TxDOT contract A00188972 bid tabulation

Bridge Replacement, SH 35 (AT CARANCAHUA BAY to STR# 0179-09-062). Let by Texas DOT on December 2, 2025, Jackson, Yoakum District. 6 bids received; low bid $21,288,202 by Copasa Inc, +19% against the engineer's estimate of $17,962,824.

Owner
Texas DOT
Letting
02 DEC 2025
Pay items
76
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Copasa Inc$21,288,202Low+19%
2Ragle Construction, Inc.$23,746,417+12%+32%
3Hunter Industries, LTD.$26,862,178+26%+50%
4Orion Construction, LLC$27,298,998+28%+52%
5McMillen, Inc.$33,412,147+57%+86%
6Altus Construction LLC$34,823,498+64%+94%
TxDOT contract A00188972: bids by rank

Engineer's estimate: $17,962,824.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Copasa Inc2. Ragle Construction, Inc.3. Hunter Industries, LTD.4. Orion Construction, LLC5. McMillen, Inc.6. Altus Construction LLC
1Preparing row (100-7002)STA66.40$4,000.00$32,059$50,000$40,164$40,000$25,000$51,921
2Removing concrete (riprap) (104-7006)SY1,832$25.00$30.00$10.00$29.70$12.00$75.00$24.81
3Removing concrete (driveways) (104-7011)SY137$20.00$24.00$25.00$29.70$12.00$60.00$24.81
4Obliterating abandoned road (106-7002)SY11,045$15.00$8.94$6.80$12.10$1.90$9.00$47.33
5Excavation (roadway) (110-7001)CY21,426$18.00$12.91$18.00$27.50$11.00$15.00$30.49
6Embankment (final)(OC)(type C) (132-7005)CY17,402$23.00$14.21$85.00$33.00$8.00$40.00$50.51
7Blading (150-7002)HR28$120.00$500.00$130.00$132.00$550.00$220.00$126.99
8Broadcast seed (permanent_rural_clay) (164-7002)SY46,925$0.75$0.21$0.45$0.23$0.24$0.30$0.21
9Broadcast seed (temporary_warm) (164-7005)SY11,731$0.75$0.36$0.35$0.40$0.38$0.52$0.36
10Broadcast seed (temporary_cool) (164-7006)SY11,731$0.75$0.37$0.35$0.41$0.38$0.53$0.37
11Vegetative watering (168-7001)TGL396$50.00$47.68$30.00$25.30$48.00$68.68$48.05
12FL BS (compacted in place)(tye GR1-2)(final pos) (247-7193)CY3,404$125.00$132.09$135.00$106.42$135.00$149.51$57.08
13Lime (com or QK)(slurry) or QK(dry) (260-7001)TON292$330.00$360.00$360.00$346.50$375.00$565.43$361.73
14Lime TRT (existing material & new base)(8") (260-7011)SY16,231$4.00$8.00$3.90$2.91$3.25$6.81$12.29
15Asphalt (RC-250) (316-7016)GAL3,063$5.00$6.00$5.20$5.17$7.00$20.00$5.74
16Aggregate (type-E, GR-5)(sac-B) (316-7194)CY109$725.00$590.00$280.00$173.60$210.00$400.00$302.33
17Aggregate (type-PE, GR-4)(sac-B) (316-7232)CY181$725.00$350.00$280.00$174.24$140.00$400.00$256.98
18Asphalt (AC 20-5TR or AC-20XP or CRS-2P) (316-7264)GAL6,127$5.00$8.00$8.00$3.91$5.00$20.00$5.29
19D-GR HMA type-B PG64-22 (341-7001)TON2,426$115.00$130.00$195.00$119.90$220.00$250.00$149.06
20D-GR HMA type D PG70-22 (level-UP) (341-7051)TON81$150.00$158.00$245.00$145.20$325.00$350.00$100.52
21D-GR HMA type D sac-B PG76-22 (341-7058)TON2,865$120.00$160.00$225.00$132.00$250.00$250.00$141.72
22Tack coat (341-7082)GAL2,910$3.50$4.75$5.20$3.08$8.00$15.00$3.33
23Cem stabil BKFL (400-7010)CY252$215.00$198.00$175.00$200.00$400.00$300.00$169.57
24Temporary special shoring (403-7001)SF3,378$30.00$60.00$60.00$66.00$1.00$78.53$51.96
25Prestressed concrete pil (18 in SQ) (409-7002)LF176$200.00$199.01$150.00$350.00$280.00$600.00$276.55
26Prestressed concrete pil (24 in SQ) (409-7004)LF14,492$245.00$262.91$175.00$360.00$290.00$454.26$673.38
27Class B concrete (flume) (420-7010)CY11.60$1,100.00$1,996.82$715.00$900.00$1,750.00$1,000.00$342.77
28Class C concrete (abutment) (420-7012)CY56.80$1,600.00$1,639.92$1,200.00$3,000.00$2,250.00$2,500.00$11,120
29Class C concrete (cap) (420-7022)CY644.80$1,500.00$2,307.19$1,100.00$3,000.00$2,250.00$3,500.00$1,768.06
30Reinforced concrete slab (422-7001)SF117,760$20.00$23.75$24.00$36.00$33.00$48.00$52.91
31Approach slab (422-7013)CY70.60$875.00$1,086.50$625.00$1,000.00$1,050.00$1,000.00$3,024.27
32Prestressed concrete girder (TX34) (425-7002)LF15,264$205.00$175.15$192.00$247.00$353.50$325.00$188.82
33Riprap (stone protection)(18 in) (432-7043)CY1,988$120.00$200.00$225.00$320.00$235.00$225.00$277.96
34Rail (type SSTR) (450-7024)LF5,172$140.00$72.98$63.00$120.00$80.00$92.00$112.45
35Sealed expansion joint (4 in) (SEJ - M) (454-7004)LF516$250.00$237.50$205.00$250.00$400.00$265.23$172.33
36RC pipe (CL III)(18 in) (464-7003)LF310$125.00$90.00$80.00$74.71$125.00$183.34$453.48
37Set (type II) (18 in) (CMP) (6: 1) (P) (467-7304)EACH12$1,500.00$2,500.00$1,380.00$3,923.54$3,200.00$1,679.51$1,726.75
38Removing structure (bridge 1000 FT or greater) (496-7012)EACH1$1,500,000$1,733,054$1,100,000$600,000$2,000,000$300,000$1,201,829
39Removing structure (small) (496-7036)EACH7$1,600.00$1,101.53$620.00$1,710.70$2,400.00$1,460.62$1,267.41
40Mobilization (500-7001)LS1$1,620,000$2,128,742$2,300,000$2,670,089$2,700,000$3,348,000$3,464,961
41Barricades, signs and traffic handling (502-7001)MO22$9,000.00$15,416$104,000$27,855$20,000$50,000$12,093
42Portable changeable message sign (503-7002)EACH2$8,500.00$8,500.00$45,500$11,272$29,715$42,000$18,083
43TMA (stationary) (505-7001)DAY20$500.00$550.00$450.00$394.54$800.00$300.00$122.43
44TMA (mobile operation) (505-7003)DAY20$300.00$550.00$750.00$845.43$1,300.00$1,200.00$113.37
45Rock filter dams (install) (type 1) (506-7006)CY13$45.00$374.62$45.00$412.08$55.00$500.00$377.53
46Sandbags for erosion control (506-7035)EACH142$18.00$21.73$3.00$23.90$8.00$26.33$21.90
47Temporary sediment control fence (install) (506-7039)LF946$4.00$6.37$4.25$7.01$8.00$10.00$6.42
48Temporary sediment control fence (remove) (506-7041)LF946$1.50$1.17$2.50$1.29$2.60$1.00$1.18
49Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001)LF1,260$50.00$50.00$100.00$75.00$128.00$1,200.00$80.84
50Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049)LF1,260$18.00$20.00$15.00$50.00$32.00$20.00$20.62
51Driveways (concrete) (530-7006)SY137$140.00$120.00$115.00$200.00$119.00$197.59$285.08
52Driveways (surface treat) (530-7016)SY968$30.00$35.49$65.00$39.60$50.00$35.62$26.20
53Mill rumble strips (asphalt) (shoulder) (533-7001)LF8,080$0.30$1.00$0.50$0.59$0.33$0.93$0.66
54Mill rumble strips (asphalt) (centerline) (533-7002)LF4,040$0.30$1.00$0.92$0.79$0.45$1.53$0.81
55Metal W-beam guard fence (timber post) (540-7001)LF300$30.00$33.50$33.50$30.55$31.00$46.78$23.48
56Metal beam guard fence trans (thrie-beam) (540-7005)EACH6$2,500.00$1,944.00$1,944.00$2,825.89$2,250.00$3,118.89$1,889.56
57Remove metal beam guard fence (542-7001)LF474$3.00$4.25$4.25$5.50$10.00$3.12$10.08
58Guardrail end treatment (install) (544-7001)EACH4$3,400.00$3,343.00$3,343.00$3,814.78$3,510.00$6,000.00$2,967.86
59Guardrail end treatment (remove) (544-7003)EACH4$300.00$380.00$380.00$302.50$350.00$155.95$277.13
60Crash cushion attenuator (move & reset) (545-7002)EACH2$1,500.00$4,100.00$1,350.00$1,127.49$2,000.00$4,000.00$1,133.73
61Crash cushion attenuator (remove) (545-7004)EACH2$1,000.00$2,500.00$1,350.00$1,099.99$1,000.00$3,000.00$944.78
62Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH2$10,000$10,298$15,000$9,267.45$15,000$12,787$6,891.09
63Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH6$900.00$890.00$890.00$979.00$725.00$923.61$1,158.93
64Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007)EACH1$800.00$1,270.00$1,270.00$1,396.99$850.00$1,378.52$1,259.70
65Remove SM RD SN sup&AM (644-7073)EACH7$100.00$95.00$95.00$104.50$100.00$165.42$151.16
66Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH102$29.00$21.00$21.00$23.10$25.00$34.46$35.27
67Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH12$35.00$35.00$35.00$38.50$40.00$55.14$45.35
68Work zone pavement marking removing (W)6"(solid) (662-7068)LF7,350$1.50$0.85$0.85$0.46$0.44$0.58$0.42
69Work zone pavement marking removing (Y)6"(solid) (662-7100)LF6,990$1.50$0.85$0.85$0.46$0.44$0.58$0.42
70Work zone pavement marking SHT terminal (tab)type Y (662-7113)EACH350$2.00$1.25$1.00$1.83$7.15$3.10$1.36
71Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266)LF5,200$1.20$1.55$1.55$1.26$1.20$2.68$1.16
72Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270)LF5,200$1.00$1.55$1.55$1.26$1.20$2.68$1.16
73Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF8,805$0.50$0.91$0.91$1.08$1.05$1.35$0.99
74Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF1,755$0.50$0.95$0.95$2.20$2.15$2.76$2.02
75Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF7,050$0.50$0.91$0.91$1.08$1.05$1.35$0.99
76Pavement surface preparation for marking (6") (678-7002)LF10,400$0.04$0.20$0.20$0.11$0.11$1.00$0.10
TxDOT contract A00188972: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of December 2, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy