TxDOT contract A00189990 bid tabulation
Bridge Replacement, BETHEL CEMETERY RD (ON CR 444 (BETHEL CEMETERY RD, F-CR 231) to AT BEDIAS CREEK). Let by Texas DOT on September 3, 2026, Madison, Bryan District. 7 bids received; low bid $1,143,373 by Fuqua Construction Co., Inc., +9.9% against the engineer's estimate of $1,040,840.
- Owner
- Texas DOT
- Letting
- 03 SEP 2026
- Pay items
- 34
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Fuqua Construction Co., Inc. | $1,143,373 | Low | +10% |
| 2 | R Construction Civil, LLC | $1,146,635 | 0.0% | +10% |
| 3 | THK Construction LLC | $1,162,175 | +2.0% | +12% |
| 4 | Pmco Construction LLC | $1,165,655 | +2.0% | +12% |
| 5 | A. L. Helmcamp, Inc. | $1,227,070 | +7.0% | +18% |
| 6 | Knife River Corporation - South | $1,276,197 | +12% | +23% |
| 7 | Hodges and Son Construction Company, Inc. | $1,376,783 | +20% | +32% |
Engineer's estimate: $1,040,840.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Fuqua Construction Co., Inc. | 2. R Construction Civil, LLC | 3. THK Construction LLC | 4. Pmco Construction LLC | 5. A. L. Helmcamp, Inc. | 6. Knife River Corporation - South |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 7.10 | $1,500.00 | $8,288.27 | $1,850.00 | $1,500.00 | $2,000.00 | $6,000.00 | $7,900.00 |
| 2 | Preparation row (tree remove) (0"-12" diameter) (100-7003) | EACH | 2 | $500.00 | $620.94 | $3,000.00 | $500.00 | $500.00 | $1,000.00 | $400.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 77 | $29.00 | $13.46 | $41.00 | $18.00 | $20.00 | $40.00 | $8.00 |
| 4 | Excavation (channel) (110-7002) | CY | 645 | $29.00 | $14.41 | $41.00 | $18.00 | $20.00 | $50.00 | $17.45 |
| 5 | Embankment (final)(DC)(type C) (132-7006) | CY | 436 | $29.00 | $15.24 | $51.00 | $18.00 | $22.00 | $55.00 | $18.50 |
| 6 | Furn & place topsoil (4") (160-7002) | SY | 1,938 | $4.00 | $1.29 | $11.00 | $3.50 | $3.00 | $2.50 | $1.35 |
| 7 | Bond fiber MTRX seed (permanent)(rural)(sand) (164-7076) | SY | 954 | $0.74 | $0.76 | $2.54 | $1.35 | $2.63 | $1.83 | |
| 8 | Bond fiber MTRX seed (temporary)(warm) (164-7077) | SY | 969 | $1.25 | $0.68 | $0.70 | $2.39 | $1.35 | $2.63 | $1.83 |
| 9 | Bond fiber MTRX seed (temporary)(cool) (164-7078) | SY | 969 | $1.25 | $0.68 | $0.70 | $2.42 | $1.35 | $2.63 | $1.83 |
| 10 | Bond fiber MTRX seed (permanent)(rural)(clay) (164-7083) | SY | 984 | $2.00 | $0.74 | $0.76 | $2.50 | $1.35 | $2.63 | $1.83 |
| 11 | Vegetative watering (168-7001) | TGL | 38.80 | $40.00 | $38.50 | $40.00 | $1.00 | $1.00 | $5.00 | $48.00 |
| 12 | FL BS (compacted in place)(type A GR 1-2) (8") (247-7067) | SY | 1,587 | $25.00 | $33.54 | $28.00 | $40.00 | $30.00 | $35.00 | $26.46 |
| 13 | Cem stabil BKFL (400-7010) | CY | 156 | $190.00 | $77.00 | $130.00 | $300.00 | $250.00 | $225.00 | $150.30 |
| 14 | Drilled shaft (30 in) (416-7005) | LF | 540 | $250.00 | $302.52 | $290.00 | $237.52 | $260.00 | $235.00 | $286.90 |
| 15 | Class C concrete (abutment) (420-7012) | CY | 65.60 | $900.00 | $1,264.90 | $695.00 | $1,000.00 | $1,100.00 | $1,450.00 | $1,319.00 |
| 16 | Reinforced concrete slab (box beam) (422-7005) | SF | 3,926 | $22.00 | $21.44 | $20.00 | $29.00 | $24.00 | $38.00 | $34.65 |
| 17 | Prestressed concrete box beam (4B28) (425-7028) | LF | 595.74 | $330.00 | $280.68 | $280.00 | $293.21 | $350.00 | $265.00 | $347.40 |
| 18 | Prestressed concrete box beam (5B28) (425-7029) | LF | 297.88 | $330.00 | $299.53 | $293.00 | $323.83 | $360.00 | $265.00 | $388.90 |
| 19 | Riprap (stone protection)(18 in) (432-7043) | CY | 887 | $150.00 | $81.83 | $160.00 | $140.00 | $150.00 | $110.00 | $163.00 |
| 20 | Rail (type T223) (450-7008) | LF | 380 | $100.00 | $95.19 | $160.00 | $175.00 | $160.00 | $200.00 | $170.50 |
| 21 | Type A joint (454-7001) | LF | 112 | $50.00 | $25.83 | $104.00 | $20.00 | $45.00 | $115.00 | $71.00 |
| 22 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 2 | $10,000 | $29,700 | $37,000 | $45,000 | $10,000 | $8,000.00 | $13,650 |
| 23 | Mobilization (500-7001) | LS | 1 | $70,000 | $166,498 | $60,000 | $80,000 | $115,000 | $120,000 | $98,700 |
| 24 | Barricades, signs and traffic handling (502-7001) | MO | 7 | $2,500.00 | $1,579.92 | $6,950.00 | $1,632.52 | $3,000.00 | $5,000.00 | $2,970.00 |
| 25 | Rock filter dams (install) (type 2) (506-7002) | LF | 80 | $37.00 | $46.20 | $46.00 | $30.00 | $30.00 | $69.00 | $94.00 |
| 26 | Rock filter dams (remove) (506-7011) | LF | 80 | $11.00 | $22.00 | $22.00 | $1.00 | $1.00 | $21.00 | $5.50 |
| 27 | Construction perimeter fence (506-7034) | LF | 59 | $6.00 | $4.95 | $5.00 | $10.00 | $5.00 | $6.00 | $5.50 |
| 28 | Temporary sediment control fence (install) (506-7039) | LF | 1,471 | $4.00 | $4.40 | $4.40 | $3.50 | $4.00 | $4.20 | $6.00 |
| 29 | Temporary sediment control fence (remove) (506-7041) | LF | 1,471 | $1.00 | $1.38 | $1.35 | $1.00 | $1.00 | $1.05 | $1.45 |
| 30 | Metal W-beam guard fence (timber post) (540-7001) | LF | 37.50 | $30.00 | $39.00 | $30.00 | $26.78 | $30.00 | $28.00 | $30.00 |
| 31 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 8 | $1,250.00 | $1,727.00 | $1,150.00 | $1,233.75 | $1,350.50 | $1,075.00 | $1,139.00 |
| 32 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $3,500.00 | $3,459.50 | $3,500.00 | $3,583.13 | $3,550.00 | $3,255.00 | $3,445.00 |
| 33 | Install delineator assembly (D-SW)SZ 1(WFLX)GF2(BI) (658-7002) | EACH | 16 | $25.00 | $55.00 | $29.00 | $18.90 | $26.05 | $27.00 | $29.00 |
| 34 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 16 | $10.00 | $44.24 | $28.00 | $18.90 | $27.00 | $26.00 | $28.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 3, 2026. Compiled by Mirage Metrics.