TxDOT contract A00128039 bid tabulation

Remove/Replace Bridge Rail, IH 610 (At Broad Street to .). Let by Texas DOT on January 6, 2026, Harris, Houston District. 7 bids received; low bid $3,111,482 by MBN Enterprises LLC, -3.9% against the engineer's estimate of $3,238,691.

Owner
Texas DOT
Letting
06 JAN 2026
Pay items
58
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1MBN Enterprises LLC$3,111,482Low-4.0%
2SCR Civil Construction, LLC$3,317,274+7.0%+2.0%
3MC2 Civil, LLC$3,390,221+9.0%+5.0%
4Ragle Construction, Inc.$3,494,519+12%+8.0%
5Grey Sky Construction LLC$4,283,190+38%+32%
6Isi Contracting, Inc.$4,401,865+41%+36%
7MB Western Industrial Contracting Co.$4,707,067+51%+45%
TxDOT contract A00128039: bids by rank

Engineer's estimate: $3,238,691.

Bid tabulation

LinePay itemUnitQuantityEstimate1. MBN Enterprises LLC2. SCR Civil Construction, LLC3. MC2 Civil, LLC4. Ragle Construction, Inc.5. Grey Sky Construction LLC6. Isi Contracting, Inc.
1Removing concrete (mowstrip) (104-7004)CY233$25.00$286.00$150.00$192.00$50.00$56.26
2Removing concrete (rail) (104-7036)LF485$43.00$10.00$69.00$50.00$17.90$150.00$55.44
3Remove (12") TRT/untrt base & asphalt pavement (105-7032)SY407$12.00$15.00$77.00$30.00$11.70$20.00$45.72
4Block sodding (162-7002)SY2,345$10.00$4.86$5.00$14.60$10.00$8.06
5Fertilizer (166-7001)ACRE0.49$2,500.00$858.00$800.00$750.00$5,000.00$3,722.36
6Vegetative watering (168-7001)TGL58.80$100.00$37.75$40.00$61.00$50.00$147.27
7Concrete pavement (CRCP)(fast TRK) (12") (360-7076)SY407$300.00$200.00$231.40$180.00$182.00$200.00$245.00
8Concrete structure repair(deck rep (full depth)) (429-7005)SF2,200$90.00$105.20$150.00$84.00$300.00$232.92
9Concrete structure repair (vertical & overhead) (429-7007)SF5$900.00$200.00$700.00$160.00$1,000.00$1,564.05
10Riprap (mow strip)(4 in) (432-7013)CY231$800.00$925.00$800.00$615.00$550.00$820.44
11Cleaning and sealing existing joints (CL7) (438-7007)LF1,565$18.00$26.60$53.00$43.00$80.00$41.25
12Rail (type SSTR) (450-7024)LF366$90.00$90.00$127.00$90.00$77.00$200.00$303.48
13Rail (CLF-RO) (450-7049)LF940$155.00$100.00$120.00$95.00$110.00$300.00$126.56
14Retrofit rail (type SSTR) (451-7024)LF5,394$205.00$205.00$200.00$225.00$114.25$185.00$286.48
15Mobilization (500-7001)LS1$294,426$310,000$205,200$339,000$350,000$400,000$350,000
16Barricades, signs and traffic handling (502-7001)MO27$9,450.00$3,500.00$6,975.00$3,000.00$40,000$12,500$16,553
17Portable changeable message sign (503-7001)DAY60$145.00$150.00$113.00$150.00$106.00$150.00$196.66
18TMA (stationary) (505-7001)DAY150$220.00$250.00$347.40$300.00$346.00$250.00$340.64
19TMA (mobile operation) (505-7002)HR120$55.00$50.00$104.60$75.00$68.00$85.00$76.90
20Biodegradable erosion control logs (install) (12") (506-7044)LF380$5.00$15.00$11.45$10.00$10.00$12.00$8.08
21Biodegradable erosion control logs (remove) (506-7046)LF380$1.00$2.00$2.30$2.00$2.00$5.00$2.15
22Portable concrete traffic barrier (des source)(single slope)(type 1) (512-7013)LF5,400$16.00$25.00$23.15$21.00$25.00$35.00$13.24
23Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025)LF6,360$10.00$20.00$11.00$7.80$20.00$6.19
24Portable concrete traffic barrier (stockpile)(single slope)(type 1) (512-7037)LF5,400$20.00$18.00$19.00$9.20$20.00$17.30
25Mill rumble strips (concrete) (shoulder) (533-7003)LF366$0.70$20.00$23.30$30.00$7.17$5.00$16.61
26Metal W-beam guard fence (timber post) (540-7001)LF4,875$27.00$25.75$33.00$22.50$28.00$36.06
27Metal beam guard fence trans (thrie-beam) (540-7005)EACH8$2,500.00$2,440.00$2,200.00$2,600.00$1,850.00$2,295.42
28Downstream anchor terminal section (540-7015)EACH4$2,000.00$1,554.00$1,650.00$1,358.00$1,850.00$1,830.14
29Remove metal beam guard fence (542-7001)LF5,125$4.20$3.75$5.00$3.25$3.00$5.89
30Remove downstream anchor terminal (542-7003)EACH4$250.00$206.00$275.00$180.00$500.00$682.42
31RM metal beam guard fence trans (thrie-beam) (542-7004)EACH1$250.00$206.00$275.00$180.00$500.00$341.23
32Guardrail end treatment (install) (544-7001)EACH4$5,000.00$3,620.00$3,850.00$3,163.00$3,850.00$4,404.74
33Guardrail end treatment (remove) (544-7003)EACH4$400.00$252.00$550.00$220.00$1,500.00$930.58
34Crash cushion attenuator (move & reset) (545-7002)EACH3$5,000.00$4,348.00$3,500.00$1,415.00$6,500.00$1,352.71
35Crash cushion attenuator (remove) (545-7004)EACH2$4,000.00$2,860.00$1,000.00$1,190.00$2,500.00$1,091.52
36Crash cushion attenuator (install)(R)(N)(TL3) (545-7010)EACH2$28,000$30,000$29,687$27,500$22,250$21,000$29,498
37In bridge MNT clearance sign assembly(type N) (644-7061)EACH6$2,200.00$6,000.00$3,800.00$4,000.00$3,211.00$5,000.00$4,810.38
38Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012)EACH192$7.00$25.00$20.60$50.00$18.00$100.00$30.62
39Install delineator assembly (D-SW)SZ 1(BRF)GF2(BR) (658-7020)EACH174$36.00$35.50$50.00$31.00$100.00$28.51
40Work zone pavement marking removing (W)6"(broken) (662-7065)LF6,885$1.35$1.75$1.77$2.00$1.55$1.00$1.92
41Work zone pavement marking removing (W)6"(solid) (662-7068)LF12,190$0.70$1.75$1.77$2.00$1.55$1.00$1.92
42Work zone pavement marking removing (Y)6"(solid) (662-7100)LF12,970$0.90$1.75$1.77$2.00$1.55$1.00$1.92
43Reflectorized pavement marking type III (W)(6")(solid) (666-7236)LF13,600$0.80$1.65$2.00$0.85$1.75$1.00$2.17
44Reflectorized pavement marking type III (W)(6")(broken) (666-7237)LF6,780$1.00$1.70$2.00$0.85$1.75$1.00$2.17
45Reflectorized pavement marking type III (W)(8")(solid) (666-7239)LF1,020$3.00$4.00$1.50$3.50$6.00$4.34
46Reflectorized pavement marking type III (W)(12")(solid) (666-7242)LF210$8.00$8.00$6.00$7.00$10.00$8.68
47Reflectorized pavement marking type III (Y)(6")(solid) (666-7248)LF14,445$1.00$1.75$2.00$0.85$1.75$2.00$2.17
48Reflectorized pavement marking type III (BLK)(6")(shadow) (666-7262)LF6,880$0.80$1.85$2.00$0.95$1.75$2.00$2.17
49Reflectorized pavement marker type II-C-R (672-7006)EACH390$5.00$8.00$11.44$6.00$10.00$6.00$12.41
50Eliminating existing PM & markers (6") (677-7002)LF43,035$0.40$0.65$0.50$0.50$0.44$1.00$0.55
51Eliminating existing PM & markers (8") (677-7004)LF1,020$1.00$0.82$2.00$0.72$6.00$0.89
52Eliminating existing PM & markers (12") (677-7006)LF210$3.50$1.89$4.00$1.65$6.00$2.05
53Pavement surface preparation for marking (6") (678-7002)LF43,035$0.08$0.25$0.07$0.01$0.06$1.00$0.07
54Pavement surface preparation for marking (8") (678-7004)LF1,020$0.50$0.09$0.02$0.08$6.00$0.10
55Pavement surface preparation for marking (12") (678-7006)LF210$1.50$0.14$0.08$0.12$10.00$0.15
56Strip mowing (730-7018)CYC6$774.00$4,500.00$2,600.00$1,500.00$1,939.33$2,500.00$1,772.18
57Litter removal (734-7002)CYC6$3,000.00$3,000.00$1,300.00$1,000.00$2,813.67$2,500.00$2,218.72
58Concrete rail replacement (in-kind) (778-7004)LF30$30.00$865.00$825.00$477.00$500.00$166.75
TxDOT contract A00128039: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of January 6, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy