 5 | Embankment (final)(DC)(type C) (132-7006) | CY | 14,581 | $40.00 | $21.50 | $24.00 | $33.00 | $25.00 | $50.52 |
| 6 | Blading (150-7001) | STA | 126.89 | $300.00 | $366.75 | $200.00 | $350.00 | $250.00 | $729.03 |
| 7 | Spec excavation work (hyd excavator) (158-7002) | HR | 50 | $175.00 | $131.25 | $135.00 | $135.00 | $400.00 | $160.47 |
| 8 | Block sodding (162-7002) | SY | 2,107 | $8.00 | $6.30 | $6.00 | $6.50 | $8.80 | $9.03 |
| 9 | Roll sodding (162-7008) | SY | 2,870 | $10.00 | $6.30 | $6.00 | $6.50 | $8.80 | $9.03 |
| 10 | Broadcast seed (temporary_warm) (164-7005) | SY | 51,126 | $0.50 | $0.11 | $0.16 | $0.15 | $0.20 | $0.19 |
| 11 | Broadcast seed (temporary_cool) (164-7006) | SY | 51,126 | $0.50 | $0.13 | $0.16 | $0.15 | $0.20 | $0.19 |
| 12 | Bond fiber MTRX seed (permanent)(rural)(clay) (164-7083) | SY | 102,244 | $1.00 | $0.65 | $0.60 | $0.70 | $0.80 | $0.80 |
| 13 | Vegetative watering (168-7001) | TGL | 4,098 | $20.00 | $0.01 | $1.00 | $25.00 | $22.00 | $53.44 |
| 14 | Soil ret BLKT(SL_steep_sand_short_roll) (169-7015) | SY | 6,130 | $2.00 | $0.77 | $2.20 | $1.00 | $1.10 | $1.14 |
| 15 | Rdside amenity (trash/recycle bin) (194-7004) | EACH | 6 | $3,000.00 | $750.00 | $8,000.00 | $5,500.00 | $750.00 | $835.94 |
| 16 | FL BS (roadway del) (type D GR 1-2) (247-7209) | TON | 27,609 | $60.00 | $67.16 | $62.00 | $66.50 | $80.00 | $225.00 |
| 17 | Rework BS metal (type C)(12")(ord comp) (251-7055) | SY | 30,075 | $9.00 | $7.06 | $2.90 | $7.25 | $4.00 | $4.42 |
| 18 | Cement (275-7001) | TON | 1,322 | $250.00 | $242.00 | $250.00 | $280.00 | $305.00 | $271.48 |
| 19 | Cement TRT (existing material & new base)(12") (275-7009) | SY | 71,897 | $6.00 | $4.00 | $4.80 | $4.25 | $4.00 | $22.00 |
| 20 | Cement TRT (subgrade)(12") (275-7015) | SY | 2,416 | $6.00 | $12.20 | $6.50 | $11.25 | $4.50 | $22.00 |
| 21 | Prime coat (MC-30) (310-7004) | GAL | 14,871 | $8.00 | $5.43 | $4.80 | $6.00 | $7.00 | $6.96 |
| 22 | Emuls asphalt (erosion control)(SS-1) (314-7008) | GAL | 1,678 | $8.00 | $8.50 | $6.00 | $6.00 | $6.50 | $5.18 |
| 23 | Asphalt (AC-15P or CRS-2P) (316-7088) | TON | 215 | $1,250.00 | $1,009.63 | $1,000.00 | $800.00 | $1,100.00 | $1,294.13 |
| 24 | Aggregate (type E or L, PE or PL GR 4) (316-7268) | CY | 862 | $225.00 | $197.66 | $200.00 | $260.00 | $240.00 | $256.85 |
| 25 | SP mixes SP-B PG70-22 (344-7004) | TON | 24,886 | $180.00 | $155.88 | $172.00 | $161.25 | $175.00 | $152.58 |
| 26 | SP mixes SP-C PG70-22 (344-7019) | TON | 7,050 | $180.00 | $172.59 | $184.00 | $176.25 | $194.00 | $195.90 |
| 27 | SP mixes SP-C sac-A PG76-22 (344-7030) | TON | 12,706 | $185.00 | $174.62 | $178.00 | $180.48 | $190.00 | $175.00 |
| 28 | Flexible pavement structure repair(12") (351-7011) | SY | 200 | $275.00 | $313.89 | $250.00 | $325.00 | $350.00 | $620.47 |
