TxDOT contract A00183318 bid tabulation
Bicycle And Pedestrian Improvements, Various (On Taylor St and Waller-Tomball Rd to From Farr St to FM 2920). Let by Texas DOT on July 1, 2025, Harris, Houston District. 8 bids received; low bid $948,028 by Highway 19 Construction LLC, -18% against the engineer's estimate of $1,157,880.
- Owner
- Texas DOT
- Letting
- 01 JUL 2025
- Pay items
- 55
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Highway 19 Construction LLC | $948,028 | Low | -18% |
| 2 | MBN Enterprises LLC | $949,545 | 0.0% | -18% |
| 3 | STX Civil | $1,056,364 | +11% | -9.0% |
| 4 | Ti-Zack Concrete, LLC | $1,096,134 | +16% | -5.0% |
| 5 | Brice Highway LLC | $1,124,883 | +19% | -3.0% |
| 6 | Artillery L.L.C. | $1,316,025 | +39% | +14% |
| 7 | Grey Sky Construction LLC | $1,426,496 | +50% | +23% |
| 8 | Ragle Construction, Inc. | $1,431,102 | +51% | +24% |
Engineer's estimate: $1,157,880.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Highway 19 Construction LLC | 2. MBN Enterprises LLC | 3. STX Civil | 4. Ti-Zack Concrete, LLC | 5. Brice Highway LLC | 6. Artillery L.L.C. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 3 | $5,250.00 | $5,000.00 | $4,500.00 | $3,000.00 | $1,100.00 | $28,150 | $7,500.00 |
| 2 | Preparation row (tree remove) (0"-12" diameter) (100-7003) | EACH | 29 | $455.00 | $1,000.00 | $1,400.00 | $150.00 | $770.00 | $550.00 | $1,500.00 |
| 3 | Tree protection (install) (100-7013) | EACH | 39 | $500.55 | $500.00 | $410.00 | $1.00 | $1.10 | $495.00 | $750.00 |
| 4 | Removing concrete (riprap) (104-7006) | SY | 25 | $23.00 | $25.00 | $25.00 | $20.00 | $31.92 | $63.28 | $30.00 |
| 5 | Removing concrete (driveways) (104-7011) | SY | 176 | $51.68 | $25.00 | $25.00 | $20.00 | $45.34 | $54.79 | $30.00 |
| 6 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 18 | $22.00 | $35.00 | $40.00 | $20.00 | $44.33 | $87.03 | $30.00 |
| 7 | Remove (4"-8") TRT/untrt base & asphalt pavement (105-7004) | SY | 333 | $9.00 | $15.00 | $20.00 | $6.00 | $23.96 | $10.00 | $10.00 |
| 8 | Excavation (channel) (110-7002) | CY | 408 | $47.44 | $25.00 | $24.00 | $30.00 | $44.71 | $44.97 | $25.00 |
| 9 | Embankment (final)(DC)(type C) (132-7006) | CY | 200 | $51.40 | $100.00 | $30.00 | $45.00 | $60.90 | $59.99 | $30.00 |
| 10 | Erosion control compost (vehicle) (161-7008) | CY | 50 | $30.02 | $50.00 | $75.00 | $35.00 | $1.10 | $75.00 | $100.00 |
| 11 | Block sodding (162-7002) | SY | 3,100 | $5.86 | $8.00 | $10.00 | $20.00 | $5.50 | $4.90 | $10.00 |
| 12 | Fertilizer (166-7001) | ACRE | 0.65 | $1,359.49 | $150.00 | $1,800.00 | $15,000 | $1.10 | $2,000.00 | $1,000.00 |
| 13 | Vegetative watering (168-7001) | TGL | 121 | $95.23 | $60.00 | $80.00 | $50.00 | $1.10 | $71.85 | $40.00 |
