TxDOT contract A00177327 bid tabulation

Intersection Improvement, FM 2499 (At FM 407 (Justin Road) to .). Let by Texas DOT on March 4, 2025, Denton, Dallas District. 6 bids received; low bid $3,143,472 by Garret Shields Infrastructure, -10% against the engineer's estimate of $3,503,881.

Owner
Texas DOT
Letting
04 MAR 2025
Pay items
109
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Garret Shields Infrastructure$3,143,472Low-10%
2O. Trevino Construction, LLC$3,411,000+9.0%-3.0%
3Ed Bell Construction Company$3,769,012+20%+8.0%
4Ragle Construction, Inc.$3,822,461+22%+9.0%
5Grey Sky Construction LLC$3,890,474+24%+11%
6Jagoe-Public Company$4,048,468+29%+16%
TxDOT contract A00177327: bids by rank

Engineer's estimate: $3,503,881.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Garret Shields Infrastructure2. O. Trevino Construction, LLC3. Ed Bell Construction Company4. Ragle Construction, Inc.5. Grey Sky Construction LLC6. Jagoe-Public Company
1Preparing row (100-7002)STA11.51$26,602$1,000.00$5,000.00$6,000.00$29,500$29,000$1,200.00
2Preparation row (tree remove) (0"-12" diameter) (100-7003)EACH13$750.00$1,000.00$1,000.00$750.00$675.00$2,500.00$800.00
3Preparation row (tree remove) (12"-24" diameter) (100-7004)EACH11$1,200.00$1,500.00$1,200.00$1,050.00$950.00$5,000.00$1,500.00
4Removing concrete (pavement) (104-7001)SY1,729$20.00$40.00$28.00$31.50$26.40$20.00$60.00
5Removing concrete (medians) (104-7008)SY299$30.00$40.00$18.00$12.60$20.00$20.00$32.00
6Removing concrete (driveways) (104-7011)SY406$30.00$40.00$38.00$18.90$17.90$20.00$32.00
7Removing concrete (sidewalk, ramp or shared use path) (104-7013)SY776$30.00$30.00$20.00$21.00$22.30$20.00$32.00
8Removing concrete (curb) (104-7016)LF5,166$15.00$5.00$8.00$1.00$2.70$20.00$1.50
9Remove (12"-16") TRT/untrt base & asphalt pavement (105-7012)SY2,952$9.75$30.00$20.00$21.00$20.70$20.00$15.00
10Excavation (roadway) (110-7001)CY5,522$25.00$50.00$22.00$21.00$46.60$20.00$44.00
11Embankment (final)(DC)(type C1) (132-7008)CY117$20.00$50.00$55.00$31.50$830.00$50.00$110.00
12Compost manuf topsoil (4") (161-7002)SY2,110$5.00$5.00$8.00$7.49$9.60$7.00$5.00
13Block sodding (162-7002)SY2,110$10.00$10.00$7.00$6.63$9.80$7.00$8.00
14Drill seed (temporary_warm_cool) (164-7015)SY2,110$3.00$1.30$1.50$1.39$0.50$1.00$1.00
15Vegetative watering (168-7001)TGL628$10.00$70.00$75.00$1.00$30.50$20.00$5.00
16FL BS (compacted in place)(type D GR 1-2) (10") (247-7102)SY6,160$36.52$30.00$45.00$40.00$26.50$32.00$50.00
17Prime coat (AE-P) (310-7001)GAL1,232$6.00$10.00$10.50$4.28$9.20$10.00$1.00
18SP mixes SP-B PG64-22 (344-7001)TON1,355$165.00$180.00$222.00$155.15$168.00$200.00$170.00
19Concrete pavement (CRCP) (9") (360-7003)SY5,112$195.00$140.00$130.75$150.00$114.50$150.00$120.00
20Flowable backfill (401-7001)CY38$360.00$300.00$270.00$630.00$2,500.00$350.00$330.00
21Trench excavation protection (402-7001)LF121$50.00$10.00$4.50$21.00$26.90$10.00$1.25