| 29 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 12,090 | $5.00 | $2.92 | $3.20 | $5.00 | $5.00 | $4.35 |
| 30 | Planing asphalt concrete pavement (0" to 2-1/2") (354-7083) | SY | 12,090 | $6.00 | $2.94 | $3.20 | $6.50 | $5.50 | $4.17 |
| 31 | Cut & restore asphalt paving (400-7008) | SY | 18 | $200.00 | $193.20 | $210.00 | $200.00 | $615.00 | $482.02 |
| 32 | Cem stabil BKFL (400-7010) | CY | 94.20 | $300.00 | $311.85 | $340.00 | $335.00 | $350.00 | $22.39 |
| 33 | Trench excavation protection (402-7001) | LF | 75 | $50.00 | $15.75 | $17.00 | $16.00 | $15.00 | $182.55 |
| 34 | Drilled shaft (36 in) (416-7006) | LF | 18 | $400.00 | $332.77 | $350.00 | $575.00 | $550.00 | $358.09 |
| 35 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 144 | $320.00 | $155.73 | $165.00 | $285.00 | $280.00 | $167.59 |
| 36 | Class C concrete (collar) (420-7061) | EACH | 2 | $5,000.00 | $1,575.00 | $1,700.00 | $1,600.00 | $2,500.00 | $8,605.99 |
| 37 | Riprap (concrete)(CL B) (432-7005) | CY | 6.30 | $1,000.00 | $840.00 | $900.00 | $860.00 | $1,400.00 | $1,268.75 |
| 38 | Riprap (concrete) (CL B) (4 in) (432-7007) | CY | 1.25 | $1,000.00 | $1,207.50 | $1,600.00 | $1,240.00 | $1,550.00 | $5,063.65 |
| 39 | Riprap (stone protection)(24 in) (432-7045) | CY | 52 | $250.00 | $331.80 | $350.00 | $340.00 | $600.00 | $512.33 |
| 40 | Concrete box culvert (4 FT X 3 FT)(extend) (462-7059) | LF | 30 | $1,000.00 | $833.70 | $880.00 | $850.00 | $700.00 | $1,382.39 |
| 41 | RC pipe (CL III)(18 in) (464-7003) | LF | 490 | $100.00 | $76.65 | $81.00 | $80.00 | $85.00 | $232.00 |
| 42 | RC pipe (CL III)(24 in) (464-7005) | LF | 276 | $125.00 | $107.10 | $113.00 | $110.00 | $125.00 | $270.45 |
| 43 | RC pipe (CL III)(30 in) (464-7007) | LF | 102 | $200.00 | $249.90 | $262.00 | $255.00 | $125.00 | $295.02 |
| 44 | RC pipe (CL III)(36 in) (464-7009) | LF | 20 | $250.00 | $210.00 | $230.00 | $215.00 | $300.00 | $347.71 |
| 45 | Junction box(complete)(PJB)(4FTX4FT) (465-7006) | EACH | 1 | $8,000.00 | $7,665.00 | $8,000.00 | $7,850.00 | $7,100.00 | $5,200.14 |
| 46 | Inlet(complete)(pazd)(FG)(4FTX4FT-3FTX3FT) (465-7159) | EACH | 2 | $9,000.00 | $8,190.00 | $8,600.00 | $8,400.00 | $7,500.00 | $6,802.24 |
| 47 | Headwall (CH - FW - 0) (diameter= 30 in) (466-7007) | EACH | 1 | $15,000 | $8,715.00 | $9,100.00 | $10,000 | $16,500 | $56,850 |
| 48 | Headwall (CH - FW - 0) (diameter= 36 in) (466-7009) | EACH | 1 | $20,000 | $13,080 | $14,000 | $15,000 | $16,500 | $64,246 |
| 49 | Headwall (CH - FW - 30) (diameter= 36 in) (466-7039) | EACH | 1 | $22,000 | $9,838.50 | $10,500 | $12,500 | $16,500 | $86,912 |
| 50 | Headwall (CH - PW - 0) (diameter= 30 in) (466-7103) | EACH | 1 | $12,000 | $13,335 | $14,000 | $15,000 | $16,500 | $57,393 |
| 51 | Wingwall (PW - 1) (HW=8 FT) (466-7178) | EACH | 2 | $20,000 | $45,150 | $47,000 | $50,000 | $25,000 | $79,245 |
| 52 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 40 | $1,300.00 | $892.50 | $950.00 | $1,000.00 | $1,025.00 | $3,206.71 |
| 53 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 19 | $2,000.00 | $1,533.00 | $1,600.00 | $1,560.00 | $1,900.00 | $4,004.58 |
| 54 | Clean existing culverts (480-7001) | EACH | 6 | $4,000.00 | $1,995.00 | $2,500.00 | $2,500.00 | $4,600.00 | $6,547.95 |
| 55 | Removing structure (inlet) (496-7002) | EACH | 2 | $750.00 | $603.75 | $830.00 | $1,500.00 | $2,500.00 | $3,000.00 |
| 56 | Removing structure (picnic area) (496-7027) | EACH | 4 | $7,800.00 | $2,500.00 | $8,400.00 | $500.00 | $3,500.00 | $2,000.00 |
| 57 | Removing structure (pipe) (496-7037) | EACH | 1 | $1,000.00 | $1,575.00 | $1,700.00 | $2,000.00 | $2,500.00 | $5,000.00 |
| 58 | Removing structure(driveway culvert) (496-7039) | EACH | 28 | $1,000.00 | $367.50 | $385.00 | $400.00 | $2,000.00 | $91.12 |
| 59 | Mobilization (500-7001) | LS | 1 | $1,500,000 | $1,000,000 | $1,100,000 | $1,650,000 | $1,750,000 | $1,000,000 |
| 60 | Barricades, signs and traffic handling (502-7001) | MO | 27 | $5,000.00 | $2,050.00 | $14,750 | $9,800.00 | $10,000 | $15,000 |
| 61 | Portable changeable message sign (503-7002) | EACH | 2 | $20,000 | $20,000 | $10,000 | $20,000 | $20,000 | $212.58 |
| 62 | TMA (stationary) (505-7001) | DAY | 120 | $300.00 | $250.00 | $300.00 | $500.00 | $265.00 | $500.00 |
| 63 | TMA (mobile operation) (505-7003) | DAY | 20 | $300.00 | $50.00 | $300.00 | $750.00 | $350.00 | $72.98 |
| 64 | Rock filter dams (install) (type 2) (506-7002) | LF | 626 | $45.00 | $49.88 | $39.00 | $60.00 | $65.00 | $65.83 |
| 65 | Rock filter dams (remove) (506-7011) | LF | 626 | $15.00 | $10.50 | $10.50 | $5.00 | $22.00 | $22.18 |
| 66 | Construction exits (install) (type 1) (506-7020) | SY | 312 | $40.00 | $15.00 | $25.00 | $100.00 | $56.00 | $57.67 |
| 67 | Construction exits (remove) (506-7024) | SY | 312 | $15.00 | $7.50 | $8.00 | $15.00 | $18.00 | $18.27 |
| 68 | Temporary sediment control fence (install) (506-7039) | LF | 17,260 | $5.00 | $3.68 | $4.00 | $4.75 | $4.00 | $4.19 |
| 69 | Temporary sediment control fence (remove) (506-7041) | LF | 17,260 | $1.00 | $1.05 | $0.50 | $1.00 | $1.10 | $1.15 |
| 70 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 45 | $7.00 | $10.50 | $10.00 | $25.00 | $6.75 | $6.90 |
| 71 | Biodegradable erosion control logs (remove) (506-7046) | LF | 45 | $2.00 | $4.20 | $1.20 | $4.00 | $0.60 | $0.61 |
| 72 | Colored textured concrete (4") (527-7001) | SY | 501 | $130.00 | $199.50 | $210.00 | $205.00 | $100.00 | $647.71 |
| 73 | Concrete curb (type I) (529-7001) | LF | 361 | $45.00 | $51.45 | $54.00 | $53.00 | $30.00 | $119.68 |
| 74 | Concrete curb (type II) (529-7002) | LF | 118 | $65.00 | $76.65 | $80.00 | $80.00 | $70.00 | $12.89 |
