TxDOT contract A00184350 bid tabulation
Hazard Elimination & Safety, Various (SOUTH OF SL338 to SOUTH OF COOK RD). Let by Texas DOT on December 3, 2025, Ector, Odessa District. 5 bids received; low bid $6,185,733 by Scout 5 Construction LLC, +4.6% against the engineer's estimate of $5,915,132.
- Owner
- Texas DOT
- Letting
- 03 DEC 2025
- Pay items
- 103
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Scout 5 Construction LLC | $6,185,733 | Low | +5.0% |
| 2 | Ragle Construction, Inc. | $8,383,423 | +36% | +42% |
| 3 | Grey Sky Construction LLC | $8,686,111 | +40% | +47% |
| 4 | Reece Albert, Inc. | $9,523,851 | +54% | +61% |
| 5 | Jones Bros. Dirt & Paving Contractors, Inc. | $11,668,844 | +89% | +97% |
Engineer's estimate: $5,915,132.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Scout 5 Construction LLC | 2. Ragle Construction, Inc. | 3. Grey Sky Construction LLC | 4. Reece Albert, Inc. | 5. Jones Bros. Dirt & Paving Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7003) | SY | 2,612 | $36.88 | $45.00 | $10.00 | $50.00 | $38.39 | $20.13 |
| 2 | Remove (2"-6") TRT/untrt base & asphalt pavement (105-7002) | SY | 5,301 | $6.98 | $10.50 | $5.00 | $10.00 | $6.68 | $15.10 |
| 3 | Excavation (roadway) (110-7001) | CY | 13,551 | $11.00 | $3.00 | $60.00 | $20.00 | $16.13 | $57.78 |
| 4 | Subgr widen (OC) (112-7001) | STA | 96 | $240.00 | $500.00 | $1,500.00 | $450.00 | $4,153.52 | $2,319.74 |
| 5 | Embankment (final)(OC)(type B) (132-7003) | CY | 2,372 | $14.00 | $4.00 | $50.00 | $35.00 | $84.01 | $125.90 |
| 6 | Blading (150-7002) | HR | 40 | $275.00 | $150.00 | $160.00 | $150.00 | $578.81 | $430.60 |
| 7 | Drill seed (permanent_urban_sand) (164-7011) | SY | 55,624 | $0.43 | $0.75 | $0.15 | $0.30 | $0.33 | $0.49 |
| 8 | Proof rolling (216-7001) | HR | 40 | $175.00 | $220.00 | $125.00 | $150.00 | $188.25 | $168.63 |
| 9 | FL BS (compacted in place)(type A GR 4) (10") (247-7092) | SY | 56,310 | $21.00 | $15.50 | $16.00 | $30.00 | $36.00 | $34.08 |
| 10 | Prime coat (MC-30) (310-7004) | GAL | 11,263 | $5.15 | $5.50 | $6.00 | $5.00 | $7.42 | $11.16 |
| 11 | Asphalt (AC-20-5TR) (316-7007) | GAL | 21,399 | $4.00 | $3.00 | $5.00 | $5.00 | $5.98 | $8.93 |
| 12 | Aggregate (type-PB, GR-4)(sac-A) (316-7136) | CY | 624 | $135.00 | $156.00 | $175.00 | $250.00 | $485.96 | $623.01 |
| 13 | SP mixes SP-C PG70-22 (344-7019) | TON | 6,196 | $120.00 | $137.50 | $160.00 | $225.00 | $212.64 | $248.91 |
| 14 | Tom-C PG76-22 sac-A (347-7001) | TON | 3,097 | $180.00 | $180.50 | $190.00 | $300.00 | $307.41 | $284.26 |
| 15 | Drilled shaft (24 in) (416-7004) | LF | 14 | $290.00 | $369.50 | $220.00 | $200.00 | $240.70 | $517.50 |
| 16 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 350 | $400.00 | $355.50 | $450.00 | $300.00 | $296.50 | $632.50 |
| 17 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 56 | $500.00 | $500.50 | $625.00 | $385.00 | $421.23 | $632.50 |
| 18 | Riprap (concrete)(4 in) (432-7001) | CY | 14 | $620.00 | $260.00 | $742.00 | $550.00 | $2,225.73 | $1,725.00 |
| 19 | Riprap (mow strip)(4 in) (432-7013) | CY | 452 | $715.00 | $266.50 | $500.00 | $550.00 | $547.05 | $701.50 |
| 20 | Inl(CMP)(pazd-CZ)(FG)(3FTX3FT-3FTX3FT) (465-7163) | EACH | 4 | $15,000 | $5,200.00 | $5,800.00 | $12,500 | $15,904 | $21,275 |
| 21 | Removing structure (inlet) (496-7002) | EACH | 4 | $1,039.32 | $1,200.00 | $925.00 | $2,500.00 | $2,909.91 | $2,875.00 |
| 22 | Removing structure (set) (496-7004) | EACH | 2 | $700.00 | $200.00 | $625.00 | $500.00 | $1,249.26 | $1,725.00 |
| 23 | Removing structure (pipe) (496-7007) | LF | 42 | $20.00 | $15.00 | $50.00 | $50.00 | $59.49 | $57.50 |
| 24 | Mobilization (500-7001) | LS | 1 | $281,411 | $545,000 | $840,000 | $800,000 | $802,636 | $750,000 |
| 25 | Barricades, signs and traffic handling (502-7001) | MO | 11 | $16,000 | $3,640.00 | $98,000 | $12,500 | $13,229 | $50,000 |
| 26 | Portable changeable message sign (503-7002) | EACH | 2 | $11,125 | $2,730.00 | $33,500 | $20,000 | $16,013 | $30,000 |
| 27 | TMA (stationary) (505-7001) | DAY | 330 | $200.00 | $195.00 | $303.00 | $250.00 | $402.00 | $187.50 |
| 28 | TMA (mobile operation) (505-7003) | DAY | 9 | $225.00 | $195.00 | $632.00 | $550.00 | $883.19 | $1,275.00 |
| 29 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 3,218 | $8.00 | $5.50 | $8.00 | $12.00 | $9.85 | $16.85 |
| 30 | Biodegradable erosion control logs (remove) (506-7046) | LF | 3,218 | $1.32 | $2.00 | $1.50 | $9.00 | $1.64 | $2.18 |
| 31 | Metal W-beam guard fence (steel post) (540-7002) | LF | 713 | $32.00 | $26.50 | $35.00 | $35.00 | $38.29 | $41.40 |
| 32 | Downstream anchor terminal section (540-7015) | EACH | 4 | $1,500.00 | $1,324.00 | $2,000.00 | $1,850.00 | $2,188.19 | $2,443.75 |
| 33 | Cable barrier system (install)(TL-4) (543-7002) | LF | 9,057 | $10.00 | $14.00 | $16.50 | $25.00 | $18.05 | $19.55 |
| 34 | Cable barrier terminal sec (install)(TL-4) (543-7018) | EACH | 38 | $1,925.00 | $1,260.00 | $4,500.00 | $3,850.00 | $4,923.43 | $5,359.00 |
| 35 | Cable barrier (remove) (543-7037) | LF | 7,825 | $6.25 | $7.00 | $1.00 | $3.00 | $1.09 | $4.60 |
| 36 | Cable barrier terminal section (remove) (543-7038) | EACH | 23 | $1,320.00 | $800.00 | $1,000.00 | $500.00 | $1,094.10 | $1,725.00 |
| 37 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,500.00 | $3,126.00 | $4,000.00 | $3,850.00 | $4,376.38 | $4,082.50 |
| 38 | In RD IL (type AL) 40T-8 (250W EQ) LED (610-7140) | EACH | 5 | $6,000.00 | $7,001.50 | $6,000.00 | $6,500.00 | $5,676.17 | $7,475.00 |
| 39 | In RD IL (type AL) 50T-8-8 (400W EQ) LED (610-7213) | EACH | 31 | $7,500.00 | $8,808.50 | $9,500.00 | $6,500.00 | $7,382.95 | $12,075 |
| 40 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 7,560 | $17.50 | $26.50 | $10.00 | $20.00 | $21.90 | $11.50 |
| 41 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 1,135 | $30.00 | $66.00 | $50.00 | $60.00 | $54.70 | $57.50 |
| 42 | Conduit (PVC) (schedule 80) (3") (618-7060) | LF | 165 | $25.00 | $41.00 | $30.00 | $30.00 | $28.60 | $34.50 |
| 43 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 415 | $35.00 | $81.00 | $60.00 | $60.00 | $65.65 | $69.00 |
| 44 | Electrical conductor (no.8) bare (620-7007) | LF | 9,360 | $1.70 | $3.50 | $1.25 | $3.00 | $2.74 | $1.44 |
| 45 | Electrical conductor (no.8) insulated (620-7008) | LF | 22,250 | $1.80 | $4.00 | $1.75 | $3.00 | $3.02 | $2.01 |
| 46 | Electrical conductor (no.6) bare (620-7009) | LF | 440 | $1.85 | $7.50 | $1.75 | $3.00 | $3.92 | $2.01 |
| 47 | Electrical conductor (no.6) insulated (620-7010) | LF | 70 | $2.20 | $6.00 | $2.25 | $3.00 | $4.65 | $2.59 |
| 48 | Ground box type A (122311)W/apron (624-7002) | EACH | 22 | $1,800.00 | $2,181.00 | $1,750.00 | $1,150.00 | $1,750.55 | $2,012.50 |
| 49 | Ground box type D (162922)W/apron (624-7008) | EACH | 5 | $2,500.00 | $2,835.00 | $2,500.00 | $1,150.00 | $2,199.13 | $2,875.00 |
| 50 | Elc SRV type A 240/480 060(NS)SS(E)SP(O) (628-7048) | EACH | 3 | $8,500.00 | $9,808.00 | $12,000 | $12,500 | $7,943.13 | $12,650 |
| 51 | Elc SRV type D 120/240 060(SS)SS(E)SP(O) (628-7161) | EACH | 1 | $5,500.00 | $10,080 | $13,000 | $12,500 | $7,549.26 | $13,800 |
| 52 | Aluminum signs (type A) (636-7001) | SF | 78 | $44.00 | $52.00 | $75.00 | $30.00 | $31.73 | $46.00 |
| 53 | Aluminum signs (type G) (636-7002) | SF | 110 | $42.00 | $60.50 | $30.00 | $30.00 | $32.82 | $43.70 |
| 54 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 60 | $740.00 | $444.00 | $690.00 | $1,150.00 | $754.93 | $1,035.00 |
| 55 | Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002) | EACH | 50 | $850.00 | $731.50 | $850.00 | $1,150.00 | $929.98 | $1,270.75 |
| 56 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 10 | $840.00 | $562.50 | $750.00 | $1,150.00 | $820.57 | $1,132.75 |
| 57 | Install small roadside sign support and assembly TYS80(1)SA(P-BM) (644-7026) | EACH | 12 | $1,090.00 | $869.00 | $990.00 | $1,150.00 | $1,083.15 | $1,437.50 |
| 58 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 1 | $1,050.00 | $725.50 | $990.00 | $1,150.00 | $1,083.15 | $1,345.50 |
| 59 | Install small roadside sign support and assembly TYS80(1)SA(U-BM) (644-7034) | EACH | 1 | $1,525.00 | $1,098.00 | $990.00 | $1,150.00 | $1,083.15 | $1,725.00 |
| 60 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 43 | $625.00 | $312.00 | $495.00 | $1,000.00 | $541.58 | $1,063.75 |
| 61 | Relocate SM RD SN sup&AM type S80 (644-7067) | EACH | 3 | $700.00 | $410.00 | $600.00 | $1,000.00 | $656.46 | $1,081.00 |
| 62 | Remove SM RD SN sup&AM (644-7073) | EACH | 149 | $112.00 | $100.00 | $80.00 | $50.00 | $162.14 | $155.72 |
| 63 | Install LRSS (struct steel) (647-7001) | LB | 591 | $9.00 | $10.97 | $7.95 | $20.00 | $8.70 | $15.53 |
| 64 | Remove lrsa (647-7003) | EACH | 1 | $850.00 | $1,274.00 | $950.00 | $5,000.00 | $1,039.39 | $1,725.00 |
| 65 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (658-7015) | EACH | 19 | $27.00 | $6.00 | $30.00 | $100.00 | $32.82 | $34.50 |
| 66 | Install delineator assembly (D-DY)SZ 2(WC)GND (658-7053) | EACH | 44 | $52.00 | $64.50 | $75.00 | $100.00 | $82.06 | $143.75 |
| 67 | Install object marker assembly (OM-2Y)(WC)GND (658-7056) | EACH | 34 | $88.00 | $68.25 | $75.00 | $100.00 | $82.06 | $143.75 |
| 68 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 2,262 | $1.50 | $2.00 | $0.90 | $4.00 | $0.98 | $1.44 |
| 69 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 43,973 | $1.05 | $2.00 | $0.89 | $3.00 | $0.97 | $0.98 |
| 70 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 116,788 | $0.90 | $2.00 | $0.69 | $0.65 | $0.75 | $1.00 |
| 71 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 117,459 | $0.90 | $2.00 | $0.69 | $0.65 | $0.75 | $1.00 |
| 72 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 29,888 | $0.70 | $3.00 | $0.60 | $0.65 | $0.66 | $0.76 |
| 73 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 1,289 | $15.00 | $12.00 | $11.00 | $20.00 | $12.04 | $16.10 |
| 74 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 97 | $240.00 | $195.00 | $190.00 | $250.00 | $207.88 | $287.50 |
| 75 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 97 | $300.00 | $260.00 | $230.00 | $250.00 | $251.64 | $368.00 |
| 76 | Prefabricated PM type C (W)(36")(yld tri) (668-7111) | EACH | 484 | $38.00 | $36.00 | $25.00 | $150.00 | $27.35 | $20.70 |
| 77 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 3,896 | $4.00 | $6.00 | $3.69 | $6.00 | $4.33 | $4.89 |
| 78 | Eliminating existing PM & markers (4") (677-7001) | LF | 110,031 | $0.30 | $0.50 | $1.00 | $0.50 | $1.93 | $5.56 |
| 79 | Eliminating existing PM & markers (24") (677-7008) | LF | 148 | $15.00 | $2.00 | $6.00 | $20.00 | $21.05 | $22.00 |
| 80 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 11 | $36.00 | $65.00 | $75.00 | $250.00 | $97.26 | $33.00 |
| 81 | Eliminating existing PM & markers (word) (677-7015) | EACH | 12 | $44.00 | $65.00 | $75.00 | $250.00 | $91.49 | $55.00 |
| 82 | Eliminating existing PM & markers (36")(yld tri) (677-7024) | EACH | 12 | $13.00 | $65.00 | $25.00 | $150.00 | $91.49 | $66.00 |
| 83 | Install highway traffic signal (isolated) (680-7002) | EACH | 1 | $40,000 | $51,000 | $45,000 | $50,000 | $41,029 | $57,500 |
| 84 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 7 | $360.00 | $534.50 | $350.00 | $350.00 | $316.19 | $373.75 |
| 85 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 2 | $360.00 | $1,862.00 | $350.00 | $350.00 | $316.20 | $373.75 |
| 86 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 7 | $360.00 | $534.50 | $350.00 | $350.00 | $316.19 | $373.75 |
| 87 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 2 | $360.00 | $934.50 | $350.00 | $350.00 | $316.20 | $373.75 |
| 88 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 7 | $360.00 | $534.50 | $350.00 | $350.00 | $316.19 | $373.75 |
| 89 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 4 | $360.00 | $653.50 | $350.00 | $350.00 | $316.19 | $373.75 |
| 90 | Backplate W/ref border(3 sec)(vent)aluminum (682-7042) | EACH | 7 | $180.00 | $373.00 | $200.00 | $200.00 | $180.53 | $230.00 |
| 91 | Backplate W/ref border(4 sec)(vent)aluminum (682-7043) | EACH | 2 | $220.00 | $863.00 | $250.00 | $250.00 | $259.30 | $287.50 |
| 92 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 345 | $3.40 | $7.00 | $3.00 | $3.00 | $3.13 | $3.45 |
| 93 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 105 | $4.30 | $16.00 | $4.00 | $3.00 | $4.29 | $4.60 |
| 94 | Traffic signal CBL (type A)(14 AWG)(12 conductor) (684-7038) | LF | 585 | $5.60 | $10.00 | $6.00 | $3.00 | $6.46 | $6.90 |
| 95 | Remove RDSD flash beacon assembly (685-7003) | EACH | 1 | $800.00 | $1,313.00 | $650.00 | $2,500.00 | $1,105.04 | $747.50 |
| 96 | Ins traffic signal PL AM(S)1 arm(44') (686-7045) | EACH | 1 | $15,650 | $24,580 | $17,500 | $20,000 | $18,818 | $20,125 |
| 97 | Ins traffic signal PL AM(S)1 arm(48') (686-7049) | EACH | 2 | $21,000 | $24,500 | $20,000 | $25,000 | $20,131 | $23,000 |
| 98 | Bonding course (3007-7001) | GAL | 5,632 | $3.20 | $4.00 | $8.38 | $5.00 | $3.43 | $12.06 |
| 99 | Bbu system (external battery cabinet) (6007-7001) | EACH | 1 | $11,250 | $15,735 | $12,500 | $8,500.00 | $12,309 | $13,800 |
| 100 | RVDS (presence detection only) (6008-7001) | EACH | 3 | $8,920.00 | $9,769.00 | $12,500 | $12,500 | $7,910.31 | $18,975 |
| 101 | RVDS (advance detection only) (6008-7002) | EACH | 3 | $8,830.00 | $9,769.00 | $12,500 | $12,500 | $7,910.31 | $18,975 |
| 102 | CCTV field equip (digital) (install only) (6018-7001) | EACH | 1 | $3,640.00 | $22,748 | $12,500 | $8,500.00 | $1,378.56 | $13,225 |
| 103 | CCTV mount (pole) (6018-7003) | EACH | 1 | $322.00 | $3,912.00 | $5,000.00 | $1,500.00 | $2,357.77 | $5,175.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of December 3, 2025. Compiled by Mirage Metrics.