TxDOT contract A00188286 bid tabulation
Bridge Replacement, FRANTZ RD (AT SAN BERNARD RIVER to STR# AA52-06-001 (FRANTZ RD)). Let by Texas DOT on January 7, 2025, Austin, Yoakum District. 9 bids received; low bid $1,737,587 by STX Civil, -2.7% against the engineer's estimate of $1,785,608.
- Owner
- Texas DOT
- Letting
- 07 JAN 2025
- Pay items
- 48
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | STX Civil | $1,737,587 | Low | -3.0% |
| 2 | Fuqua Construction Co., Inc. | $1,841,526 | +6.0% | +3.0% |
| 3 | Trevway, Inc. | $1,852,147 | +7.0% | +4.0% |
| 4 | Aranda Brothers Construction Co., Inc. | $1,999,363 | +15% | +12% |
| 5 | MB Western Industrial Contracting Co. | $2,292,293 | +32% | +28% |
| 6 | C. E. Barker, LTD. | $2,373,110 | +37% | +33% |
| 7 | Knife River Corporation - South | $2,393,202 | +38% | +34% |
| 8 | R Construction Civil, LLC | $2,690,100 | +55% | +51% |
| 9 | Texas Materials Group, Inc. | $2,765,588 | +59% | +55% |
Engineer's estimate: $1,785,608.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. STX Civil | 2. Fuqua Construction Co., Inc. | 3. Trevway, Inc. | 4. Aranda Brothers Construction Co., Inc. | 5. MB Western Industrial Contracting Co. | 6. C. E. Barker, LTD. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 10.70 | $5,000.00 | $5,000.00 | $4,200.00 | $5,700.00 | $15,000 | $5,000.00 | $21,500 |
| 2 | Obliterating abandoned road (106-7002) | SY | 1,020 | $18.00 | $5.25 | $9.00 | $10.00 | $7.00 | $12.03 | |
| 3 | Excavation (roadway) (110-7001) | CY | 2,192 | $22.00 | $20.00 | $21.00 | $9.00 | $20.00 | $35.00 | $35.84 |
| 4 | Excavation (channel) (110-7002) | CY | 759 | $22.00 | $18.00 | $15.75 | $16.00 | $25.00 | $45.00 | $20.66 |
| 5 | Embankment (final)(OC)(type C) (132-7005) | CY | 488 | $27.00 | $20.00 | $22.05 | $29.65 | $15.00 | $60.00 | $20.65 |
| 6 | Blading (150-7002) | HR | 32 | $115.00 | $100.00 | $52.50 | $50.00 | $55.00 | $150.00 | $160.61 |
| 7 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 5,681 | $1.00 | $2.00 | $1.31 | $1.80 | $2.20 | $2.89 | $0.48 |
| 8 | Broadcast seed (temporary_warm) (164-7005) | SY | 1,420 | $1.00 | $2.00 | $1.05 | $0.50 | $2.20 | $2.89 | $0.90 |
| 9 | Broadcast seed (temporary_cool) (164-7006) | SY | 1,420 | $1.00 | $2.00 | $1.05 | $0.50 | $2.20 | $2.89 | $1.01 |
| 10 | Vegetative watering (168-7001) | TGL | 71.30 | $65.00 | $50.00 | $26.25 | $75.00 | $75.00 | $600.00 | $66.58 |
| 11 | FL BS (compacted in place)(type E GR 5)(final pos) (247-7196) | CY | 763 | $135.00 | $100.00 | $115.50 | $165.00 | $105.00 | $120.00 | $125.74 |
| 12 | Asphalt (RC-250) (316-7016) | GAL | 666 | $13.00 | $10.00 | $47.25 | $18.32 | $11.35 | $25.00 | $10.61 |
| 13 | Aggregate (type-E, GR-5)(sac-B) (316-7194) | CY | 24 | $600.00 | $150.00 | $1,575.00 | $1,271.40 | $95.00 | $590.00 | $212.15 |
| 14 | Aggregate (type-PE, GR-4)(sac-B) (316-7232) | CY | 26 | $600.00 | $150.00 | $1,575.00 | $1,242.90 | $100.00 | $315.00 | $212.15 |
| 15 | Asphalt (AC 20-5TR or AC-20XP or CRS-2P) (316-7264) | GAL | 1,133 | $12.00 | $8.50 | $46.20 | $17.12 | $10.00 | $15.00 | $10.61 |
| 16 | Cem stabil BKFL (400-7010) | CY | 48 | $210.00 | $190.00 | $207.90 | $200.00 | $120.00 | $200.00 | $112.25 |
| 17 | Drilled shaft (24 in) (416-7004) | LF | 1,197 | $260.00 | $410.00 | $231.47 | $289.00 | $400.00 | $468.00 | $320.23 |
| 18 | Class C concrete (abutment) (420-7012) | CY | 41.40 | $1,500.00 | $1,350.00 | $1,260.00 | $1,000.00 | $1,150.00 | $1,300.00 | $4,571.60 |
| 19 | Class C concrete (cap) (420-7022) | CY | 27 | $2,000.00 | $1,400.00 | $1,470.00 | $1,100.00 | $1,300.00 | $1,500.00 | $4,717.41 |
| 20 | Class C concrete (column) (420-7038) | CY | 8.70 | $2,000.00 | $2,100.00 | $1,605.45 | $2,000.00 | $1,250.00 | $1,500.00 | $7,440.58 |