| 75 | Intersections (ACP) (530-7002) | SY | 349 | $75.00 | $88.26 | $110.00 | $93.00 | $80.00 | $97.21 |
| 76 | Driveways (concrete) (530-7006) | SY | 1,601 | $200.00 | $162.75 | $170.00 | $165.00 | $140.00 | $320.57 |
| 77 | Driveways (ACP) (530-7010) | SY | 2,714 | $75.00 | $80.43 | $100.00 | $86.00 | $100.00 | $115.26 |
| 78 | Turnouts (ACP) (530-7018) | SY | 74 | $75.00 | $148.05 | $170.00 | $156.00 | $200.00 | $939.01 |
| 79 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 24,920 | $2.00 | $0.36 | $0.30 | $1.00 | $0.60 | $0.46 |
| 80 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 668 | $2.00 | $0.39 | $0.30 | $1.50 | $2.00 | $1.60 |
| 81 | Metal W-beam guard fence (timber post) (540-7001) | LF | 350 | $35.00 | $27.83 | $25.00 | $28.50 | $30.00 | $32.19 |
| 82 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,000.00 | $2,520.00 | $1,800.00 | $1,775.00 | $1,815.00 | $2,141.18 |
| 83 | Remove metal beam guard fence (542-7001) | LF | 475 | $5.00 | $2.63 | $4.00 | $3.25 | $3.50 | $4.24 |
| 84 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 4 | $500.00 | $262.50 | $340.00 | $162.00 | $165.00 | $282.48 |
| 85 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,500.00 | $3,150.00 | $3,100.00 | $3,225.00 | $3,300.00 | $3,681.27 |
| 86 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $450.00 | $262.50 | $340.00 | $215.00 | $220.00 | $282.48 |
| 87 | Gate (remove) (550-7016) | EACH | 1 | $500.00 | $500.00 | $600.00 | $1,000.00 | $400.00 | $557.29 |
| 88 | Wire fence (type C) (552-7003) | LF | 200 | $50.00 | $50.00 | $20.00 | $20.00 | $50.00 | $29.61 |
| 89 | Gate (type 1) (552-7006) | EACH | 1 | $1,500.00 | $5,250.00 | $1,000.00 | $2,000.00 | $2,500.00 | $2,786.48 |
| 90 | Mailbox install-S (WC-post) type 3 (560-7004) | EACH | 13 | $250.00 | $309.75 | $200.00 | $240.00 | $250.00 | $231.63 |
| 91 | Mailbox install-D (WC-post) type 3 (560-7005) | EACH | 1 | $300.00 | $309.75 | $250.00 | $287.00 | $300.00 | $276.84 |
| 92 | Remove RD IL asm (trans-base) (610-7009) | EACH | 9 | $660.00 | $731.39 | $160.00 | $887.00 | $910.00 | $168.29 |
| 93 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 18 | $7,000.00 | $4,904.80 | $5,200.00 | $7,500.00 | $7,600.00 | $4,990.66 |
| 94 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 30 | $11.00 | $17.00 | $18.00 | $25.00 | $22.00 | $17.30 |
| 95 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 13 | $20.00 | $18.48 | $19.00 | $35.00 | $32.00 | $18.80 |
| 96 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 1,510 | $17.00 | $17.88 | $19.00 | $13.00 | $13.00 | $18.19 |
| 97 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 1,630 | $25.00 | $25.40 | $27.00 | $24.25 | $25.00 | $25.84 |
| 98 | Conduit (RM) (3") (618-7082) | LF | 4 | $50.00 | $91.83 | $100.00 | $200.00 | $165.00 | $93.44 |
| 99 | Electrical conductor (no.8) bare (620-7007) | LF | 3,320 | $2.50 | $2.39 | $2.50 | $2.50 | $2.60 | $2.44 |