| 14 | FL BS (compacted in place)(type A GR 1-2) (8") (247-7067) | SY | 224 | $17.75 | $75.00 | $46.00 | $40.00 | $69.09 | $70.00 | $70.00 |
| 15 | D-GR HMA type D PG64-22 (341-7043) | TON | 95 | $564.90 | $350.00 | $190.00 | $350.00 | $275.00 | $300.00 | $250.00 |
| 16 | Class C concrete (collar) (420-7061) | EACH | 4 | $922.50 | $1,500.00 | $1,000.00 | $1,000.00 | $1,844.70 | $2,500.00 | $3,000.00 |
| 17 | RC pipe (CL IV)(18 in) (464-7019) | LF | 811 | $128.82 | $106.00 | $104.00 | $150.00 | $153.78 | $150.00 | $140.00 |
| 18 | RC pipe (CL IV)(24 in) (464-7021) | LF | 43 | $105.00 | $135.00 | $110.00 | $210.00 | $329.97 | $240.00 | $170.00 |
| 19 | Junction box(complete)(PJB)(3FTX3FT) (465-7005) | EACH | 1 | $5,731.67 | $7,500.00 | $7,000.00 | $9,000.00 | $4,507.80 | $4,500.00 | $6,000.00 |
| 20 | Inlet (complete)(type A)(hou) (465-7313) | EACH | 3 | $8,138.50 | $7,500.00 | $7,000.00 | $8,000.00 | $5,127.10 | $5,000.00 | $7,000.00 |
| 21 | Inlet (complete)(type AZ)(hou) (465-7316) | EACH | 2 | $8,138.50 | $7,500.00 | $7,000.00 | $10,000 | $4,767.40 | $8,000.00 | $6,000.00 |
| 22 | Wingwall (PW - 1) (HW=7 FT) (466-7177) | EACH | 2 | $32,450 | $21,000 | $15,000 | $30,000 | $29,979 | $13,000 | $6,000.00 |
| 23 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 34 | $1,623.67 | $1,200.00 | $2,000.00 | $1,800.00 | $1,560.90 | $2,000.00 | $2,500.00 |
| 24 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 2 | $2,600.00 | $2,000.00 | $2,750.00 | $2,100.00 | $2,310.00 | $3,000.00 | $3,500.00 |
| 25 | Adjusting manholes (479-7001) | EACH | 1 | $1,676.78 | $500.00 | $2,500.00 | $2,000.00 | $1,596.00 | $1,860.36 | $2,000.00 |
| 26 | Removing structure (inlet) (496-7002) | EACH | 3 | $330.00 | $1,000.00 | $1,000.00 | $100.00 | $854.70 | $834.18 | $2,000.00 |
| 27 | Removing structure (pipe) (496-7007) | LF | 671 | $43.18 | $50.00 | $15.00 | $10.00 | $46.46 | $45.47 | $25.00 |
| 28 | Mobilization (500-7001) | LS | 1 | $93,737 | $150,000 | $90,000 | $96,000 | $83,970 | $110,000 | $250,000 |
| 29 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $6,260.71 | $5,000.00 | $6,000.00 | $3,000.00 | $9,350.00 | $2,581.11 | $10,000 |
| 30 | Construction exits (install) (type 1) (506-7020) | SY | 440 | $29.33 | $25.00 | $20.00 | $40.00 | $0.11 | $22.00 | $20.00 |
| 31 | Construction exits (remove) (506-7024) | SY | 440 | $15.00 | $10.00 | $6.00 | $5.00 | $0.11 | $10.00 | $10.00 |
| 32 | Temporary sediment control fence (install) (506-7039) | LF | 2,078 | $5.75 | $4.00 | $4.50 | $5.00 | $0.11 | $2.25 | $7.00 |
| 33 | Temporary sediment control fence (remove) (506-7041) | LF | 2,078 | $1.53 | $1.00 | $2.00 | $2.00 | $0.11 | $0.50 | $2.00 |
| 34 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 164 | $6.92 | $5.00 | $12.00 | $10.00 | $0.11 | $8.00 | $11.00 |
| 35 | Biodegradable erosion control logs (remove) (506-7046) | LF | 164 | $1.37 | $1.00 | $2.00 | $1.00 | $0.11 | $2.00 | $5.00 |
| 36 | Driveways (concrete) (530-7006) | SY | 427 | $171.13 | $110.00 | $100.00 | $130.00 | $138.87 | $180.00 | $126.00 |
| 37 | Driveways (ACP) (530-7010) | SY | 552 | $34.31 | $85.00 | $100.00 | $90.00 | $93.50 | $85.00 | $110.00 |
| 38 | Concrete sidewalks (6") (531-7003) | SY | 1,787 | $173.00 | $75.00 | $100.00 | $115.00 | $161.82 | $125.00 | $126.00 |
| 39 | Curb ramps (type 1) (531-7005) | EACH | 9 | $3,200.00 | $1,500.00 | $2,000.00 | $3,000.00 | $2,234.52 | $3,405.19 | $4,000.00 |
| 40 | Metal W-beam guard fence (timber post) (540-7001) | LF | 100 | $30.01 | $27.00 | $40.00 | $35.00 | $29.70 | $35.00 | $35.00 |
| 41 | Downstream anchor terminal section (540-7015) | EACH | 1 | $1,555.15 | $1,250.00 | $1,800.00 | $1,900.00 | $1,375.00 | $1,850.00 | $1,500.00 |
| 42 | TL-3 31" short radius (transition) (540-7035) | EACH | 1 | $5,798.25 | $1,085.00 | $4,000.00 | $23,000 | $1,193.50 | $1,500.00 | $1,500.00 |
| 43 | Remove metal beam guard fence (542-7001) | LF | 60 | $8.84 | $3.00 | $15.00 | $2.00 | $3.30 | $5.00 | $15.00 |
| 44 | Remove terminal anchor section (542-7002) | EACH | 1 | $194.00 | $220.00 | $400.00 | $500.00 | $242.00 | $500.00 | $500.00 |
| 45 | Remove downstream anchor terminal (542-7003) | EACH | 1 | $273.00 | $230.00 | $400.00 | $500.00 | $253.00 | $150.00 | $500.00 |
| 46 | Guardrail end treatment (install) (544-7001) | EACH | 1 | $3,256.63 | $3,050.00 | $5,000.00 | $3,800.00 | $3,355.00 | $3,850.00 | $4,000.00 |
| 47 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 4 | $275.00 | $315.00 | $400.00 | $500.00 | $346.50 | $415.00 | $750.00 |
| 48 | Mailbox install-D (TWW-post) type 4 (560-7009) | EACH | 3 | $284.61 | $355.00 | $450.00 | $500.00 | $390.50 | $465.00 | $750.00 |
| 49 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 6 | $350.00 | $385.00 | $850.00 | $500.00 | $973.50 | $825.00 | $1,250.00 |
| 50 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 6 | $565.00 | $850.00 | $650.00 | $700.00 | $918.50 | $625.00 | $1,250.00 |
| 51 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 9 | $563.07 | $350.00 | $600.00 | $400.00 | $819.50 | $495.00 | $1,000.00 |
| 52 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 228 | $8.28 | $10.00 | $18.00 | $25.00 | $22.11 | $20.10 | $25.00 |
| 53 | Pavement sler 24" (666-7352) | LF | 228 | $1.71 | $5.00 | $3.00 | $1.00 | $0.79 | $0.75 | $1.50 |
| 54 | Pavement surface preparation for marking (24") (678-7008) | LF | 228 | $0.68 | $5.00 | $3.00 | $0.50 | $0.26 | $0.25 | $1.00 |
| 55 | Remove and relocate meters and boxes (7004-7055) | EACH | 6 | $2,560.00 | $500.00 | $3,000.00 | $3,500.00 | $1,650.00 | $1,352.80 | $2,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 1, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.