22Drilled shaft (traffic signal pole) (48 in) (416-7046)LF88$500.00$800.00$850.00$781.42$687.55$650.00$1,500.00
23RC pipe (CL III)(18 in) (464-7003)LF94$120.00$80.00$330.00$450.00$159.00$105.00$150.00
24RC pipe (CL III)(24 in) (464-7005)LF27$150.00$120.00$550.00$650.00$276.00$250.00$170.00
25Inlet (complete)(pcu)(4FT)(both) (465-7036)EACH5$8,000.00$8,000.00$10,000$21,000$8,000.00$12,500$16,000
26Inlet (complete)(pazd)(RC)(4FTX4FT) (465-7153)EACH1$10,000$5,000.00$10,000$18,000$6,460.00$12,500$18,000
27Adjusting inlets (cap) (479-7006)EACH2$5,000.00$2,000.00$4,500.00$7,500.00$1,615.00$2,500.00$3,000.00
28Removing structure (inlet) (496-7002)EACH7$1,400.00$2,000.00$2,500.00$2,200.00$612.00$2,500.00$1,100.00
29Removing structure (pipe) (496-7007)LF271$25.00$20.00$47.00$30.00$22.00$50.00$15.00
30Mobilization (500-7001)LS1$304,631$300,000$340,000$473,000$385,000$400,000$440,000
31Barricades, signs and traffic handling (502-7001)MO9$12,000$5,000.00$25,000$63,000$55,000$8,500.00$45,000
32TMA (stationary) (505-7001)DAY50$276.00$1,000.00$185.00$200.00$346.00$250.00$1,000.00
33TMA (mobile operation) (505-7002)HR50$108.00$100.00$80.00$1,000.00$68.00$550.00$50.00
34Construction exits (install) (type 3) (506-7022)SY72$40.00$40.00$150.00$55.00$39.00$50.00$25.00
35Construction exits (remove) (506-7024)SY72$10.00$10.00$100.00$27.50$30.00$20.00$10.00
36Temporary sediment control fence (install) (506-7039)LF2,015$5.00$6.00$4.00$3.30$3.50$4.00$4.25
37Temporary SDMT cont fence (inlet protection) (506-7040)LF342$10.00$6.00$9.00$11.00$8.25$8.00$10.00
38Temporary sediment control fence (remove) (506-7041)LF2,357$1.50$1.00$2.25$1.65$1.10$2.00$2.50
39Biodegradable erosion control logs (install) (12") (506-7044)LF342$10.00$10.00$8.50$9.90$5.75$18.00$9.00
40Biodegradable erosion control logs (remove) (506-7046)LF342$5.00$1.00$3.00$3.30$1.25$9.00$3.25
41Colored textured concrete (4") (527-7001)SY232$206.00$120.00$210.00$210.00$84.00$200.00$330.00
42Concrete curb (mono) (type II) (529-7007)LF3,850$20.00$25.00$10.00$9.00$7.60$20.00$15.00
43Concrete curb & gutter (type II) (529-7009)LF132$95.00$20.00$60.00$75.00$50.00$55.00$80.00
44Driveways (concrete) (hes) (530-7007)SY151$250.00$120.00$180.00$175.00$98.00$125.00$190.00
45Concrete sidewalks (4") (531-7001)SY617$95.00$100.00$120.00$90.00$66.00$65.00$110.00
46Curb ramps (type 7) (531-7010)EACH13$2,500.00$3,000.00$3,000.00$3,500.00$1,700.00$3,250.00$5,000.00
47Right of way markers (538-7001)EACH4$350.00$500.00$500.00$450.00$500.00$500.00$500.00
48Conduit (PVC) (schedule 40) (3") (618-7036)LF190$25.00$25.00$28.00$25.57$15.32$40.00$60.00
49Conduit (PVC) (schedule 40) (4") (618-7040)LF50$35.00$30.00$32.00$29.10$26.67$50.00$60.00
50Conduit (PVC) (schedule 40) (4") (bore) (618-7041)LF615$45.00$40.00$46.00$42.80$48.65$80.00$110.00
51Electrical conductor (no.12) insulated (620-7004)LF560$2.00$3.00$2.00$1.93$1.76$3.00$6.00
52Electrical conductor (no.8) insulated (620-7008)LF1,170$2.00$3.00$3.25$2.89$2.21$3.00$7.00
53Electrical conductor (no.6) bare (620-7009)LF885$2.20$3.00$3.25$2.89$2.68$3.00$9.00
54Electrical conductor (no.6) insulated (620-7010)LF40$2.00$5.00$4.00$3.64$2.75$3.00$9.00
55Ground box type D (162922)W/apron (624-7008)EACH5$1,500.00$2,500.00$2,500.00$2,187.08$1,668.00$1,500.00$5,000.00
56Elc SRV type D 120/240 060(NS)SS(E)PS(U) (628-7147)EACH1$6,000.00$12,000$12,000$10,834$10,659$12,500$20,000
57Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH3$855.00$600.00$750.00$679.45$689.00$1,500.00$800.00
58Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH5$1,500.00$600.00$800.00$715.83$697.00$1,500.00$800.00
59Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009)EACH4$687.00$600.00$825.00$765.05$596.00$1,500.00$900.00
60Install small roadside sign support and assembly type 10BWG(1)SB(T) (644-7012)EACH3$700.00$600.00$850.00$786.45$754.00$1,500.00$900.00
61Relocate SM RD SN sup&AM type 10BWG (644-7065)EACH6$1,200.00$500.00$700.00$652.70$594.00$1,000.00$800.00
62Relocate SM RD SN sup&AM type S80 (644-7067)EACH3$1,200.00$500.00$900.00$829.25$625.00$1,000.00$1,000.00
63Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018)LF232$2.00$3.00$2.25$3.30$3.00$6.00$2.50
64Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF3,771$2.00$2.00$2.00$1.65$1.50$6.00$2.00
65Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF660$10.00$9.00$10.00$7.70$7.00$20.00$11.00
66Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042)EACH26$250.00$250.00$250.00$209.00$190.00$250.00$280.00
67Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066)EACH25$250.00$300.00$300.00$231.00$210.00$250.00$340.00
68Type I high perf PM (W)6"(solid)(100MIL) (666-7293)LF1,258$2.00$2.19$2.00$1.10$1.00$1.00$2.25
69Type I high perf PM (Y)6"(solid)(100MIL) (666-7305)LF2,480$2.00$2.19$2.00$1.10$1.00$1.00$2.25
70Pavement sler 6" (666-7347)LF5,665$2.00$0.70$0.55$0.28$0.25$1.00$0.60
71Pavement sler 8" (666-7348)LF4,003$2.00$1.00$0.85$0.39$0.35$1.00$1.00
72Pavement sler 24" (666-7352)LF660$2.00$3.00$2.25$1.10$1.00$6.00$2.50
73Pavement sler (arrow) (666-7353)EACH26$100.00$80.00$85.00$27.50$25.00$150.00$90.00
74Pavement sler (word) (666-7354)EACH25$100.00$80.00$85.00$27.50$25.00$150.00$90.00
75Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF1,927$2.00$2.00$2.00$1.10$1.00$1.00$2.25
76Reflectorized pavement marker type I-C (672-7002)EACH224$10.00$7.00$8.00$5.50$5.00$6.00$9.00
77Eliminating existing PM & markers (4") (677-7001)LF5,058$1.16$0.80$0.75$0.61$0.55$1.00$0.80
78Eliminating existing PM & markers (8") (677-7004)LF3,157$2.07$0.80$1.00$1.10$1.00$6.00$1.00
79Eliminating existing PM & markers (12") (677-7006)LF1,124$2.63$2.50$2.25$1.65$1.50$8.00$2.50
80Eliminating existing PM & markers (24") (677-7008)LF229$4.55$4.00$4.00$3.30$3.00$20.00$3.75
81Eliminating existing PM & markers (arrow) (677-7009)EACH18$110.00$100.00$100.00$71.50$65.00$250.00$110.00
82Eliminating existing PM & markers (double arrow) (677-7010)EACH1$175.00$130.00$135.00$132.00$120.00$500.00$150.00
