TxDOT contract A00127651 bid tabulation
Surfacing/Roadway Restoration, US 70 (FARWELL EAST CITY LIMITS to BAILEY COUNTY LINE). Let by Texas DOT on May 1, 2025, Parmer, Lubbock District. 8 bids received; low bid $29,652,485 by A. L. Helmcamp, Inc., +2.6% against the engineer's estimate of $28,903,376.
- Owner
- Texas DOT
- Letting
- 01 MAY 2025
- Pay items
- 110
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | A. L. Helmcamp, Inc. | $29,652,485 | Low | +3.0% |
| 2 | Duininck, Inc. | $29,920,089 | +1.0% | +4.0% |
| 3 | James Hamilton Construction Co. | $30,719,988 | +4.0% | +6.0% |
| 4 | J. Lee Milligan, Inc. | $31,366,142 | +6.0% | +9.0% |
| 5 | Gilvin-Terrill, LTD. | $34,221,487 | +15% | +18% |
| 6 | RK Hall, LLC | $35,975,099 | +21% | +24% |
| 7 | Kiewit Infrastructure South Co. | $37,257,716 | +26% | +29% |
| 8 | Webber, LLC | $37,506,456 | +26% | +30% |
Engineer's estimate: $28,903,376.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. A. L. Helmcamp, Inc. | 2. Duininck, Inc. | 3. James Hamilton Construction Co. | 4. J. Lee Milligan, Inc. | 5. Gilvin-Terrill, LTD. | 6. RK Hall, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (pavement) (104-7001) | SY | 634 | $11.40 | $35.00 | $23.50 | $40.00 | $46.25 | $40.00 | $37.70 |
| 2 | Removing concrete (medians) (104-7008) | SY | 303 | $95.00 | $45.00 | $23.50 | $40.00 | $48.75 | $40.00 | $37.88 |
| 3 | Removing concrete (driveways) (104-7011) | SY | 358 | $28.50 | $40.00 | $20.00 | $45.00 | $45.00 | $40.00 | $40.08 |
| 4 | Remove (10"-14") TRT/untrt base & asphalt pavement (105-7010) | SY | 7,981 | $5.70 | $9.00 | $11.00 | $14.20 | $13.75 | $10.00 | $13.14 |
| 5 | Remove (6") TRT/untrt base & asphalt pavement (105-7026) | SY | 1,078 | $19.00 | $12.00 | $9.00 | $14.20 | $13.50 | $10.00 | $11.31 |
| 6 | Obliterating abandoned road (106-7001) | STA | 10 | $2,375.00 | $1,500.00 | $2,700.00 | $4,500.00 | $1,940.00 | $2,500.00 | $2,502.87 |
| 7 | Excavation (roadway) (110-7001) | CY | 5,000 | $60.00 | $38.00 | $21.00 | $15.00 | $40.00 | $20.00 | $21.96 |
| 8 | Subgr widen (DC) (112-7002) | STA | 328.34 | $712.50 | $700.00 | $530.00 | $600.00 | $1,125.00 | $2,500.00 | $995.55 |
| 9 | Backfill (type B) (134-7002) | STA | 1,021.60 | $142.50 | $145.00 | $115.00 | $400.00 | $109.00 | $250.00 | $154.31 |
| 10 | Blading (150-7001) | STA | 1,031.60 | $114.00 | $110.00 | $105.00 | $300.00 | $104.00 | $130.00 | $138.93 |
| 11 | Prime coat (MC-30) (310-7004) | GAL | 6,643.40 | $6.18 | $5.00 | $4.90 | $5.00 | $7.20 | $12.50 | $7.83 |
| 12 | Emuls asphalt (erosion control)(CSS-1H) (314-7011) | GAL | 210,469.93 | $3.50 | $4.80 | $2.65 | $3.75 | $2.25 | $3.75 | $3.71 |
| 13 | Fog seal (CSS-1H) (315-7004) | GAL | 6,172 | $5.70 | $5.50 | $3.65 | $4.00 | $3.40 | $4.25 | $4.66 |
| 14 | D-GR HMA type-B PG70-28 (341-7009) | TON | 11,087.97 | $130.00 | $176.00 | $165.00 | $160.00 | $163.75 | $155.50 | $223.15 |
| 15 | D-GR HMA type-C sac-B PG70-28 (341-7028) | TON | 7,490.53 | $159.00 | $166.00 | $165.00 | $162.00 | $155.00 | $180.50 | $210.13 |
| 16 | D-GR HMA type D sac-B PG70-28 (341-7054) | TON | 20,218.96 | $140.00 | $170.00 | $145.00 | $160.00 | $150.00 | $205.50 | $199.90 |
| 17 | Tack coat (341-7082) | GAL | 74,772.42 | $5.30 | $4.50 | $3.35 | $4.50 | $3.60 | $6.00 | $4.83 |
| 18 | Stone-MTRX-asphalt SMA-D sac-A PG76-28 (346-7010) | TON | 40,887.88 | $170.00 | $189.00 | $185.00 | $150.00 | $195.00 | $180.50 | $244.76 |
| 19 | Tack coat (346-7028) | GAL | 19,732.37 | $6.18 | $4.50 | $3.50 | $4.50 | $3.85 | $6.00 | $5.33 |
| 20 | Flexible pavement structure repair(2") (351-7001) | SY | 2,724.26 | $28.50 | $28.00 | $40.00 | $27.00 | $40.75 | $60.00 | $27.41 |
| 21 | Flexible pavement structure repair(6") (351-7005) | SY | 8,172.75 | $76.00 | $76.00 | $60.00 | $60.00 | $60.50 | $70.00 | $73.44 |
| 22 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 424,818.25 | $2.00 | $1.25 | $2.05 | $1.40 | $1.85 | $2.00 | $2.34 |
| 23 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 160 | $360.00 | $360.00 | $380.00 | $361.00 | $300.00 | $386.40 | |
| 24 | Riprap (concrete)(CL A) (432-7004) | CY | 162.58 | $950.00 | $640.00 | $730.00 | $660.00 | $837.00 | $700.00 | $896.00 |
| 25 | Riprap (mow strip)(5 in) (432-7014) | CY | 4,231.96 | $580.00 | $460.00 | $610.00 | $575.00 | $440.00 | $616.00 | |
| 26 | Concrete box culvert (3 FT X 2 FT)(extend) (462-7056) | LF | 18 | $788.50 | $950.00 | $940.00 | $1,740.00 | $1,750.00 | $1,000.00 | $952.00 |
| 27 | Concrete box culvert (3 FT X 3 FT)(extend) (462-7057) | LF | 6 | $888.25 | $1,300.00 | $1,300.00 | $1,860.00 | $1,780.00 | $1,275.00 | $1,008.00 |
| 28 | Concrete box culvert (4 FT X 2 FT)(extend) (462-7058) | LF | 5.50 | $441.75 | $1,450.00 | $1,400.00 | $1,900.00 | $1,925.00 | $1,500.00 | $1,008.00 |
| 29 | Concrete box culvert (5 FT X 2 FT)(extend) (462-7061) | LF | 15 | $745.75 | $1,400.00 | $1,400.00 | $2,150.00 | $2,130.00 | $1,500.00 | $1,064.00 |
| 30 | Concrete box culvert (5 FT X 3 FT)(extend) (462-7062) | LF | 5.50 | $1,282.50 | $1,500.00 | $1,500.00 | $2,200.00 | $2,000.00 | $1,450.00 | $1,176.00 |
| 31 | RC pipe (CL III)(24 in) (464-7005) | LF | 16 | $142.50 | $170.00 | $165.00 | $205.00 | $210.00 | $200.00 | $168.00 |
| 32 | Set (type I)(S= 3 FT)(HW= 2 FT)(6:1)(C) (467-7038) | EACH | 7 | $1,900.00 | $19,000 | $18,500 | $23,150 | $17,100 | $18,000 | $8,960.00 |
| 33 | Set (type I)(S= 3 FT)(HW= 3 FT)(4:1)(C) (467-7041) | EACH | 1 | $10,189 | $29,000 | $29,500 | $23,250 | $16,300 | $30,000 | $10,080 |
| 34 | Set (type I)(S= 3 FT)(HW= 3 FT)(6:1)(C) (467-7042) | EACH | 1 | $9,500.00 | $24,000 | $24,000 | $32,600 | $19,000 | $25,000 | $13,440 |
| 35 | Set (type I)(S= 4 FT)(HW= 2 FT)(4:1)(C) (467-7064) | EACH | 1 | $3,800.00 | $15,000 | $15,000 | $16,650 | $14,800 | $15,000 | $11,200 |
| 36 | Set (type I)(S= 5 FT)(HW= 2 FT)(6:1)(C) (467-7093) | EACH | 4 | $12,350 | $13,000 | $12,500 | $14,720 | $16,500 | $12,000 | $10,640 |
| 37 | Set (type I)(S= 5 FT)(HW= 3 FT)(4:1)(C) (467-7096) | EACH | 1 | $13,300 | $24,000 | $23,500 | $24,570 | $16,700 | $24,000 | $13,440 |
| 38 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 2 | $2,375.00 | $2,200.00 | $2,100.00 | $5,460.00 | $4,500.00 | $2,500.00 | $2,240.00 |
| 39 | Clean existing culverts (480-7001) | EACH | 26 | $2,850.00 | $3,700.00 | $3,700.00 | $4,400.00 | $2,050.00 | $3,650.00 | $2,240.00 |