| 21 | Reinforced concrete slab (slab beam) (422-7007) | SF | 5,460 | $30.00 | $22.00 | $26.25 | $18.00 | $15.00 | $35.00 | $32.50 |
| 22 | Prestressed concrete slab beam (5SB15) (425-7019) | LF | 1,034.92 | $240.00 | $245.00 | $259.35 | $264.00 | $320.00 | $298.00 | $254.74 |
| 23 | Riprap (stone protection)(18 in) (432-7043) | CY | 615 | $175.00 | $185.00 | $194.25 | $167.00 | $220.00 | $270.00 | $203.09 |
| 24 | Rail (type T223) (450-7008) | LF | 468 | $150.00 | $155.00 | $124.95 | $150.00 | $130.00 | $200.00 | $282.42 |
| 25 | Armor joint (sealed) (454-7003) | LF | 90 | $150.00 | $150.00 | $113.40 | $150.00 | $110.00 | $92.00 | $93.59 |
| 26 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 2 | $30,000 | $13,500 | $26,250 | $75,000 | $20,000 | $30,000 | $21,078 |
| 27 | Mobilization (500-7001) | LS | 1 | $157,000 | $113,000 | $230,190 | $200,000 | $190,000 | $150,000 | $213,660 |
| 28 | Barricades, signs and traffic handling (502-7001) | MO | 13 | $5,000.00 | $1,500.00 | $1,486.36 | $1,200.00 | $4,000.00 | $5,000.00 | $1,166.85 |
| 29 | TMA (stationary) (505-7001) | DAY | 20 | $200.00 | $400.61 | $300.00 | $500.00 | $250.00 | $203.32 | |
| 30 | TMA (mobile operation) (505-7003) | DAY | 8 | $130.00 | $296.76 | $300.00 | $700.00 | $250.00 | $912.25 | |
| 31 | Rock filter dams (install) (type 1) (506-7006) | CY | 5 | $75.00 | $40.00 | $525.00 | $200.00 | $100.00 | $50.00 | $397.79 |
| 32 | Sandbags for erosion control (506-7035) | EACH | 143 | $20.00 | $18.00 | $21.00 | $11.00 | $50.00 | $10.00 | $19.09 |
| 33 | Temporary sediment control fence (install) (506-7039) | LF | 945 | $5.00 | $5.00 | $4.04 | $5.00 | $5.00 | $7.00 | $5.14 |
| 34 | Temporary sediment control fence (remove) (506-7041) | LF | 945 | $2.00 | $2.00 | $1.05 | $1.00 | $1.00 | $3.00 | $1.59 |
| 35 | Metal W-beam guard fence (timber post) (540-7001) | LF | 50 | $30.00 | $36.75 | $134.69 | $40.00 | $49.00 | $37.13 | |
| 36 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,150.00 | $1,890.00 | $3,381.60 | $3,200.00 | $3,690.00 | $2,492.82 | |
| 37 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 4 | $2,300.00 | $2,000.00 | $1,365.00 | $2,859.90 | $4,650.00 | $2,800.00 | $1,644.20 |
| 38 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $3,200.00 | $3,750.00 | $3,307.50 | $3,635.30 | $3,100.00 | $4,900.00 | $3,447.51 |
| 39 | Wire fence (type A) (552-7001) | LF | 550 | $20.00 | $25.00 | $30.45 | $19.00 | $25.00 | $35.00 | $28.91 |
| 40 | Wire fence (type C) (552-7003) | LF | 733 | $22.00 | $25.00 | $28.88 | $16.00 | $20.00 | $25.00 | $28.91 |
| 41 | Wire fence (remove) (552-7011) | LF | 733 | $5.00 | $5.00 | $4.46 | $1.00 | $1.00 | $2.00 | $7.23 |
| 42 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 4 | $600.00 | $8,048.25 | $966.00 | $650.00 | $615.00 | $424.31 | |
| 43 | Relocate SM RD SN sup&AM(sign only) (644-7072) | EACH | 1 | $350.00 | $290.00 | $404.25 | $500.00 | $300.00 | $369.00 | $159.12 |
| 44 | Remove SM RD SN sup&AM (644-7073) | EACH | 1 | $128.00 | $100.00 | $131.25 | $100.00 | $250.00 | $184.00 | $159.12 |
| 45 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 10 | $40.00 | $45.00 | $21.00 | $6.32 | $100.00 | $37.00 | $37.13 |
| 46 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 18 | $40.00 | $50.00 | $26.25 | $13.00 | $100.00 | $67.00 | $42.43 |
| 47 | Amphibian/reptile exclusion fence inst (5003-7001) | LF | 4,553 | $3.50 | $5.00 | $4.46 | $4.29 | $5.00 | $4.00 | $3.66 |
| 48 | Amphibian/reptile exclusion fence rem (5003-7002) | LF | 4,553 | $3.50 | $1.00 | $1.31 | $1.00 | $1.00 | $1.00 | $1.59 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.