83Eliminating existing PM & markers (word) (677-7015)EACH18$150.00$100.00$100.00$71.50$65.00$250.00$110.00
84Pavement surface preparation for marking (6") (678-7002)LF5,665$2.00$0.50$0.50$0.06$0.05$1.00$0.50
85Pavement surface preparation for marking (8") (678-7004)LF4,003$2.00$0.60$0.55$0.08$0.07$1.00$0.60
86Pavement surface preparation for marking (24") (678-7008)LF660$5.00$1.70$1.75$0.22$0.20$6.00$2.00
87Pavement surface preparation for marking (arrow) (678-7009)EACH26$100.00$70.00$68.00$11.00$10.00$150.00$80.00
88Pavement surface preparation for marking (word) (678-7016)EACH25$100.00$70.00$68.00$11.00$10.00$150.00$80.00
89Install highway traffic signal (isolated) (680-7002)EACH1$4,000.00$75,000$90,000$78,640$55,430$55,000$50,000
90Removing traffic signals (680-7004)EACH1$30,000$10,000$12,000$9,818.11$150,000$12,500$11,000
91Vehicle signal section (12")LED(green) (682-7001)EACH12$350.00$500.00$500.00$433.35$465.00$325.00$1,300.00
92Vehicle signal section (12")LED(green arrow) (682-7002)EACH12$350.00$500.00$500.00$433.35$473.00$325.00$1,300.00
93Vehicle signal section (12")LED(yel) (682-7003)EACH12$350.00$500.00$500.00$433.35$465.00$325.00$1,300.00
94Vehicle signal section (12")LED(yel arrow) (682-7004)EACH12$350.00$500.00$500.00$433.35$473.00$325.00$1,300.00
95Vehicle signal section (12")LED(red) (682-7005)EACH12$350.00$500.00$500.00$433.35$465.00$325.00$1,300.00
96Vehicle signal section (12")LED(red arrow) (682-7006)EACH8$350.00$500.00$500.00$433.35$473.00$325.00$1,300.00
97Pedestrian signal section (LED)(countdown) (682-7018)EACH8$350.00$1,000.00$1,000.00$836.31$879.00$8,500.00$2,200.00
98Backplate W/ref border(3 sec)(vent)aluminum (682-7042)EACH16$275.00$250.00$250.00$222.77$286.99$250.00$490.00
99Backplate W/ref border(5 sec)(vent)aluminum (682-7044)EACH4$275.00$400.00$400.00$357.27$345.00$300.00$500.00
100Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031)LF1,030$2.00$3.50$3.50$3.21$3.93$3.00$6.00
101Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033)LF80$3.00$5.00$4.50$3.85$5.31$3.00$7.00
102Traffic signal CBL (type A)(14 AWG)(10 conductor) (684-7036)LF1,615$3.50$5.00$5.00$4.28$4.63$3.00$11.00
103Traffic signal CBL (type A)(14 AWG)(20 conductor) (684-7046)LF840$5.00$8.00$9.00$8.35$8.88$3.00$17.00
104Traffic signal CBL (type C)(12 AWG)(2 conductor) (684-7079)LF1,675$2.00$3.00$3.00$2.78$4.66$3.00$6.00
105Ins traffic signal PL AM(S)1 arm(65')lum (686-7067)EACH4$40,000$40,000$50,000$40,464$42,502$85,000$70,000
106Pedestrian pole assembly (687-7001)EACH7$3,600.00$4,000.00$4,400.00$3,737.72$4,550.00$6,500.00$9,000.00
107Pedestrian detect push button (APS) (688-7001)EACH8$900.00$1,600.00$2,000.00$1,680.97$844.00$1,850.00$2,900.00
108Removal of traffic signal pole FND (690-7033)LF4$500.00$500.00$500.00$392.80$1,586.00$2,500.00$1,800.00
109ITS com CBL (ethernet) (6005-7001)LF190$3.50$5.00$3.50$3.00$3.80$6.00$9.00
TxDOT contract A00177327: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of March 4, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy