TxDOT contract A00184478 bid tabulation
Highway Improvement, US 79 (0.1 Mi E of SH 75 to 0.2 Mi E of FM 1848). Let by Texas DOT on April 3, 2025, Leon, Bryan District. 6 bids received; low bid $2,870,625 by Larry Young Paving, Inc., -15% against the engineer's estimate of $3,385,053.
- Owner
- Texas DOT
- Letting
- 03 APR 2025
- Pay items
- 105
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Larry Young Paving, Inc. | $2,870,625 | Low | -15% |
| 2 | Cornerstone Paving and Construction, L.L.C. | $3,299,950 | +15% | -3.0% |
| 3 | Brazos Paving, Inc. | $3,401,661 | +18% | 0.0% |
| 4 | Big Creek Construction, LTD. | $3,600,417 | +25% | +6.0% |
| 5 | A. L. Helmcamp, Inc. | $3,649,250 | +27% | +8.0% |
| 6 | Knife River Corporation - South | $3,975,045 | +38% | +17% |
Engineer's estimate: $3,385,053.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Larry Young Paving, Inc. | 2. Cornerstone Paving and Construction, L.L.C. | 3. Brazos Paving, Inc. | 4. Big Creek Construction, LTD. | 5. A. L. Helmcamp, Inc. | 6. Knife River Corporation - South |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 21 | $1,100.00 | $1,000.00 | $3,200.00 | $1,500.00 | $4,000.00 | $3,000.00 | |
| 2 | Preparation row (tree remove) (24"-36" diameter) (100-7005) | EACH | 1 | $1,700.00 | $2,000.00 | $2,000.00 | $1,770.00 | $2,000.00 | $2,500.00 | $2,000.00 |
| 3 | Removing concrete (driveways) (104-7011) | SY | 785 | $17.00 | $35.00 | $31.50 | $18.00 | $56.00 | $35.00 | |
| 4 | Removing concrete (curb ramp) (104-7015) | SY | 10 | $20.00 | $65.00 | $36.00 | $30.00 | $250.00 | $100.00 | |
| 5 | Remove (0"-4") TRT/untrt base & asphalt pavement (105-7001) | SY | 1,448 | $29.00 | $9.00 | $40.00 | $6.50 | $14.00 | $28.00 | $20.00 |
| 6 | Remove (16") TRT/untrt base & asphalt pavement (105-7036) | SY | 1,328 | $12.00 | $65.00 | $14.65 | $20.00 | $32.00 | $24.00 | |
| 7 | Excavation (roadway) (110-7001) | CY | 2,076 | $21.00 | $40.00 | $25.00 | $30.00 | $16.00 | $40.00 | |
| 8 | Embankment (final)(OC)(type C) (132-7005) | CY | 424 | $48.00 | $45.00 | $35.00 | $30.00 | $50.00 | $110.00 | |
| 9 | Embankment (final)(DC)(type C) (132-7006) | CY | 1,888 | $30.00 | $42.50 | $40.00 | $30.00 | $25.00 | $40.00 | |
| 10 | Backfill (type A or B) (134-7004) | STA | 38 | $230.00 | $500.00 | $625.00 | $220.00 | $340.00 | $400.00 | |
| 11 | Furn & place topsoil (4") (160-7002) | SY | 11,608 | $1.50 | $1.00 | $4.95 | $1.50 | $1.50 | $2.50 | |
| 12 | Block sodding (162-7002) | SY | 2,245 | $7.50 | $5.75 | $6.78 | $6.25 | $6.50 | $6.75 | |
| 13 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 9,636 | $1.00 | $0.75 | $0.88 | $0.80 | $0.75 | $0.40 | |
| 14 | Broadcast seed (temporary_warm) (164-7005) | SY | 5,945 | $0.75 | $0.65 | $0.77 | $0.70 | $0.70 | $0.27 | |
| 15 | Broadcast seed (temporary_cool) (164-7006) | SY | 5,945 | $0.75 | $0.65 | $0.77 | $0.70 | $0.70 | $0.27 | |
| 16 | Vegetative watering (168-7001) | TGL | 242 | $56.00 | $10.00 | $92.00 | $35.00 | $50.00 | $55.00 | |
| 17 | Rdside amenity (wheel stop) (194-7007) | EACH | 2 | $280.00 | $1,000.00 | $150.00 | $300.00 | $1,700.00 | $750.00 | |
| 18 | FL BS (compacted in place)(type A GR 1-2) (10") (247-7090) | SY | 4,133 | $28.00 | $35.00 | $29.00 | $40.00 | $26.00 | $40.00 | |
| 19 | Cement (275-7001) | TON | 52 | $310.00 | $300.00 | $408.00 | $325.00 | $275.00 | $300.00 | |
| 20 | Cement TRT (subgrade)(10") (275-7028) | SY | 4,133 | $6.00 | $6.30 | $18.00 | $4.00 | $5.00 | $7.50 | |
| 21 | Prime coat (MC-30) (310-7004) | GAL | 827 | $6.50 | $6.50 | $8.25 | $6.00 | $7.00 | $12.00 | |
| 22 | D-GR HMA type D PG64-22 (level-UP) (341-7046) | TON | 904 | $130.00 | $134.25 | $130.00 | $130.00 | $155.00 | $170.00 | |
| 23 | Tack coat (341-7082) | GAL | 1,096 | $6.00 | $4.00 | $7.10 | $4.25 | $8.00 | $3.50 | |
| 24 | SP mixes SP-B sac-B PG64-22 (344-7002) | TON | 910 | $125.00 | $145.00 | $148.00 | $130.00 | $155.00 | $160.00 | |
| 25 | SP mixes SP-C sac-A PG70-22 (344-7020) | TON | 2,223 | $135.00 | $134.00 | $164.00 | $145.00 | $165.00 | $175.00 | |
| 26 | Tack coat (344-7077) | GAL | 2,021 | $6.00 | $4.00 | $7.10 | $4.25 | $7.00 | $3.50 | |
| 27 | Stone-MTRX-asphalt SMA-C sac-A PG76-22 (346-7001) | TON | 2,558 | $168.00 | $190.00 | $175.00 | $182.00 | $225.00 | $220.00 | $210.00 |
| 28 | Tack coat (346-7028) | GAL | 2,067 | $4.50 | $6.00 | $4.00 | $7.20 | $4.25 | $7.00 | $3.50 |
| 29 | Plane & text asphalt concrete pavement(0" to 2") (354-7002) | SY | 1,960 | $5.00 | $8.20 | $6.25 | $5.00 | $7.50 | $6.00 | |
| 30 | Planing asphalt concrete pavement(0" to 2.25") (354-7075) | SY | 20,665 | $3.50 | $1.75 | $3.40 | $5.00 | $3.00 | $3.50 | $3.50 |
| 31 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 16 | $330.00 | $347.00 | $351.00 | $420.00 | $330.00 | $400.00 | |
| 32 | Retaining wall (cast-in-place) (423-7016) | SF | 345 | $61.00 | $150.00 | $92.00 | $100.00 | $96.00 | $95.00 | |
| 33 | Riprap (concrete)(4 in) (432-7001) | CY | 30 | $780.00 | $800.00 | $1,445.00 | $735.00 | $780.00 | $950.00 | |
| 34 | Riprap (concrete)(5 in) (432-7002) | CY | 19 | $880.00 | $900.00 | $676.00 | $765.00 | $810.00 | $1,060.00 | |
| 35 | Riprap (concrete) (CL B) (4 in) (432-7007) | CY | 0.70 | $780.00 | $1,200.00 | $944.00 | $750.00 | $2,200.00 | $1,500.00 | |
| 36 | Rail (type PR11) (450-7044) | LF | 18 | $260.00 | $600.00 | $708.00 | $317.00 | $520.00 | $780.00 | |
| 37 | Rail (handrail)(type A) (450-7058) | LF | 228 | $77.00 | $115.00 | $135.70 | $122.00 | $140.00 | $150.00 | |
| 38 | Rail (handrail)(type E) (450-7062) | LF | 56 | $170.00 | $150.00 | $135.70 | $215.00 | $280.00 | $200.00 | |
| 39 | Concrete box culvert (3 FT X 2 FT)(extend) (462-7056) | LF | 6 | $520.00 | $850.00 | $1,003.00 | $950.00 | $1,100.00 | $1,500.00 | |
| 40 | RC pipe (CL III)(18 in) (464-7003) | LF | 290 | $69.00 | $65.00 | $95.00 | $78.00 | $86.00 | $85.00 | |
| 41 | RC pipe (CL IV)(18 in) (464-7019) | LF | 88 | $78.00 | $70.00 | $102.00 | $97.00 | $100.00 | $100.00 | |
| 42 | Inlet (comp)(type sidewalk bridge) (465-7336) | EACH | 12 | $14,000 | $16,000 | $17,612 | $20,000 | $29,000 | $12,000 | |
| 43 | Wingwall (PW - 1) (HW=4 FT) (466-7174) | EACH | 1 | $14,000 | $7,000.00 | $21,122 | $10,600 | $25,000 | $14,000 | |
| 44 | Set (type II) (18 in) (RCP) (3: 1) (C) (467-7305) | EACH | 3 | $1,400.00 | $850.00 | $1,450.00 | $1,100.00 | $900.00 | $1,200.00 | |
| 45 | Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306) | EACH | 2 | $1,400.00 | $900.00 | $1,500.00 | $1,280.00 | $1,200.00 | $1,200.00 | |
| 46 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 21 | $1,500.00 | $950.00 | $1,625.00 | $1,500.00 | $1,300.00 | $1,500.00 | |
| 47 | Adjusting manholes (utility box) (479-7004) | EACH | 2 | $760.00 | $2,000.00 | $2,500.00 | $1,000.00 | $1,500.00 | $3,000.00 | |
| 48 | Adjusting inlets (cap) (479-7006) | EACH | 1 | $1,600.00 | $2,000.00 | $3,000.00 | $2,800.00 | $1,500.00 | $3,500.00 | |
| 49 | Adjusting manholes (water valve box) (479-7007) | EACH | 3 | $450.00 | $2,000.00 | $650.00 | $1,300.00 | $1,500.00 | $3,000.00 | |
| 50 | Clean existing culverts (480-7001) | EACH | 2 | $2,200.00 | $2,500.00 | $3,304.00 | $3,200.00 | $8,400.00 | $3,000.00 | |
| 51 | Removing structure (inlet) (496-7002) | EACH | 2 | $1,000.00 | $650.00 | $1,180.00 | $1,700.00 | $2,400.00 | $800.00 | |
| 52 | Removing structure (set) (496-7004) | EACH | 14 | $390.00 | $650.00 | $360.00 | $450.00 | $1,400.00 | $800.00 | |
| 53 | Removing structure (headwall) (496-7006) | EACH | 5 | $1,000.00 | $1,500.00 | $2,125.00 | $1,200.00 | $2,400.00 | $1,800.00 | |
| 54 | Removing structure (pipe) (496-7007) | LF | 378 | $28.00 | $40.00 | $24.00 | $20.00 | $35.00 | $60.00 | |
| 55 | Mobilization (500-7001) | LS | 1 | $314,187 | $270,000 | $200,000 | $287,280 | $359,000 | $200,000 | $395,000 |
| 56 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $5,000.00 | $3,900.00 | $7,500.00 | $6,805.00 | $7,000.00 | $8,000.00 | $27,500 |
| 57 | Portable changeable message sign (503-7002) | EACH | 4 | $6,700.00 | $3,700.00 | $17,500 | $9,000.00 | $10,000 | $11,000 | $20,000 |
| 58 | TMA (stationary) (505-7001) | DAY | 89 | $302.00 | $210.00 | $125.00 | $460.00 | $200.00 | $250.00 | $300.00 |
| 59 | TMA (mobile operation) (505-7003) | DAY | 9 | $500.00 | $1,000.00 | $125.00 | $810.00 | $935.00 | $250.00 | $855.00 |
| 60 | Rock filter dams (install) (type 1) (506-7001) | LF | 40 | $65.00 | $50.00 | $59.00 | $55.00 | $54.00 | $58.00 | |
| 61 | Rock filter dams (install) (type 2) (506-7002) | LF | 560 | $49.00 | $38.00 | $45.00 | $40.00 | $42.00 | $45.00 | |
| 62 | Rock filter dams (remove) (506-7011) | LF | 600 | $13.00 | $10.00 | $11.80 | $11.00 | $10.00 | $12.00 | |
| 63 | Sandbags for erosion control (506-7035) | EACH | 24 | $39.00 | $30.00 | $35.40 | $35.00 | $40.00 | $40.00 | |
| 64 | Temporary sediment control fence (install) (506-7039) | LF | 936 | $7.25 | $5.50 | $6.50 | $6.00 | $6.00 | $10.00 | |
| 65 | Temporary sediment control fence (remove) (506-7041) | LF | 936 | $2.00 | $1.50 | $1.77 | $1.75 | $1.50 | $1.75 | |
| 66 | Concrete curb (type II) (529-7002) | LF | 29 | $4.00 | $85.00 | $15.75 | $200.00 | $75.00 | $55.00 | |
| 67 | Concrete curb & gutter (type I) (529-7008) | LF | 7 | $44.00 | $100.00 | $42.20 | $225.00 | $145.00 | $55.00 | |
| 68 | Concrete curb & gutter (type II) (529-7009) | LF | 1,126 | $43.00 | $65.00 | $41.00 | $80.00 | $51.00 | $55.00 | |
| 69 | Driveways (concrete) (530-7006) | SY | 1,334 | $96.00 | $175.00 | $113.20 | $180.00 | $125.00 | $135.00 | |
| 70 | Driveways (ACP) (530-7010) | SY | 2,111 | $45.00 | $33.00 | $60.00 | $35.00 | $80.00 | $90.00 | $110.00 |
| 71 | Concrete sidewalks (4") (531-7001) | SY | 749 | $68.00 | $150.00 | $93.85 | $150.00 | $160.00 | $90.00 | |
| 72 | Curb ramps (type 1) (531-7005) | EACH | 4 | $2,600.00 | $3,000.00 | $2,485.00 | $3,000.00 | $2,100.00 | $3,000.00 | |
| 73 | Curb ramps (type 10) (531-7011) | EACH | 4 | $2,700.00 | $3,000.00 | $3,200.00 | $3,500.00 | $2,100.00 | $4,000.00 | |
| 74 | Mailbox install-S (TWG-post) type 2 (560-7002) | EACH | 6 | $490.00 | $447.00 | $530.00 | $410.00 | $410.00 | $500.00 | |
| 75 | Relocate existing mailbox (560-7012) | EACH | 8 | $490.00 | $257.00 | $303.25 | $410.00 | $410.00 | $500.00 | |
| 76 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 2 | $7,400.00 | $6,900.00 | $11,260 | $7,600.00 | $11,000 | $15,000 | |
| 77 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 38 | $28.00 | $10.10 | $23.60 | $11.00 | $23.00 | $25.00 | |
| 78 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 227 | $19.00 | $15.00 | $40.70 | $18.00 | $38.00 | $45.00 | |
| 79 | Electrical conductor (no.8) insulated (620-7008) | LF | 795 | $2.50 | $2.35 | $3.55 | $2.50 | $3.50 | $3.50 | |
| 80 | Ground box type D (162922)W/apron (624-7008) | EACH | 4 | $1,700.00 | $1,400.00 | $2,415.00 | $1,500.00 | $2,300.00 | $3,000.00 | |
| 81 | Elc SRV type D 120/240 100(NS)SS(E)SP(O) (628-7248) | EACH | 1 | $8,500.00 | $12,800 | $9,735.00 | $14,000 | $9,100.00 | $12,500 | |
| 82 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 34 | $700.00 | $830.00 | $672.00 | $793.00 | $700.00 | $700.00 | $815.00 |
| 83 | Remove SM RD SN sup&AM (644-7073) | EACH | 6 | $410.00 | $110.00 | $130.00 | $345.00 | $350.00 | $350.00 | |
| 84 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 4 | $69.00 | $64.00 | $111.00 | $55.00 | $60.00 | $100.00 | |
| 85 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 1,748 | $1.22 | $0.75 | $1.00 | $1.15 | $1.50 | $1.50 | $1.75 |
| 86 | Reflectorized pavement marking type I (W)8"(DOT)(090MIL) (666-7017) | LF | 66 | $6.25 | $3.00 | $3.55 | $5.00 | $3.30 | $3.53 | |
| 87 | Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023) | LF | 1,880 | $2.00 | $3.50 | $1.00 | $1.18 | $2.75 | $1.10 | $1.18 |
| 88 | Reflectorized pavement marking type I (W)12"(solid)(090MIL) (666-7029) | LF | 48 | $1.70 | $18.00 | $4.00 | $4.75 | $14.00 | $4.40 | $4.71 |
| 89 | Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035) | LF | 125 | $8.00 | $21.00 | $7.00 | $8.25 | $17.00 | $7.70 | $8.24 |
| 90 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 535 | $21.00 | $7.00 | $8.25 | $17.00 | $7.70 | $8.24 | |
| 91 | Reflectorized pavement marking type I (W)4"(solid)(090MIL) (666-7404) | LF | 926 | $4.50 | $6.25 | $3.50 | $4.15 | $5.25 | $3.85 | $4.12 |
| 92 | Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410) | LF | 12,608 | $0.54 | $1.50 | $0.80 | $0.94 | $1.25 | $0.90 | $0.94 |
| 93 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 114 | $1.50 | $2.00 | $2.36 | $1.25 | $2.20 | $2.35 | |
| 94 | Reflectorized pavement marking type I (Y)6"(broken)(090MIL) (666-7419) | LF | 1,361 | $0.55 | $1.50 | $0.80 | $0.94 | $1.25 | $0.90 | $0.94 |
| 95 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 16,011 | $0.54 | $1.50 | $0.80 | $0.94 | $1.25 | $0.88 | $0.94 |
| 96 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 124 | $1.50 | $2.00 | $2.36 | $1.25 | $2.20 | $2.35 | |
| 97 | PRFB rumble strip (BLK)(1')(centerline) (668-7002) | LF | 4,866 | $7.25 | $4.00 | $4.70 | $5.25 | $4.40 | $4.71 | |
| 98 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 28 | $270.00 | $510.00 | $215.00 | $255.00 | $425.00 | $240.00 | $252.00 |
| 99 | Prefabricated PM type C (W)(double arrow) (668-7093) | EACH | 2 | $370.00 | $660.00 | $300.00 | $354.00 | $530.00 | $330.00 | $352.00 |
| 100 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 10 | $330.00 | $620.00 | $265.00 | $313.00 | $500.00 | $300.00 | $312.00 |
| 101 | Pre PM type C (WHT)(acc PRK)(symbl only) (668-7132) | EACH | 2 | $1,690.87 | $830.00 | $350.00 | $413.00 | $650.00 | $385.00 | $450.00 |
| 102 | PRFB rumble strip (BLK)(1')(edgeline) (668-7137) | LF | 7,180 | $6.50 | $4.00 | $4.75 | $5.50 | $4.40 | $4.71 | |
| 103 | Reflectorized pavement marker type I-C (672-7002) | EACH | 90 | $3.50 | $12.00 | $5.00 | $5.90 | $10.00 | $5.50 | $5.75 |
| 104 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 588 | $4.50 | $8.50 | $5.00 | $5.90 | $7.00 | $5.50 | $5.75 |
| 105 | Install RDSD FLSH BCN assembly (solar PWRD) (685-7004) | EACH | 1 | $6,200.00 | $12,800 | $12,425 | $14,000 | $12,000 | $15,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 3, 2025. Compiled by Mirage Metrics.