| 100 | Electrical conductor (no.8) insulated (620-7008) | LF | 6,730 | $2.50 | $3.29 | $3.50 | $3.00 | $3.00 | $3.34 |
| 101 | Ground box type C (162911)W/apron (624-7006) | EACH | 7 | $1,400.00 | $1,332.26 | $1,400.00 | $1,750.00 | $1,800.00 | $1,355.58 |
| 102 | Ground box type D (162922)W/apron (624-7008) | EACH | 1 | $1,800.00 | $1,345.92 | $1,420.00 | $2,500.00 | $2,000.00 | $1,369.48 |
| 103 | Remove electrical services (628-7002) | EACH | 2 | $550.00 | $469.14 | $500.00 | $550.00 | $550.00 | $477.35 |
| 104 | Elc SRV type A 120/240 060(NS)SS(E)SP(U) (628-7010) | EACH | 2 | $7,000.00 | $7,062.84 | $7,400.00 | $7,500.00 | $7,400.00 | $7,186.48 |
| 105 | Elc SRV type D 120/240 100(NS)SS(E)SP(O) (628-7248) | EACH | 1 | $8,000.00 | $7,834.05 | $8,200.00 | $10,000 | $10,000 | $7,971.19 |
| 106 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 5 | $840.00 | $577.50 | $780.00 | $650.00 | $670.00 | $698.29 |
| 107 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 5 | $875.00 | $708.75 | $1,000.00 | $760.00 | $780.00 | $839.52 |
| 108 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 5 | $1,125.00 | $918.75 | $1,200.00 | $925.00 | $950.00 | $897.15 |
| 109 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 1 | $1,500.00 | $1,055.25 | $1,400.00 | $1,500.00 | $1,150.00 | $1,239.52 |
| 110 | Install small roadside sign support and assembly TYS80(1)SA(U-WC) (644-7035) | EACH | 1 | $1,500.00 | $1,260.00 | $1,500.00 | $1,750.00 | $1,300.00 | $1,239.52 |
| 111 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 33 | $600.00 | $425.25 | $700.00 | $455.00 | $470.00 | $429.37 |
| 112 | Install small roadside sign support and assembly tytwt(1)WS(T) (644-7058) | EACH | 3 | $725.00 | $472.50 | $710.00 | $525.00 | $550.00 | $371.97 |
| 113 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 1 | $600.00 | $525.00 | $750.00 | $750.00 | $650.00 | $509.61 |
| 114 | Remove SM RD SN sup&AM (644-7073) | EACH | 48 | $150.00 | $99.75 | $110.00 | $110.00 | $110.00 | $96.04 |
| 115 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 12 | $32.00 | $47.25 | $45.00 | $48.50 | $50.00 | $23.73 |
| 116 | Install object marker assembly (OM-2Z)(WFLX)SRF(BI) (658-7061) | EACH | 12 | $125.00 | $99.75 | $85.00 | $182.75 | $200.00 | $141.25 |
| 117 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 25,489 | $1.00 | $0.21 | $0.22 | $0.22 | $0.25 | $0.21 |
| 118 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 50,978 | $1.00 | $0.21 | $0.22 | $0.22 | $0.25 | $0.21 |
| 119 | Work zone pavement marking removing (traffic BTN) type W (662-7058) | LF | 25,489 | $5.00 | $0.58 | $1.10 | $1.10 | $1.10 | $1.07 |
| 120 | Work zone pavement marking removing (traffic BTN) type Y (662-7060) | LF | 25,489 | $5.00 | $0.58 | $1.10 | $1.10 | $1.10 | $1.07 |
