| 1 | Preparing row (100-7002) | STA | 45 | $4,500.00 | $950.00 | $136.25 | $17,105 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 16 | $70.00 | $170.00 | $29.10 | $23.00 |
| 3 | Remove (10") TRT/untrt base & asphalt pavement (105-7030) | SY | 19,265 | $6.00 | $8.40 | $8.29 | $5.75 |
| 4 | Excavation (roadway) (110-7001) | CY | 17,955 | $17.50 | $16.25 | $33.81 | $10.40 |
| 5 | Embankment (final)(DC)(type B) (132-7004) | CY | 1,070 | $35.00 | $25.00 | $28.07 | $11.50 |
| 6 | Blading (150-7001) | STA | 50 | $200.00 | $400.00 | $494.79 | $30.00 |
| 7 | Drill seed (permanent_urban_sand) (164-7011) | SY | 28,686 | $0.75 | $0.39 | $0.39 | $0.21 |
| 8 | Soil ret BLKT(SL_steep_sand_long) (169-7008) | SY | 1,038 | $3.00 | $2.75 | $2.77 | $3.78 |
| 9 | Proof rolling (216-7001) | HR | 13 | $150.00 | $150.00 | $183.88 | $118.20 |
| 10 | FL BS (compacted in place)(type A GR 4) (6") (247-7046) | SY | 1,061 | $25.00 | $31.50 | $22.64 | $16.40 |
| 11 | FL BS (compacted in place)(type A GR 4)(5") (247-7345) | SY | 34,693 | $20.00 | $8.00 | $9.20 | $7.60 |
| 12 | Prime coat (AE-P) (310-7001) | GAL | 6,942 | $6.00 | $4.75 | $5.29 | $4.90 |
| 13 | SP mixes SP-B sac-B PG70-22 (344-7005) | TON | 13,662 | $120.00 | $117.00 | $134.29 | $121.90 |
| 14 | Tack coat (344-7077) | GAL | 3,272 | $3.00 | $4.36 | $2.60 | $6.00 |
| 15 | Stone-MTRX-asphalt smar-F sac-A (346-7023) | TON | 0 | $150.00 | $0.00 | $0.00 | $0.00 |
| 16 | Flowable backfill (401-7001) | CY | 89 | $450.00 | $220.00 | $450.50 | $233.00 |
| 17 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 13 | | $550.00 | $553.50 | $500.00 |
| 18 | Drilled shaft (traffic signal pole) (48 in) (416-7046) | LF | 66 | | $880.00 | $885.60 | $800.00 |
| 19 | Riprap (concrete)(4 in) (432-7001) | CY | 189 | $730.00 | $467.50 | $883.29 | $650.00 |
| 20 | Riprap (concrete)(5 in) (432-7002) | CY | 127 | $800.00 | $451.00 | $778.22 | $622.00 |
| 21 | Concrete box culvert (5 FT X 2 FT) (462-7006) | LF | 238 | $520.00 | $726.00 | $416.67 | $308.00 |
| 22 | Concrete box culvert (5 FT X 3 FT) (462-7007) | LF | 173 | $535.00 | $772.20 | $483.02 | $332.00 |
| 23 | RC pipe (CL III)(24 in) (464-7005) | LF | 259 | $132.00 | $198.00 | $139.15 | $69.00 |
| 24 | RC pipe (CL III)(36 in) (464-7009) | LF | 26 | $185.00 | $136.40 | $249.03 | $153.00 |
| 25 | RC pipe (CL V)(18 in) (464-7032) | LF | 259 | $56.00 | $202.95 | $135.87 | $63.00 |
| 26 | RC pipe (arch)(CL V)(des 1) (464-7052) | LF | 236 | $146.00 | $293.15 | $276.42 | $183.00 |
| 27 | Junction box(complete)(PJB)(5FTX5FT) (465-7009) | EACH | 1 | $7,200.00 | $14,335 | $12,521 | $10,763 |
| 28 | Inlet (complete)(pco)(5FT)(both) (465-7024) | EACH | 3 | $8,000.00 | $13,361 | $13,640 | $6,982.00 |
| 29 | Inlet (complete)(pazd)(RC)(5FTX5FT) (465-7154) | EACH | 1 | $7,570.00 | $11,068 | $11,634 | $7,552.00 |
| 30 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 8 | $1,500.00 | $2,119.70 | $2,237.30 | $1,763.00 |
| 31 | Set (type II) (36 in) (RCP) (3: 1) (C) (467-7365) | EACH | 1 | $5,000.00 | $4,054.60 | $5,905.35 | $3,285.00 |
| 32 | Set (type II) (des 1) (RCP) (6: 1) (P) (467-7418) | EACH | 6 | $3,500.00 | $2,149.40 | $2,237.30 | $1,960.00 |
| 33 | Clean existing culverts (480-7001) | EACH | 8 | $8,250.00 | $3,850.00 | $2,512.79 | $450.00 |
| 34 | Mobilization (500-7001) | LS | 1 | $682,689 | $180,280 | $710,466 | $780,000 |
| 35 | Barricades, signs and traffic handling (502-7001) | MO | 14 | $35,000 | $20,000 | $4,305.28 | $55,000 |
