TxDOT contract A00130820 bid tabulation
Bridge Replacement, FM 239 (AT DRAW & AT DRAW to STR# 0943-02-005 & -004). Let by Texas DOT on December 3, 2025, De Witt, Yoakum District. 8 bids received; low bid $883,521 by E-Z Bel Construction, LLC, -12% against the engineer's estimate of $1,003,566.
- Owner
- Texas DOT
- Letting
- 03 DEC 2025
- Pay items
- 45
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | E-Z Bel Construction, LLC | $883,521 | Low | -12% |
| 2 | Hunter Industries, LTD. | $914,064 | +3.0% | -9.0% |
| 3 | STX Civil | $1,065,337 | +21% | +6.0% |
| 4 | Acme Bridge Company, Inc. | $1,095,396 | +24% | +9.0% |
| 5 | Clark Construction of Texas, Inc. | $1,154,678 | +31% | +15% |
| 6 | Texas Steel Industrial Placing, LLC | $1,214,369 | +37% | +21% |
| 7 | Constar Construction | $1,296,437 | +47% | +29% |
| 8 | Lucania Contractors LLC | $1,414,658 | +60% | +41% |
Engineer's estimate: $1,003,566.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. E-Z Bel Construction, LLC | 2. Hunter Industries, LTD. | 3. STX Civil | 4. Acme Bridge Company, Inc. | 5. Clark Construction of Texas, Inc. | 6. Texas Steel Industrial Placing, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 4 | $4,000.00 | $1,850.00 | $976.80 | $1,500.00 | $4,730.00 | $2,822.40 | $1,500.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 474 | $20.00 | $12.00 | $27.50 | $25.00 | $21.30 | $20.04 | $25.00 |
| 3 | Embankment (final)(OC)(type C) (132-7005) | CY | 395 | $25.00 | $22.00 | $27.50 | $30.00 | $18.50 | $24.05 | $30.00 |
| 4 | Blading (150-7002) | HR | 8 | $125.00 | $143.00 | $121.00 | $55.00 | $75.00 | $100.00 | $125.00 |
| 5 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 1,213 | $1.00 | $1.20 | $0.20 | $0.25 | $1.60 | $1.26 | $1.50 |
| 6 | Broadcast seed (temporary_warm) (164-7005) | SY | 304 | $1.00 | $1.50 | $0.19 | $0.25 | $4.40 | $1.58 | $4.15 |
| 7 | Broadcast seed (temporary_cool) (164-7006) | SY | 304 | $1.00 | $1.50 | $0.19 | $0.25 | $4.40 | $1.58 | $4.15 |
| 8 | Vegetative watering (168-7001) | TGL | 11 | $65.00 | $70.00 | $36.30 | $65.00 | $75.00 | $50.00 | $1.00 |
| 9 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 12.80 | $300.00 | $440.00 | $353.12 | $370.00 | $300.00 | $421.49 | $375.00 |
| 10 | Lime TRT (existing material)(8") (260-7007) | SY | 778 | $6.00 | $7.00 | $9.90 | $5.00 | $15.00 | $27.95 | $10.00 |
| 11 | Cement (275-7001) | TON | 8 | $265.00 | $255.00 | $220.00 | $165.00 | $341.00 | $414.08 | $300.00 |
| 12 | Cement TRT (existing material)(8") (275-7003) | SY | 778 | $5.00 | $7.00 | $9.90 | $5.00 | $15.00 | $26.62 | $10.00 |
| 13 | Aggregate (type-PE, GR-3)(sac-B) (316-7229) | CY | 20.30 | $650.00 | $1,000.00 | $253.11 | $1,000.00 | $1,060.00 | $541.87 | $750.00 |
| 14 | Aggregate (type-PE, GR-4)(sac-B) (316-7232) | CY | 14.30 | $650.00 | $1,000.00 | $252.85 | $1,000.00 | $1,060.00 | $699.30 | $750.00 |
| 15 | Asphalt (AC 20-5TR or AC-20XP or CRS-2P) (316-7264) | GAL | 1,294 | $5.00 | $10.00 | $5.72 | $10.00 | $10.60 | $16.53 | $8.00 |
| 16 | D-GR HMA type-B PG70-22 (341-7006) | TON | 776.90 | $110.00 | $140.00 | $116.60 | $186.00 | $186.00 | $160.60 | $190.00 |
| 17 | D-GR HMA type D sac-B PG70-22 (341-7050) | TON | 177.20 | $100.00 | $175.00 | $131.99 | $271.00 | $276.00 | $344.09 | $190.00 |
| 18 | Cem stabil BKFL (400-7010) | CY | 47 | $190.00 | $225.00 | $130.00 | $175.00 | $291.00 | $126.00 | $200.00 |
| 19 | Trench excavation protection (402-7001) | LF | 94 | $25.00 | $19.00 | $20.00 | $5.00 | $12.40 | $8.40 | $35.00 |
| 20 | Riprap (concrete)(5 in) (432-7002) | CY | 23 | $585.00 | $450.00 | $700.00 | $595.00 | $638.00 | $630.00 | $750.00 |
| 21 | Concrete box culvert (7 FT X 3 FT) (462-7015) | LF | 372.50 | $750.00 | $790.00 | $900.00 | $680.00 | $897.00 | $1,025.85 | $800.00 |
| 22 | Set (type I)(S= 7 FT)(HW= 4 FT)(3:1)(C) (467-7153) | EACH | 16 | $9,800.00 | $6,500.00 | $5,000.00 | $8,615.00 | $7,820.00 | $3,885.00 | $9,500.00 |
| 23 | Removing structure (box culvert) (496-7001) | EACH | 2 | $20,000 | $5,000.00 | $10,000 | $10,000 | $4,250.00 | $7,350.00 | $20,000 |
| 24 | Mobilization (500-7001) | LS | 1 | $110,000 | $75,000 | $77,918 | $75,000 | $90,000 | $124,200 | $121,328 |
| 25 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $2,500.00 | $550.00 | $2,547.85 | $1,800.00 | $6,550.00 | $2,027.00 | $2,000.00 |
| 26 | Portable changeable message sign (503-7002) | EACH | 2 | $10,000 | $4,500.00 | $5,000.00 | $5,000.00 | $12,900 | $10,000 | $20,000 |
| 27 | TMA (stationary) (505-7001) | DAY | 20 | $320.00 | $175.00 | $150.00 | $65.00 | $200.00 | $150.00 | $250.00 |
| 28 | TMA (mobile operation) (505-7003) | DAY | 20 | $600.00 | $300.00 | $250.00 | $65.00 | $300.00 | $300.00 | $1.00 |
| 29 | Temporary sediment control fence (install) (506-7039) | LF | 849 | $4.00 | $3.00 | $3.82 | $3.00 | $4.75 | $3.15 | $4.00 |
| 30 | Temporary sediment control fence (remove) (506-7041) | LF | 849 | $1.00 | $1.20 | $1.02 | $1.00 | $0.53 | $1.26 | $1.00 |
| 31 | One-way traffic control (port traffic signal) (510-7003) | MO | 5 | $3,000.00 | $2,300.00 | $7,000.00 | $5,000.00 | $4,240.00 | $4,620.00 | $6,000.00 |
| 32 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 1,340 | $40.00 | $23.00 | $18.98 | $90.00 | $23.90 | $76.22 | $80.00 |
| 33 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 160 | $70.00 | $27.50 | $44.56 | $87.00 | $25.90 | $69.30 | $80.00 |
| 34 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 1,340 | $20.00 | $12.50 | $16.43 | $18.50 | $10.00 | $9.39 | $20.00 |
| 35 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 160 | $25.00 | $12.50 | $38.23 | $11.00 | $10.00 | $7.21 | $20.00 |
| 36 | Wire fence (type A) (552-7001) | LF | 981 | $20.00 | $28.00 | $25.09 | $25.00 | $15.90 | $21.00 | $30.00 |
| 37 | Wire fence (water gap) (552-7010) | LF | 48 | $55.00 | $80.00 | $27.18 | $50.00 | $53.00 | $78.75 | $60.00 |
| 38 | Wire fence (remove) (552-7011) | LF | 981 | $5.00 | $5.00 | $19.26 | $1.00 | $3.20 | $2.10 | $5.00 |
| 39 | Install object marker assembly (OM-2Y)(WC)GND (658-7056) | EACH | 8 | $70.00 | $165.00 | $41.30 | $50.00 | $74.10 | $262.50 | $250.00 |
| 40 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 150 | $1.00 | $5.00 | $5.00 | $1.46 | $5.30 | $2.00 | $5.00 |
| 41 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 48 | $8.00 | $16.00 | $16.00 | $12.48 | $17.00 | $15.54 | $16.00 |
| 42 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 7,680 | $1.00 | $0.66 | $0.66 | $1.46 | $0.70 | $1.16 | $0.66 |
| 43 | Reflectorized pavement marking type I (Y)6"(broken)(090MIL) (666-7419) | LF | 1,270 | $1.00 | $4.50 | $4.50 | $8.74 | $4.75 | $1.16 | $4.50 |
| 44 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 64 | $6.00 | $7.50 | $7.50 | $8.74 | $7.90 | $7.14 | $7.50 |
| 45 | Eliminating existing PM & markers (4") (677-7001) | LF | 1,270 | $1.00 | $3.50 | $3.50 | $5.31 | $3.70 | $1.16 | $3.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of December 3, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way