| 121 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 39,508 | $2.00 | $0.01 | $0.55 | $0.75 | $1.75 | $2.45 |
| 122 | Work zone pavement marking SHT terminal (tab)type Y (662-7113) | EACH | 2,549 | $2.00 | $3.15 | $0.55 | $1.20 | $1.25 | $1.93 |
| 123 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 1,274 | $2.00 | $3.15 | $0.55 | $1.25 | $1.25 | $2.45 |
| 124 | Reflectorized pavement marking type I (W)6"(DOT)(090MIL) (666-7008) | LF | 2,492 | $0.75 | $2.63 | $2.20 | $2.15 | $2.20 | $2.14 |
| 125 | Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023) | LF | 585 | $0.75 | $1.84 | $1.10 | $2.00 | $1.10 | $1.07 |
| 126 | Reflectorized pavement marking type I (W)6"(broken)(090MIL) (666-7407) | LF | 5,262 | $0.75 | $0.65 | $0.90 | $1.00 | $0.90 | $0.85 |
| 127 | Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410) | LF | 24,964 | $0.75 | $0.65 | $0.70 | $0.65 | $0.70 | $0.64 |
| 128 | Reflectorized pavement marking type I (Y)6"(broken)(090MIL) (666-7419) | LF | 5,142 | $0.75 | $0.65 | $0.90 | $0.86 | $0.90 | $0.85 |
| 129 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 25,466 | $0.75 | $0.65 | $0.70 | $0.65 | $0.70 | $0.64 |
| 130 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 52 | $22.00 | $15.75 | $15.00 | $20.00 | $15.50 | $14.96 |
| 131 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 10 | $250.00 | $210.00 | $250.00 | $250.00 | $250.00 | $240.39 |
| 132 | Prefabricated PM type C (W)(LN reduct arrow) (668-7100) | EACH | 2 | $350.00 | $367.50 | $360.00 | $350.00 | $360.00 | $347.22 |
| 133 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 5 | $250.00 | $236.25 | $290.00 | $280.00 | $290.00 | $277.78 |
| 134 | Reflectorized pavement marker type I-C (672-7002) | EACH | 306 | $7.00 | $5.25 | $6.00 | $5.50 | $5.50 | $5.34 |
| 135 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 603 | $7.00 | $5.25 | $6.00 | $5.50 | $5.50 | $5.34 |
| 136 | Bonding course (3007-7001) | GAL | 22,617 | $6.00 | $6.04 | $4.50 | $6.15 | $5.00 | $6.38 |
| 137 | ITS pole MNT cab (type 2)(conf 2) (6011-7002) | EACH | 1 | $6,200.00 | $7,967.08 | $8,500.00 | $9,406.25 | $9,625.00 | $8,106.54 |
| 138 | ITS pole (30 FT) (110 MPH) (6011-7029) | EACH | 1 | $12,000 | $11,923 | $13,000 | $16,384 | $16,800 | $12,132 |
| 139 | Installation of cellular modem (6015-7001) | EACH | 1 | $1,300.00 | $1,876.60 | $2,000.00 | $1,343.75 | $1,400.00 | $1,909.45 |
| 140 | CCTV field equipment (digital) (6018-7002) | EACH | 1 | $5,400.00 | $7,609.88 | $8,000.00 | $8,487.13 | $8,700.00 | $7,743.09 |
| 141 | CCTV mount (pole) (6018-7003) | EACH | 1 | $700.00 | $191.10 | $200.00 | $1,397.50 | $1,450.00 | $194.45 |
| 142 | Installation of ethernet switch (6052-7001) | EACH | 1 | $1,000.00 | $1,876.60 | $2,000.00 | $1,032.00 | $1,100.00 | $1,909.45 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 1, 2025. Compiled by Mirage Metrics.