| 36 | Portable changeable message sign (503-7002) | EACH | 6 | $24,800 | $5,500.00 | $5,173.24 | $8,833.00 |
| 37 | TMA (stationary) (505-7001) | DAY | 192 | $165.00 | $137.50 | $39.79 | $346.00 |
| 38 | TMA (mobile operation) (505-7003) | DAY | 40 | $165.00 | $946.00 | $406.65 | $678.00 |
| 39 | Construction exits (install) (type 1) (506-7020) | SY | 156 | $32.00 | $25.00 | $30.05 | $49.97 |
| 40 | Construction exits (remove) (506-7024) | SY | 156 | $13.00 | $12.00 | $15.13 | $16.33 |
| 41 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 1,522 | $5.00 | $3.52 | $3.54 | $8.49 |
| 42 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,522 | $2.00 | $1.65 | $1.66 | $1.75 |
| 43 | Constructing detours (508-7001) | SY | 9,258 | $75.00 | $62.00 | $83.38 | $62.00 |
| 44 | Concrete curb & gutter (type II) (529-7009) | LF | 3,585 | $45.00 | $19.80 | $25.92 | $32.00 |
| 45 | Driveways (concrete) (530-7006) | SY | 1,625 | $115.00 | $104.50 | $83.29 | $10.00 |
| 46 | Driveways (ACP) (530-7010) | SY | 371 | $75.00 | $88.50 | $77.71 | $240.00 |
| 47 | Concrete sidewalks (4") (531-7001) | SY | 816 | $150.00 | $82.50 | $64.12 | $58.00 |
| 48 | Curb ramps (type 1) (531-7005) | EACH | 6 | $2,450.00 | $1,650.00 | $1,599.31 | $1,000.00 |
| 49 | Curb ramps (type 7) (531-7010) | EACH | 7 | $1,700.00 | $1,650.00 | $1,730.51 | $1,000.00 |
| 50 | Curb ramps (type 10) (531-7011) | EACH | 1 | $4,000.00 | $1,650.00 | $1,896.47 | $1,000.00 |
| 51 | Remove metal beam guard fence (542-7001) | LF | 373 | $5.50 | $13.34 | $11.07 | $5.38 |
| 52 | Remove terminal anchor section (542-7002) | EACH | 4 | $550.00 | $1,860.00 | $1,107.01 | $395.81 |
| 53 | Wire fence (remove) (552-7011) | LF | 3,938 | $4.00 | $3.00 | $1.41 | $1.82 |
| 54 | Relocate existing mailbox (560-7012) | EACH | 7 | $500.00 | $584.10 | $587.82 | $531.00 |
| 55 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 30 | | $22.00 | $22.14 | $20.00 |
| 56 | Conduit (PVC) (schedule 80) (3") (618-7060) | LF | 140 | | $27.50 | $27.68 | $25.00 |
| 57 | Conduit (PVC) (schedule 80) (4") (618-7064) | LF | 30 | | $38.50 | $38.75 | $35.00 |
| 58 | Conduit (PVC) (schedule 80) (4") (bore) (618-7065) | LF | 845 | | $49.50 | $49.82 | $45.00 |
| 59 | Electrical conductor (no.12) insulated (620-7004) | LF | 480 | | $1.38 | $1.38 | $1.25 |
| 60 | Electrical conductor (no.8) insulated (620-7008) | LF | 1,620 | | $1.65 | $1.66 | $1.50 |
| 61 | Electrical conductor (no.6) bare (620-7009) | LF | 955 | | $1.93 | $1.94 | $1.75 |
| 62 | Electrical conductor (no.6) insulated (620-7010) | LF | 60 | | $2.20 | $2.21 | $2.00 |
| 63 | Tray cable (3 conductor) (14 AWG) (621-7001) | LF | 2,790 | | $4.40 | $4.43 | $4.00 |
| 64 | Ground box type D (162922)W/apron (624-7008) | EACH | 6 | | $3,025.00 | $3,044.26 | $2,750.00 |
| 65 | Remove ground box (624-7013) | EACH | 4 | $600.00 | $275.00 | $276.75 | $250.00 |
| 66 | Elc SRV type D 120/240 070(NS)SS(E)SP(O) (628-7191) | EACH | 1 | | $12,100 | $12,177 | $11,000 |
| 67 | Aluminum signs (type A) (636-7001) | SF | 17.50 | | $49.50 | $49.82 | $45.00 |
| 68 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 17 | $800.00 | $908.60 | $914.39 | $826.00 |
| 69 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 1 | $924.05 | $1,079.10 | $1,085.97 | $981.00 |
| 70 | Remove SM RD SN sup&AM (644-7073) | EACH | 9 | $250.00 | $95.00 | $125.87 | $150.00 |
| 71 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 20,436 | $0.50 | $0.39 | $0.39 | $0.60 |
| 72 | Work zone pavement marking non-removing (W)8"(DOT) (662-7010) | LF | 379 | $1.25 | $1.32 | $1.33 | $0.92 |
| 73 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 562 | $1.25 | $1.08 | $1.08 | $0.92 |
| 74 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 176 | $4.50 | $5.50 | $5.54 | $4.85 |
| 75 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 20,353 | $0.50 | $0.39 | $0.39 | $0.67 |
| 76 | Work zone pavement marking removing (reflectorized) type I-C (662-7049) | EACH | 242 | $3.87 | $4.95 | $4.98 | $3.00 |
| 77 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 573 | $5.00 | $4.95 | $4.98 | $3.00 |
| 78 | Work zone pavement marking removing (traffic BTN) type W (662-7057) | EACH | 727 | $5.00 | $4.95 | $4.98 | $3.00 |
| 79 | Work zone pavement marking removing (traffic BTN) type Y (662-7059) | EACH | 1,721 | $4.00 | $4.95 | $4.98 | $3.00 |
| 80 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 1,605 | $1.50 | $1.65 | $1.66 | $0.94 |
| 81 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 3,895 | $1.00 | $1.08 | $1.08 | $0.94 |
| 82 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 3,099 | $7.00 | $6.60 | $6.64 | $2.68 |
| 83 | Reflectorized pavement marking type II (W) 6" (broken) (666-7172) | LF | 180 | $1.16 | $2.20 | $2.21 | $0.56 |
| 84 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 15,285 | $0.35 | $0.30 | $0.30 | $0.22 |
| 85 | Reflectorized pavement marking type II (W) 8" (DOT) (666-7177) | LF | 1,605 | $0.30 | $0.55 | $0.55 | $0.25 |
| 86 | Reflectorized pavement marking type II (W) 8" (solid) (666-7179) | LF | 3,895 | $1.25 | $0.39 | $0.39 | $0.27 |
| 87 | Reflectorized pavement marking type II (W) 24" (solid) (666-7184) | LF | 3,099 | $3.50 | $1.65 | $1.66 | $0.67 |
| 88 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 16,662 | $0.35 | $0.30 | $0.30 | $0.22 |
| 89 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 180 | $2.00 | $2.20 | $2.21 | $0.72 |
| 90 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 15,285 | $0.75 | $0.87 | $0.87 | $0.72 |
| 91 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 16,662 | $0.80 | $0.87 | $0.87 | $0.72 |
| 92 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 27 | $565.00 | $275.00 | $276.75 | $266.00 |
| 93 | Prefabricated PM type C (W)(double arrow) (668-7093) | EACH | 2 | $565.00 | $495.00 | $498.15 | $455.77 |
| 94 | Prefabricated PM type C (W)(LN reduct arrow) (668-7100) | EACH | 2 | $630.00 | $605.00 | $608.85 | $425.55 |
| 95 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 21 | $765.00 | $352.00 | $354.24 | $250.55 |
| 96 | Prefabricated PM type C (W)(36")(yld tri) (668-7111) | EACH | 16 | $30.00 | $22.00 | $22.14 | $65.00 |
| 97 | Prefabricated PM type C (Y)(24")(solid) (668-7127) | LF | 370 | $15.00 | $13.20 | $13.28 | $8.21 |
| 98 | Reflectorized pavement marker type I-C (672-7002) | EACH | 210 | $4.00 | $4.68 | $4.70 | $6.75 |
| 99 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 535 | $3.00 | $4.13 | $4.15 | $6.75 |
| 100 | Eliminating existing PM & markers (4") (677-7001) | LF | 15,075 | $0.79 | $1.25 | $5.26 | $0.20 |
| 101 | Eliminating existing PM & markers (8") (677-7004) | LF | 229 | $2.25 | $10.00 | $8.84 | $1.00 |
| 102 | Eliminating existing PM & markers (24") (677-7008) | LF | 22 | $5.00 | $75.00 | $48.21 | $1.00 |
| 103 | Pavement surface preparation for marking (6") (678-7002) | LF | 32,147 | $0.35 | $0.39 | $0.39 | $0.37 |
| 104 | Pavement surface preparation for marking (8") (678-7004) | LF | 5,500 | $0.10 | $0.72 | $0.72 | $0.37 |
| 105 | Pavement surface preparation for marking (24") (678-7008) | LF | 3,469 | $2.35 | $2.20 | $2.21 | $0.37 |
| 106 | Pavement surface preparation for marking (36")(yld tri) (678-7023) | EACH | 16 | $10.00 | $3.30 | $3.32 | $19.00 |
| 107 | Install highway traffic signal (isolated) (680-7002) | EACH | 1 | | $49,500 | $49,815 | $45,000 |
| 108 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 14 | | $385.00 | $387.45 | $350.00 |
| 109 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 5 | | $385.00 | $387.45 | $350.00 |
| 110 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 14 | | $385.00 | $387.45 | $350.00 |
| 111 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 8 | | $385.00 | $387.45 | $350.00 |
| 112 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 14 | | $385.00 | $387.45 | $350.00 |
| 113 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 8 | | $385.00 | $387.45 | $350.00 |
| 114 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 8 | | $1,045.00 | $1,051.65 | $950.00 |
| 115 | Backplate W/reflectorized border(3 sec)aluminum (682-7039) | EACH | 16 | | $192.50 | $193.73 | $175.00 |
| 116 | Backplate W/reflectorized border(5 sec)aluminum (682-7041) | EACH | 3 | | $247.50 | $249.08 | $225.00 |
| 117 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 665 | | $3.30 | $3.32 | $3.00 |
| 118 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 230 | | $3.85 | $3.87 | $3.50 |
| 119 | Traffic signal CBL (type A)(14 AWG)(10 conductor) (684-7036) | LF | 1,525 | | $4.40 | $4.43 | $4.00 |
| 120 | Traffic signal CBL (type A)(14 AWG)(20 conductor) (684-7046) | LF | 1,165 | | $6.60 | $6.64 | $6.00 |
| 121 | Traffic signal CBL (type C)(12 AWG)(2 conductor) (684-7079) | LF | 2,265 | | $2.20 | $2.21 | $2.00 |
| 122 | Ins traffic signal PL AM(S)1 arm(48')lum&ilsn (686-7052) | EACH | 1 | | $30,800 | $30,996 | $28,000 |
| 123 | Ins traffic signal PL AM(S)1 arm(65')lum&ilsn (686-7068) | EACH | 3 | | $57,750 | $58,118 | $52,500 |
| 124 | Pedestrian pole assembly (687-7001) | EACH | 5 | | $4,125.00 | $4,151.26 | $3,750.00 |
| 125 | Pedestrian detect push button (APS) (688-7001) | EACH | 8 | | $1,100.00 | $1,107.00 | $1,000.00 |
| 126 | Pedestrian detector controller unit (688-7003) | EACH | 1 | | $5,500.00 | $5,535.02 | $5,000.00 |
| 127 | Remove luminaire pole (690-7127) | EACH | 2 | $1,250.00 | $550.00 | $553.50 | $500.00 |
| 128 | Tree removal (24" - 30" diameter) (752-7008) | EACH | 38 | $600.00 | $1,700.00 | $830.25 | $1,350.00 |
| 129 | Bonding course (3007-7001) | GAL | 3,272 | $2.64 | $4.18 | $2.60 | $6.20 |
| 130 | Bbu system (external battery cabinet) (6007-7001) | EACH | 1 | | $13,750 | $13,838 | $12,500 |
| 131 | Video imaging and radar detector (6017-7015) | EACH | 4 | | $7,150.00 | $7,195.53 | $6,500.00 |
| 132 | Video imaging and radar set-UP sys (6017-7016) | EACH | 1 | | $2,750.00 | $2,767.51 | $2,500.00 |
| 133 | Vid image and radar det processor sys (6017-7018) | EACH | 1 | | $24,750 | $24,908 | $22,500 |
| 134 | Stone-MTRX-asphalt SMA-D sac-A PG76-22 (346-7009) | TON | 2,521 | $150.00 | $165.00 | $226.77 | $179.00 |
| 135 | Thermoplastic pipe (PP) (24") (468-7002) | LF | 0 | $132.00 | $0.00 | $0.00 | $0.00 |
| 136 | Thermoplastic pipe (PP) (36") (468-7004) | LF | 0 | $185.00 | $0.00 | $0.00 | $0.00 |
| 137 | Thermoplastic pipe (PP) (18") (468-7001) | LF | 0 | $56.00 | $0.00 | $0.00 | $0.00 |
| 138 | Set (type II) (18 in) (TP) (6: 1) (P) (467-7312) | EACH | 0 | $1,500.00 | $0.00 | $0.00 | $0.00 |
| 139 | Set (type II) (36 in) (TP) (3: 1) (C) (467-7369) | EACH | 0 | $5,000.00 | $0.00 | $0.00 | $0.00 |