TxDOT contract A00187296 bid tabulation
Rehabilitate Existing Roadway, FM 159 (9.8 Mi S of FM 2154 to SH 105). Let by Texas DOT on April 4, 2025, Brazos, Bryan District. 5 bids received; low bid $6,280,471 by Brazos Paving, Inc., -5.7% against the engineer's estimate of $6,658,923.
- Owner
- Texas DOT
- Letting
- 04 APR 2025
- Pay items
- 97
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Brazos Paving, Inc. | $6,280,471 | Low | -6.0% |
| 2 | Texas Materials Group, Inc. | $7,073,471 | +13% | +6.0% |
| 3 | Cornerstone Paving and Construction, L.L.C. | $7,523,366 | +20% | +13% |
| 4 | Knife River Corporation - South | $7,776,380 | +24% | +17% |
| 5 | Big Creek Construction, LTD. | $8,887,999 | +42% | +33% |
Engineer's estimate: $6,658,923.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Brazos Paving, Inc. | 2. Texas Materials Group, Inc. | 3. Cornerstone Paving and Construction, L.L.C. | 4. Knife River Corporation - South | 5. Big Creek Construction, LTD. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 65 | $2,000.00 | $550.00 | $3,900.00 | $1,600.00 | $585.00 | $1,000.00 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 90 | $12.50 | $21.50 | $165.00 | $25.00 | $71.00 | $50.00 |
| 3 | Remove (2"-8") TRT/untrt base & asphalt pavement (105-7053) | SY | 1,124 | $20.00 | $13.20 | $20.00 | $20.00 | $9.48 | $15.00 |
| 4 | Excavation (roadway) (110-7001) | CY | 19,045.35 | $17.00 | $18.60 | $19.00 | $42.75 | $14.95 | $25.00 |
| 5 | Embankment (final)(DC)(type C) (132-7006) | CY | 2,085.65 | $22.00 | $21.50 | $30.00 | $30.70 | $5.00 | $25.00 |
| 6 | Furn & place topsoil (4") (160-7009) | STA | 203.53 | $225.00 | $98.00 | $280.00 | $300.00 | $134.00 | $250.00 |
| 7 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 24,974 | $0.42 | $0.22 | $0.30 | $0.30 | $0.24 | $0.25 |
| 8 | Broadcast seed (temporary_warm) (164-7005) | SY | 12,487 | $0.28 | $0.14 | $0.28 | $0.28 | $0.23 | $0.15 |
| 9 | Broadcast seed (temporary_cool) (164-7006) | SY | 12,487 | $0.28 | $0.17 | $0.28 | $0.28 | $0.23 | $0.20 |
| 10 | Vegetative watering (168-7001) | TGL | 500 | $35.00 | $66.00 | $30.00 | $10.00 | $37.70 | $25.00 |
| 11 | FL BS (compacted in place)(type A GR 1-2) (8") (247-7067) | SY | 67,599 | $23.00 | $19.80 | $23.00 | $21.20 | $21.33 | $25.00 |
| 12 | Rework BS metal (type B)(6")(ord comp) (251-7025) | SY | 53,715 | $3.75 | $2.05 | $3.30 | $7.50 | $1.46 | $3.50 |
| 13 | Cement (275-7001) | TON | 1,076 | $250.00 | $260.00 | $235.00 | $260.00 | $243.00 | $300.00 |
| 14 | Cement TRT (existing material)(10") (275-7004) | SY | 76,631 | $4.25 | $2.65 | $1.50 | $3.30 | $1.52 | $3.50 |
| 15 | Asphalt (AC-20XP) (316-7006) | GAL | 48,173 | $5.50 | $3.90 | $4.80 | $4.60 | $3.75 | $4.50 |
| 16 | Asphalt (RC-250) (316-7016) | GAL | 16,900 | $6.50 | $4.00 | $5.30 | $7.15 | $5.00 | $5.00 |
| 17 | Aggregate (type-PB or PL, GR-4)(sac-A) (316-7241) | CY | 1,071 | $179.00 | $180.00 | $208.00 | $175.00 | $176.49 | $170.00 |
| 18 | Aggregate (type-B or L, GR-5) (316-7251) | CY | 501 | $165.00 | $154.75 | $202.00 | $133.00 | $189.64 | $140.00 |
| 19 | SP mixes SP-C PG64-22 (344-7009) | TON | 76 | $150.00 | $181.65 | $370.00 | $280.00 | $281.00 | $300.00 |
| 20 | Tack coat (344-7077) | GAL | 69 | $5.00 | $8.00 | $32.00 | $15.00 | $5.00 | $10.00 |
| 21 | Cut & restoring pavement (400-7006) | SY | 186 | $175.00 | $29.85 | $100.00 | $165.00 | $33.19 | $100.00 |
| 22 | Cem stabil BKFL (400-7010) | CY | 112 | $225.00 | $100.20 | $280.00 | $1,000.00 | $195.00 | $250.00 |
| 23 | Trench excavation protection (402-7001) | LF | 224 | $25.00 | $2.00 | $3.00 | $9.00 | $48.00 | $20.00 |
| 24 | Drilled shaft (18 in) (416-7002) | LF | 216 | $200.00 | $361.40 | $132.00 | $306.00 | $132.00 | $250.00 |
| 25 | Drilled shaft (36 in) (416-7006) | LF | 432 | $354.00 | $516.00 | $420.00 | $436.00 | $517.19 | $450.00 |
| 26 | Drilled shaft (42 in) (416-7007) | LF | 264 | $431.00 | $564.20 | $535.00 | $477.00 | $629.00 | $650.00 |
| 27 | Class C concrete (abutment)(HPC) (420-7013) | CY | 48.20 | $1,630.00 | $2,423.75 | $4,400.00 | $2,047.00 | $8,482.00 | $5,000.00 |
| 28 | Class C concrete (cap)(HPC) (420-7023) | CY | 58.50 | $1,505.00 | $2,246.40 | $3,600.00 | $1,900.00 | $7,242.00 | $5,000.00 |
| 29 | Class C concrete (column)(HPC) (420-7039) | CY | 19.20 | $1,724.63 | $2,246.40 | $2,600.00 | $1,900.00 | $3,217.00 | $5,000.00 |
| 30 | Reinforced concrete slab (HPC) (422-7002) | SF | 6,120 | $28.23 | $48.75 | $65.00 | $42.00 | $146.70 | $150.00 |
| 31 | Approach slab (HPC) (422-7014) | CY | 54.60 | $777.83 | $925.55 | $830.00 | $790.00 | $1,245.00 | $2,500.00 |
| 32 | Prestressed concrete girder (TX28) (425-7001) | LF | 1,011 | $298.24 | $230.45 | $623.00 | $195.00 | $449.45 | $300.00 |
| 33 | Riprap (mow strip)(4 in) (432-7013) | CY | 36 | $650.00 | $455.00 | $850.00 | $800.00 | $1,285.00 | $850.00 |
| 34 | Riprap (stone protection)(12 in) (432-7041) | CY | 15.50 | $225.00 | $325.00 | $202.00 | $1,200.00 | $438.00 | $500.00 |
| 35 | Riprap (stone protection)(18 in) (432-7043) | CY | 369 | $203.50 | $160.00 | $202.00 | $375.00 | $261.00 | $300.00 |
| 36 | Rail (type T223)(HPC) (450-7009) | LF | 372 | $170.00 | $172.80 | $240.00 | $146.00 | $263.00 | $300.00 |
| 37 | Header type expansion joint (454-7009) | CF | 71 | $500.00 | $940.30 | $360.00 | $327.00 | $400.00 | $350.00 |
| 38 | RC pipe (CL III)(24 in) (464-7005) | LF | 325 | $150.00 | $129.10 | $216.00 | $102.00 | $129.00 | $120.00 |
| 39 | RC pipe (CL III)(30 in) (464-7007) | LF | 58 | $210.00 | $182.10 | $235.00 | $135.00 | $140.00 | $160.00 |
| 40 | RC pipe (CL III)(36 in) (464-7009) | LF | 46 | $300.00 | $262.20 | $310.00 | $220.00 | $182.00 | $220.00 |
| 41 | RC pipe (CL III)(42 in) (464-7010) | LF | 46 | $325.00 | $273.40 | $360.00 | $315.00 | $214.00 | $250.00 |
| 42 | Set (type I) (36 in) (3: 1) (C) (467-7017) | EACH | 2 | $4,750.00 | $5,725.00 | $15,000 | $3,450.00 | $11,650 | $8,000.00 |
| 43 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 2 | $1,347.85 | $1,590.00 | $2,100.00 | $1,950.00 | $1,100.00 | $1,500.00 |
| 44 | Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325) | EACH | 2 | $2,500.00 | $1,100.00 | $2,300.00 | $2,255.00 | $1,360.00 | $1,600.00 |
| 45 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 10 | $2,500.00 | $1,990.00 | $2,500.00 | $2,315.00 | $1,430.00 | $1,700.00 |
| 46 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 4 | $2,376.37 | $2,300.00 | $2,500.00 | $2,458.00 | $1,300.00 | $2,200.00 |
| 47 | Set (type II) (30 in) (RCP) (3: 1) (C) (467-7345) | EACH | 1 | $4,000.00 | $2,400.00 | $3,100.00 | $3,653.00 | $1,800.00 | $2,000.00 |
| 48 | Set (type II) (30 in) (RCP) (4: 1) (C) (467-7346) | EACH | 1 | $4,200.00 | $2,650.00 | $3,100.00 | $3,789.00 | $1,800.00 | $2,400.00 |
| 49 | Set (type II) (42 in) (TP) (3: 1) (C) (467-7381) | EACH | 2 | $4,750.00 | $6,510.00 | $5,200.00 | $4,978.00 | $2,500.00 | $5,200.00 |
| 50 | Clean existing culverts (480-7001) | EACH | 2 | $2,500.00 | $2,000.00 | $3,000.00 | $2,750.00 | $4,100.00 | $1,500.00 |
| 51 | Diamond grinding slab (abc) (483-7019) | SY | 642 | $14.00 | $18.80 | $12.00 | $40.00 | $17.25 | $30.00 |
| 52 | Removing structure (set) (496-7004) | EACH | 18 | $1,000.00 | $792.00 | $400.00 | $650.00 | $500.00 | $750.00 |
| 53 | Removing structure (pipe) (496-7007) | LF | 401 | $50.00 | $177.00 | $35.00 | $25.00 | $34.00 | $20.00 |
| 54 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 1 | $75,000 | $49,825 | $55,000 | $255,000 | $53,400 | $147,000 |
| 55 | Mobilization (500-7001) | LS | 1 | $620,000 | $737,120 | $528,000 | $750,000 | $811,000 | $880,000 |
| 56 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $10,000 | $6,500.00 | $3,500.00 | $7,000.00 | $18,500 | $50,000 |
| 57 | Portable changeable message sign (503-7001) | DAY | 280 | $230.00 | $68.00 | $140.00 | $65.00 | $120.00 | $150.00 |
| 58 | Portable changeable message sign (503-7002) | EACH | 2 | $12,000 | $17,373 | $5,000.00 | $20,000 | $21,000 | $15,000 |
| 59 | TMA (stationary) (505-7001) | DAY | 174 | $250.00 | $248.10 | $280.00 | $210.00 | $500.00 | $375.00 |
| 60 | TMA (mobile operation) (505-7003) | DAY | 24 | $200.00 | $580.00 | $280.00 | $210.00 | $900.00 | $750.00 |
| 61 | Rock filter dams (install) (type 2) (506-7002) | LF | 580 | $40.00 | $43.60 | $36.00 | $36.00 | $56.45 | $40.00 |
| 62 | Rock filter dams (remove) (506-7011) | LF | 580 | $12.00 | $14.50 | $12.00 | $12.00 | $25.00 | $12.00 |
| 63 | Temporary sediment control fence (install) (506-7039) | LF | 3,940 | $4.41 | $4.25 | $3.50 | $3.50 | $6.40 | $5.00 |
| 64 | Temporary sediment control fence (remove) (506-7041) | LF | 3,940 | $1.22 | $1.20 | $1.00 | $1.00 | $1.50 | $1.00 |
| 65 | Driveways (ACP) (530-7010) | SY | 437 | $85.00 | $39.05 | $115.00 | $145.00 | $58.00 | $65.00 |
| 66 | Driveways (surface treat) (530-7016) | SY | 534 | $50.00 | $13.00 | $51.00 | $120.00 | $48.00 | $45.00 |
| 67 | Turnouts (surface treat) (530-7019) | SY | 16 | $77.00 | $73.65 | $51.00 | $500.00 | $180.00 | $45.00 |
| 68 | Metal W-beam guard fence (timber post) (540-7001) | LF | 250 | $27.50 | $29.05 | $25.00 | $31.00 | $26.70 | $40.00 |
| 69 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,450.00 | $2,408.00 | $2,800.00 | $2,020.00 | $3,120.00 | $2,500.00 |
| 70 | Remove metal beam guard fence (542-7001) | LF | 200 | $4.50 | $3.00 | $2.00 | $11.00 | $2.20 | $5.00 |
| 71 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,460.00 | $3,631.00 | $3,300.00 | $3,125.00 | $3,550.00 | $3,500.00 |
| 72 | Guardrail end treatment (remove) (544-7003) | EACH | 6 | $400.00 | $303.00 | $200.00 | $300.00 | $230.00 | $350.00 |
| 73 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 2 | $400.00 | $91.25 | $350.00 | $300.00 | $400.00 | $350.00 |
| 74 | Mailbox install-D (TWW-post) type 4 (560-7009) | EACH | 1 | $415.00 | $411.50 | $430.00 | $350.00 | $470.00 | $450.00 |
| 75 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 46 | $800.00 | $750.35 | $530.00 | $700.00 | $583.00 | $700.00 |
| 76 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 3 | $900.00 | $895.60 | $620.00 | $750.00 | $683.00 | $750.00 |
| 77 | Remove SM RD SN sup&AM (644-7073) | EACH | 40 | $120.00 | $109.00 | $100.00 | $100.00 | $100.00 | $150.00 |
| 78 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 6 | $40.00 | $27.00 | $25.00 | $28.00 | $28.00 | $40.00 |
| 79 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 12 | $40.13 | $29.00 | $35.00 | $32.00 | $39.00 | $45.00 |
| 80 | Install object marker assembly (OM-2Z)(WFLX)SRF (658-7060) | EACH | 18 | $120.00 | $91.00 | $150.00 | $90.00 | $160.00 | $150.00 |
| 81 | Remove delin & object marker assms (658-7078) | EACH | 20 | $55.00 | $22.00 | $25.00 | $15.00 | $28.00 | $30.00 |
| 82 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 40,706 | $0.35 | $0.50 | $0.25 | $0.32 | $0.28 | $0.35 |
| 83 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 4,450 | $0.70 | $0.50 | $0.33 | $0.34 | $0.37 | $0.40 |
| 84 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 11,944 | $0.35 | $0.50 | $0.33 | $0.32 | $0.37 | $0.40 |
| 85 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 4,070 | $0.80 | $1.00 | $1.50 | $1.00 | $2.00 | $1.50 |
| 86 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 40,706 | $0.35 | $0.50 | $0.33 | $0.34 | $0.37 | $0.40 |
| 87 | Reflectorized pavement marking type II (Y) 6" (broken) (666-7211) | LF | 4,450 | $0.50 | $0.50 | $0.33 | $0.36 | $0.37 | $0.40 |
| 88 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 11,944 | $0.35 | $0.40 | $0.33 | $0.34 | $0.37 | $0.40 |
| 89 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 40,706 | $2.77 | $0.90 | $0.65 | $0.66 | $0.72 | $0.90 |
| 90 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 4,450 | $2.43 | $0.95 | $0.65 | $0.68 | $0.72 | $0.75 |
| 91 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 11,944 | $2.43 | $0.95 | $0.65 | $0.66 | $0.72 | $0.75 |
| 92 | PRFB rumble strip (BLK)(1')(centerline) (668-7002) | LF | 4,071 | $4.21 | $5.75 | $4.40 | $4.50 | $4.90 | $6.00 |
| 93 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 33 | $30.00 | $18.15 | $25.00 | $33.00 | $28.00 | $35.00 |
| 94 | PRFB rumble strip (BLK)(1')(edgeline) (668-7137) | LF | 8,142 | $0.23 | $5.75 | $4.30 | $4.30 | $4.78 | $6.00 |
| 95 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 392 | $7.50 | $7.25 | $5.00 | $5.50 | $5.60 | $7.00 |
| 96 | Pavement surface preparation for marking (6") (678-7002) | LF | 800 | $0.10 | $1.20 | $1.20 | $1.00 | $1.30 | $1.50 |
| 97 | Ultra-high performance concrete (4024-7001) | CY | 16.80 | $10,000 | $10,660 | $1,850.00 | $9,000.00 | $3,500.00 | $5,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 4, 2025. Compiled by Mirage Metrics.