| 40 | Mobilization (500-7001) | LS | 1 | $2,852,000 | $1,900,000 | $2,900,000 | $2,550,000 | $3,100,000 | $3,400,000 | $1,798,755 |
| 41 | Barricades, signs and traffic handling (502-7001) | MO | 29 | $11,400 | $11,950 | $15,000 | $34,000 | $35,000 | $70,000 | $18,356 |
| 42 | Portable changeable message sign (503-7001) | DAY | 1,000 | $104.50 | $25.00 | $105.00 | $50.00 | $76.00 | $40.00 | $88.38 |
| 43 | TMA (stationary) (505-7001) | DAY | 1,250 | $199.50 | $95.00 | $260.00 | $300.00 | $310.00 | $180.00 | $592.29 |
| 44 | TMA (mobile operation) (505-7003) | DAY | 165 | $247.00 | $95.00 | $940.00 | $900.00 | $105.00 | $500.00 | $1,188.13 |
| 45 | Construction exits (install) (type 1) (506-7020) | SY | 231 | $57.00 | $35.00 | $52.50 | $31.00 | $50.00 | $50.00 | $56.00 |
| 46 | Construction exits (remove) (506-7024) | SY | 231 | $9.50 | $5.00 | $15.50 | $8.00 | $15.00 | $15.00 | $16.80 |
| 47 | Sandbags for erosion control (506-7035) | EACH | 600 | $9.50 | $18.00 | $21.00 | $20.00 | $13.00 | $20.00 | $22.40 |
| 48 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 6,680 | $11.40 | $8.00 | $8.35 | $7.00 | $8.00 | $8.00 | $8.96 |
| 49 | Biodegradable erosion control logs (remove) (506-7046) | LF | 3,340 | $2.85 | $1.50 | $1.55 | $3.50 | $6.00 | $1.50 | $1.68 |
| 50 | Intersections (ACP) (530-7002) | SY | 6,061 | $57.00 | $100.00 | $125.00 | $120.00 | $72.00 | $100.00 | $121.90 |
| 51 | Driveways (concrete) (530-7006) | SY | 358 | $109.25 | $280.00 | $150.00 | $250.00 | $100.00 | $145.00 | $140.00 |
| 52 | Driveways (ACP) (530-7010) | SY | 3,192 | $76.00 | $48.00 | $66.50 | $122.00 | $26.00 | $60.00 | $161.48 |
| 53 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 154,300 | $0.24 | $0.25 | $0.08 | $0.22 | $0.35 | $0.17 | $0.30 |
| 54 | Cable barrier sys(install)(TL-4)(20 '-0") (543-7016) | LF | 89,320 | $15.00 | $16.50 | $17.70 | $15.20 | $16.00 | $16.24 | |
| 55 | Cable barrier terminal sec (install)(TL-4) (543-7018) | EACH | 76 | $3,600.00 | $4,700.00 | $4,990.00 | $3,600.00 | $4,500.00 | $3,864.00 | |
| 56 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 2 | $351.50 | $230.00 | $230.00 | $240.00 | $525.00 | $220.00 | $246.40 |
| 57 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 2 | $760.00 | $580.00 | $575.00 | $600.00 | $890.00 | $550.00 | $616.00 |
| 58 | In RD IL (type SA) 40T-12-12(250W EQ)LED (610-7129) | EACH | 20 | $6,500.00 | $6,400.00 | $6,740.00 | $6,400.00 | $8,000.00 | $6,860.00 | |
| 59 | Conduit (HDPE) (2") (618-7009) | LF | 3,520 | $15.00 | $15.00 | $16.00 | $15.20 | $12.00 | $16.24 | |
| 60 | Conduit (HDPE) (2") bore (618-7010) | LF | 520 | $32.00 | $31.50 | $33.00 | $31.35 | $18.00 | $33.60 | |
| 61 | Electrical conductor (no.6) bare (620-7009) | LF | 4,040 | $3.00 | $2.75 | $2.90 | $2.80 | $3.00 | $2.97 | |
| 62 | Electrical conductor (no.6) insulated (620-7010) | LF | 8,080 | $3.20 | $3.15 | $3.30 | $3.15 | $3.50 | $3.36 | |
| 63 | Ground box type A (122311)W/apron (624-7002) | EACH | 2 | $1,300.00 | $1,300.00 | $1,375.00 | $1,310.00 | $1,500.00 | $1,400.00 | |
| 64 | Elc SRV type A 120/240 060(NS)SS(E)SP(O) (628-7009) | EACH | 2 | $9,000.00 | $9,000.00 | $9,460.00 | $9,000.00 | $8,500.00 | $9,632.00 | |
| 65 | Aluminum signs (type G) (636-7002) | SF | 96 | $33.25 | $32.00 | $31.50 | $33.00 | $37.00 | $30.00 | $33.60 |
| 66 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 69 | $760.00 | $750.00 | $750.00 | $780.00 | $940.00 | $750.00 | $800.80 |
| 67 | Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002) | EACH | 26 | $522.50 | $920.00 | $910.00 | $957.00 | $1,090.00 | $900.00 | $974.40 |
| 68 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 54 | $855.00 | $810.00 | $805.00 | $847.00 | $1,000.00 | $800.00 | $862.40 |
| 69 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 3 | $1,045.00 | $1,000.00 | $995.00 | $1,045.00 | $1,200.00 | $950.00 | $1,064.00 |
| 70 | Install small roadside sign support and assembly TYS80(1)SA(P-BM) (644-7026) | EACH | 28 | $1,140.00 | $1,200.00 | $1,200.00 | $1,210.00 | $1,400.00 | $1,100.00 | $1,232.00 |
| 71 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 2 | $997.50 | $900.00 | $890.00 | $935.00 | $1,230.00 | $850.00 | $952.00 |
| 72 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 2 | $1,140.00 | $1,100.00 | $1,000.00 | $1,090.00 | $1,465.00 | $1,000.00 | $1,108.80 |
| 73 | Install small roadside sign support and assembly TYS80(1)SA(U-2EXT) (644-7033) | EACH | 5 | $1,235.00 | $1,100.00 | $1,000.00 | $1,090.00 | $1,700.00 | $1,000.00 | $1,108.80 |
| 74 | Install small roadside sign support and assembly TYS80(1)SA(U-WC) (644-7035) | EACH | 2 | $1,235.00 | $1,100.00 | $1,000.00 | $1,090.00 | $1,600.00 | $1,000.00 | $1,108.80 |
| 75 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 24 | $720.00 | $715.00 | $754.00 | $835.00 | $700.00 | $767.20 | |
| 76 | Remove SM RD SN sup&AM (644-7073) | EACH | 203 | $95.00 | $110.00 | $105.00 | $110.00 | $105.00 | $100.00 | $112.00 |
| 77 | Install LRSS (struct steel) (647-7001) | LB | 548.60 | $6.18 | $8.00 | $7.85 | $8.50 | $10.00 | $13.00 | $8.40 |
| 78 | Remove lrsa (647-7003) | EACH | 1 | $760.00 | $1,300.00 | $1,300.00 | $1,320.00 | $1,570.00 | $1,100.00 | $1,344.00 |
| 79 | Install delineator assembly (D-DY)SZ 1(yflx)GND (658-7050) | EACH | 76 | $95.00 | $94.00 | $100.00 | $157.00 | $100.00 | $100.80 | |
| 80 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 60 | $142.50 | $95.00 | $94.00 | $100.00 | $157.00 | $100.00 | $100.80 |
| 81 | Remove delin & object marker assms (658-7078) | EACH | 148 | $23.75 | $16.00 | $15.50 | $16.50 | $16.00 | $15.00 | $16.80 |
| 82 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 25,540 | $0.48 | $0.31 | $0.31 | $0.33 | $0.31 | $0.30 | $0.34 |
| 83 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 217,255 | $0.48 | $0.31 | $0.30 | $0.32 | $0.30 | $0.29 | $0.32 |
| 84 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 29,020 | $0.95 | $0.36 | $0.37 | $0.38 | $0.37 | $0.35 | $0.39 |
| 85 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 217,255 | $0.48 | $0.31 | $0.30 | $0.32 | $0.30 | $0.29 | $0.32 |
| 86 | Work zone pavement marking removing (reflectorized) type I-A (662-7047) | EACH | 6,252 | $4.75 | $4.50 | $4.50 | $4.70 | $4.50 | $4.30 | $4.82 |
| 87 | Work zone pavement marking removing (reflectorized) type I-C (662-7049) | EACH | 6,204 | $4.75 | $4.50 | $4.50 | $4.70 | $4.50 | $4.30 | $4.82 |
| 88 | Work zone pavement marking removing (traffic BTN) type W (662-7057) | EACH | 18,557 | $9.50 | $4.00 | $3.90 | $4.10 | $3.95 | $3.75 | $4.20 |
| 89 | Work zone pavement marking removing (traffic BTN) type Y (662-7059) | EACH | 18,696 | $9.50 | $4.00 | $3.90 | $4.10 | $3.95 | $3.75 | $4.20 |
| 90 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 9,113 | $1.66 | $1.25 | $1.55 | $1.25 | $1.50 | $1.25 | $2.26 |
| 91 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 320 | $1.43 | $1.25 | $1.55 | $1.20 | $1.55 | $1.25 | $2.44 |
| 92 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 1,702 | $0.95 | $1.10 | $1.05 | $1.10 | $1.05 | $1.00 | $1.12 |
| 93 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 28,140 | $1.14 | $1.00 | $0.94 | $1.00 | $0.94 | $0.90 | $1.01 |
| 94 | Type I high perf PM (W)6"(broken)(100MIL) (666-7290) | LF | 25,560 | $0.67 | $0.75 | $0.73 | $0.77 | $0.73 | $0.70 | $0.78 |
| 95 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 104,980 | $0.48 | $0.70 | $0.68 | $0.72 | $0.68 | $0.65 | $0.73 |
| 96 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 525 | $19.00 | $18.00 | $18.00 | $17.70 | $17.80 | $17.50 | $19.06 |
| 97 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 88 | $237.50 | $240.00 | $235.00 | $250.00 | $235.00 | $225.00 | $252.00 |
| 98 | Prefabricated PM type C (W)(36")(yld tri) (668-7111) | EACH | 210 | $33.25 | $60.00 | $59.00 | $62.00 | $59.00 | $56.50 | $63.28 |
| 99 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 398 | $3.80 | $5.30 | $5.25 | $5.50 | $5.25 | $5.00 | $5.60 |
| 100 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 1,787 | $4.75 | $4.50 | $4.20 | $4.40 | $4.20 | $4.00 | $4.48 |
| 101 | Eliminating existing PM & markers (6") (677-7002) | LF | 538,760 | $0.60 | $0.30 | $0.68 | $0.70 | $0.70 | $0.65 | $0.73 |
| 102 | Eliminating existing PM & markers (8") (677-7004) | LF | 27,240 | $1.43 | $0.90 | $0.89 | $0.93 | $0.90 | $0.85 | $0.95 |
| 103 | Pavement surface preparation for marking (24") (678-7008) | LF | 525 | $11.40 | $2.20 | $2.10 | $2.20 | $2.10 | $2.00 | $2.24 |
| 104 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 88 | $142.50 | $32.00 | $31.50 | $33.00 | $31.35 | $30.00 | $33.60 |
| 105 | Pavement surface preparation for marking (36")(yld tri) (678-7023) | EACH | 210 | $23.75 | $5.50 | $5.25 | $5.50 | $5.25 | $5.00 | $5.60 |
| 106 | Full - width mowing (730-7019) | CYC | 6 | $5,700.00 | $5,000.00 | $5,100.00 | $4,600.00 | $30,000 | $16,000 | $15,000 |
| 107 | Litter removal (734-7002) | CYC | 6 | $2,850.00 | $7,500.00 | $4,300.00 | $2,815.00 | $20,000 | $4,525.00 | $15,000 |
| 108 | Reinforced fab for asphalt PVMNT overlays (3002-7001) | SY | 323,897.02 | $6.80 | $6.50 | $6.80 | $6.90 | $6.50 | $7.00 | $7.13 |
| 109 | Asphalt for reinforced fab (PG76-28) (3002-7002) | GAL | 48,584.55 | $4.75 | $5.00 | $3.50 | $5.00 | $3.85 | $6.00 | $5.81 |
| 110 | Temporary speed monitor sys (6016-7001) | EACH | 2 | $12,825 | $12,000 | $8,900.00 | $16,500 | $31,265 | $20,000 | $13,200 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 1, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.