TxDOT contract A00194720 bid tabulation
Intersection Improvement, SL 375 (1.0 MI N OF SERGEANT MAJOR to 1.0 MI S OF SERGEANT MAJOR). Let by Texas DOT on July 2, 2025, El Paso, El Paso District. 5 bids received; low bid $11,897,786 by Jordan Foster Construction, LLC, -30% against the engineer's estimate of $16,966,233.
- Owner
- Texas DOT
- Letting
- 02 JUL 2025
- Pay items
- 195
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Jordan Foster Construction, LLC | $11,897,786 | Low | -30% |
| 2 | International Eagle Enterprises, Inc. | $12,636,765 | +6.0% | -26% |
| 3 | Dan Williams Company | $12,749,191 | +7.0% | -25% |
| 4 | Spartan Construction of Texas, Inc. | $15,059,265 | +27% | -11% |
| 5 | C. E. Barker, LTD. | $16,639,051 | +40% | -2.0% |
Engineer's estimate: $16,966,233.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Jordan Foster Construction, LLC | 2. International Eagle Enterprises, Inc. | 3. Dan Williams Company | 4. Spartan Construction of Texas, Inc. | 5. C. E. Barker, LTD. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (pavement) (104-7001) | SY | 14,064 | $30.00 | $25.00 | $35.00 | $18.00 | $28.74 | $50.00 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 5,992 | $20.00 | $12.00 | $20.00 | $12.00 | $16.17 | $50.00 |
| 3 | Removing concrete (medians) (104-7008) | SY | 1,255 | $40.00 | $10.00 | $35.00 | $12.00 | $16.17 | $50.00 |
| 4 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 432 | $48.00 | $10.00 | $50.00 | $15.00 | $32.34 | $50.00 |
| 5 | Removing concrete (curb) (104-7016) | LF | 1,308 | $7.50 | $4.25 | $10.00 | $4.00 | $7.18 | $25.00 |
| 6 | Excavation (roadway) (110-7001) | CY | 3,474 | $20.00 | $16.00 | $18.00 | $25.00 | $35.93 | $18.39 |
| 7 | Excavation (special) (110-7003) | CY | 24 | $30.00 | $1,250.00 | $500.00 | $500.00 | $179.67 | $18.39 |
| 8 | Embankment (final)(DC)(type C) (132-7006) | CY | 7,644 | $45.00 | $20.00 | $18.00 | $31.00 | $35.93 | $31.27 |
| 9 | Backfill (type A or B) (134-7004) | STA | 107 | $250.00 | $700.00 | $400.00 | $650.00 | $359.34 | $1,287.51 |
| 10 | Rdside amenity (194-7011) | EACH | 2 | $100,000 | $70,000 | $90,000 | $75,000 | $6,611.85 | $5,923.18 |
| 11 | Proof rolling (216-7001) | HR | 12 | $200.00 | $80.00 | $80.00 | $83.00 | $179.67 | $128.75 |
| 12 | FL BS (compacted in place)(type A GR 1-2) (4") (247-7021) | SY | 4,355 | $45.00 | $10.00 | $13.00 | $11.50 | $15.57 | $14.74 |
| 13 | Cement (275-7001) | TON | 125 | $300.00 | $270.00 | $360.00 | $325.00 | $359.34 | $311.15 |
| 14 | Cement TRT (subgrade)(6") (275-7022) | SY | 23,939 | $10.00 | $7.00 | $3.25 | $3.00 | $3.59 | $6.44 |
| 15 | Prime coat (multi option) (310-7015) | GAL | 5,665 | $7.50 | $7.00 | $7.50 | $6.00 | $10.78 | $9.66 |
| 16 | D-GR HMA type-B PG64-22 (341-7001) | TON | 4,922 | $120.00 | $97.00 | $105.00 | $120.00 | $131.75 | $202.72 |
| 17 | D-GR HMA type D PG64-22 (341-7043) | TON | 481 | $150.00 | $108.00 | $200.00 | $175.00 | $143.73 | $213.98 |
| 18 | Concrete pavement (CRCP) (10") (360-7004) | SY | 2,504 | $160.00 | $89.00 | $85.00 | $110.00 | $113.79 | $114.80 |
| 19 | Concrete pavement (CRCP) (12") (360-7006) | SY | 19,840 | $180.00 | $108.00 | $95.00 | $120.00 | $119.78 | $118.02 |
| 20 | Struct excavation (400-7001) | CY | 63 | $20.00 | $7.00 | $200.00 | $1.00 | $53.90 | $42.92 |
| 21 | Cem stabil BKFL (400-7010) | CY | 618 | $225.00 | $165.00 | $120.00 | $225.00 | $200.41 | $189.91 |
| 22 | Flowable backfill (401-7001) | CY | 151 | $275.00 | $180.00 | $120.00 | $250.00 | $194.42 | $183.47 |
| 23 | Drilled shaft (18 in) (416-7002) | LF | 180 | $240.00 | $265.00 | $330.00 | $300.00 | $299.45 | $500.00 |
| 24 | Drilled shaft (36 in) (416-7006) | LF | 2,000 | $300.00 | $325.00 | $460.00 | $325.00 | $329.39 | $600.00 |
| 25 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 240 | $350.00 | $355.00 | $390.00 | $375.00 | $421.62 | $377.45 |
| 26 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 39 | $450.00 | $400.00 | $445.00 | $450.00 | $479.12 | $428.01 |
| 27 | Class C concrete (abutment)(HPC) (420-7013) | CY | 131 | $1,650.00 | $1,200.00 | $900.00 | $1,050.00 | $1,437.36 | $1,512.82 |
| 28 | Class C concrete (cap)(HPC) (420-7023) | CY | 115.60 | $1,600.00 | $1,260.00 | $1,500.00 | $1,700.00 | $1,976.37 | $1,512.82 |
| 29 | Class C concrete (column)(HPC) (420-7039) | CY | 104.80 | $1,600.00 | $1,300.00 | $1,200.00 | $1,000.00 | $1,557.14 | $1,512.82 |
| 30 | Class C concrete (rail foundation) (420-7052) | CY | 149 | $675.00 | $585.00 | $800.00 | $500.00 | $598.90 | $1,512.82 |
| 31 | Reinforced concrete slab (HPC) (422-7002) | SF | 28,761 | $30.00 | $24.00 | $26.00 | $34.00 | $33.53 | $34.41 |
| 32 | Approach slab (HPC) (422-7014) | CY | 324.70 | $700.00 | $410.00 | $700.00 | $600.00 | $718.68 | $869.07 |
| 33 | Prestressed concrete girder (TX34) (425-7002) | LF | 3,815.52 | $300.00 | $237.00 | $280.00 | $250.00 | $441.66 | $272.62 |
| 34 | Concrete paint finish (427-7002) | SF | 11,000 | $0.75 | $2.25 | $2.00 | $2.40 | $2.09 | $26.82 |
| 35 | Concrete structure repair (epoxy mortar) (429-7002) | SF | 50 | $342.00 | $190.00 | $300.00 | $225.00 | $323.21 | $321.88 |
| 36 | Riprap (concrete)(4 in) (432-7001) | CY | 579 | $600.00 | $455.00 | $380.00 | $525.00 | $778.57 | $577.59 |
| 37 | Riprap (concrete) (CL B) (4 in) (432-7007) | CY | 557 | $700.00 | $500.00 | $380.00 | $500.00 | $808.51 | $577.59 |
| 38 | Riprap (stone type R)(grout)(8 in) (432-7026) | CY | 244 | $230.00 | $360.00 | $580.00 | $200.00 | $359.34 | $81.14 |
| 39 | Cleaning and sealing existing joints (438-7001) | LF | 624 | $50.25 | $40.00 | $24.00 | $14.00 | $95.82 | $53.65 |
| 40 | Rail (type SSTR)(HPC) (450-7025) | LF | 544 | $70.00 | $120.00 | $90.00 | $75.00 | $89.83 | $211.08 |
| 41 | Rail (type T80PP-TS) (450-7053) | LF | 433 | $550.00 | $530.00 | $150.00 | $450.00 | $119.78 | $486.63 |
| 42 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 251 | $240.00 | $280.00 | $275.00 | $215.00 | $239.56 | $241.41 |
| 43 | RC pipe (CL III)(24 in) (464-7005) | LF | 159 | $110.00 | $170.00 | $170.00 | $250.00 | $131.75 | $134.12 |
| 44 | RC pipe (CL III)(30 in) (464-7007) | LF | 174 | $380.00 | $215.00 | $190.00 | $300.00 | $155.71 | $187.76 |
| 45 | Headwall (CH - PW - S) (diameter= 24 in) (466-7116) | EACH | 4 | $9,500.00 | $10,600 | $13,000 | $17,500 | $8,085.15 | $8,851.61 |
| 46 | Headwall (CH - PW - S) (diameter= 30 in) (466-7118) | EACH | 6 | $13,500 | $13,000 | $15,000 | $17,500 | $12,936 | $16,684 |
| 47 | Clean existing culverts (480-7001) | EACH | 14 | $10,432 | $4,000.00 | $4,000.00 | $1,275.00 | $2,395.60 | $2,145.85 |
| 48 | Removing structure (set) (496-7004) | EACH | 10 | $1,200.00 | $1,170.00 | $1,000.00 | $575.00 | $718.68 | $1,072.92 |
| 49 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 2 | $150,000 | $61,000 | $180,000 | $175,000 | $107,802 | $75,000 |
| 50 | Removing structure (approach slab) (496-7022) | EACH | 4 | $3,000.00 | $3,500.00 | $20,000 | $3,000.00 | $26,352 | $8,583.38 |
| 51 | Mobilization (500-7001) | LS | 1 | $1,600,000 | $916,000 | $850,000 | $1,000,000 | $1,087,688 | $1,500,000 |
| 52 | Barricades, signs and traffic handling (502-7001) | MO | 15 | $30,000 | $12,000 | $15,000 | $15,000 | $13,780 | $9,119.85 |
| 53 | Portable changeable message sign (503-7002) | EACH | 2 | $15,000 | $14,000 | $16,000 | $10,000 | $3,593.40 | $21,458 |
| 54 | TMA (stationary) (505-7001) | DAY | 22 | $275.00 | $300.00 | $150.00 | $200.00 | $479.12 | $1,072.92 |
| 55 | TMA (mobile operation) (505-7003) | DAY | 20 | $550.00 | $405.00 | $300.00 | $650.00 | $419.23 | $1,072.92 |
| 56 | Rock filter dams (install) (type 2) (506-7002) | LF | 3,584 | $60.00 | $40.00 | $25.00 | $1.00 | $17.96 | $59.01 |
| 57 | Rock filter dams (remove) (506-7011) | LF | 3,584 | $15.00 | $10.00 | $10.00 | $1.00 | $9.58 | $21.46 |
| 58 | Construction exits (install) (type 1) (506-7020) | SY | 312 | $35.00 | $25.00 | $35.00 | $32.00 | $35.93 | $59.01 |
| 59 | Construction exits (remove) (506-7024) | SY | 312 | $13.00 | $10.00 | $15.00 | $10.00 | $11.97 | $21.46 |
| 60 | Temporary sediment control fence (install) (506-7039) | LF | 9,267 | $5.50 | $5.00 | $4.50 | $8.00 | $3.89 | $6.44 |
| 61 | Temporary sediment control fence (remove) (506-7041) | LF | 9,267 | $1.50 | $3.00 | $1.00 | $5.00 | $0.95 | $1.88 |
| 62 | Constructing detours (508-7001) | SY | 492 | $70.00 | $100.00 | $120.00 | $125.00 | $167.69 | $95.00 |
| 63 | Portable concrete traffic barrier (des source)(F-shape)(type 1) (512-7017) | LF | 5,970 | $50.00 | $15.00 | $8.00 | $10.00 | $33.53 | $50.00 |
| 64 | Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029) | LF | 5,040 | $15.00 | $7.00 | $5.00 | $3.50 | $21.56 | $12.88 |
| 65 | Portable concrete traffic barrier (stockpile)(F-shape)(type 1) (512-7041) | LF | 5,970 | $22.00 | $8.00 | $8.00 | $7.00 | $23.95 | $18.24 |
| 66 | Permanent CTB(single slope)(type 1)(42)(HPC) (514-7018) | LF | 630 | $115.00 | $180.00 | $75.00 | $115.00 | $503.07 | $105.15 |
| 67 | Concrete curb (type II) (529-7002) | LF | 6,177 | $50.00 | $12.00 | $12.00 | $12.00 | $21.56 | $42.92 |
| 68 | Fixed bollard (531-7027) | EACH | 5 | $1,648.05 | $1,000.00 | $1,500.00 | $1,500.00 | $479.12 | $536.46 |
| 69 | Concrete median (536-7002) | SY | 453 | $150.00 | $70.00 | $50.00 | $60.00 | $167.69 | $193.13 |
| 70 | Metal W-beam guard fence (timber post) (540-7001) | LF | 3,050 | $35.00 | $30.00 | $36.00 | $30.00 | $37.13 | $33.26 |
| 71 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,750.00 | $3,000.00 | $2,200.00 | $2,400.00 | $3,892.85 | $3,487.00 |
| 72 | Transition adjustment (540-7012) | EACH | 6 | $2,000.00 | $200.00 | $2,000.00 | $1,400.00 | $1,347.52 | $1,207.04 |
| 73 | Downstream anchor terminal section (540-7015) | EACH | 6 | $1,500.00 | $2,000.00 | $2,500.00 | $1,750.00 | $2,156.04 | $1,877.62 |
| 74 | Remove metal beam guard fence (542-7001) | LF | 2,525 | $5.00 | $2.50 | $4.00 | $5.00 | $7.18 | $6.44 |
| 75 | Remove terminal anchor section (542-7002) | EACH | 3 | $1,000.00 | $225.00 | $800.00 | $350.00 | $718.68 | $643.75 |
| 76 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 4 | $350.00 | $225.00 | $500.00 | $350.00 | $718.68 | $643.75 |
| 77 | Cable barrier system (install)(TL-4) (543-7002) | LF | 602 | $20.00 | $90.00 | $40.00 | $28.00 | $53.90 | $48.28 |
| 78 | Cable barrier terminal sec (install)(TL-4) (543-7018) | EACH | 2 | $3,750.00 | $6,000.00 | $7,000.00 | $5,000.00 | $9,582.40 | $8,046.92 |
| 79 | Cable barrier (remove) (543-7037) | LF | 859 | $6.00 | $4.00 | $10.00 | $4.00 | $4.79 | $4.29 |
| 80 | Cable barrier terminal section (remove) (543-7038) | EACH | 2 | $900.00 | $450.00 | $600.00 | $400.00 | $1,557.14 | $1,072.92 |
| 81 | Guardrail end treatment (install) (544-7001) | EACH | 6 | $3,500.00 | $3,400.00 | $2,500.00 | $3,500.00 | $4,551.64 | $4,023.46 |
| 82 | Guardrail end treatment (remove) (544-7003) | EACH | 3 | $300.00 | $250.00 | $800.00 | $350.00 | $479.12 | $429.17 |
| 83 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 4 | $1,500.00 | $950.00 | $1,500.00 | $750.00 | $1,437.36 | $3,755.23 |
| 84 | Crash cushion attenuator (remove) (545-7004) | EACH | 4 | $1,200.00 | $950.00 | $800.00 | $700.00 | $1,497.25 | $1,341.15 |
| 85 | Crash cushion attenuator (install)(L)(N)(TL3) (545-7006) | EACH | 4 | $22,000 | $29,000 | $35,000 | $35,000 | $32,341 | $37,552 |
| 86 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 4 | $20,500 | $12,000 | $40,000 | $10,000 | $11,978 | $37,552 |
| 87 | Chain link fence (remove) (550-7007) | LF | 101 | $15.00 | $8.00 | $40.00 | $12.00 | $8.38 | $10.73 |
| 88 | Relocate RD IL asm (trans-base) (610-7004) | EACH | 16 | $3,300.00 | $3,102.00 | $3,400.00 | $3,105.00 | $3,715.57 | $3,327.80 |
| 89 | Relocate RD IL asm (U/P) (610-7005) | EACH | 6 | $1,300.00 | $1,207.00 | $1,340.00 | $1,210.00 | $1,445.74 | $1,294.40 |
| 90 | In RD IL (U/P) (type 1) (150W EQ) LED (610-7014) | EACH | 2 | $1,500.00 | $2,183.00 | $2,415.00 | $2,185.00 | $2,614.79 | $2,341.95 |
| 91 | In RD IL (type SA) 50T-4 (400W EQ) LED (610-7194) | EACH | 8 | $5,200.00 | $5,156.00 | $5,700.00 | $5,160.00 | $6,175.85 | $5,531.18 |
| 92 | Conduit (PVC) (schedule 40) (1") (bore) (618-7022) | LF | 320 | $27.00 | $24.00 | $25.00 | $23.50 | $28.74 | $24.78 |
| 93 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 6,630 | $30.00 | $21.00 | $22.00 | $20.00 | $23.95 | $21.42 |
| 94 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 370 | $28.00 | $29.00 | $31.00 | $28.50 | $35.93 | $30.22 |
| 95 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 355 | $31.00 | $30.00 | $31.00 | $29.00 | $35.93 | $30.62 |
| 96 | Conduit (PVC) (schedule 40) (4") (618-7040) | LF | 15 | $35.00 | $55.00 | $75.00 | $55.00 | $65.87 | $59.01 |
| 97 | Conduit (PVC) (schedule 40) (4") (bore) (618-7041) | LF | 405 | $42.00 | $37.00 | $40.00 | $37.00 | $47.91 | $39.49 |
| 98 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 415 | $37.00 | $31.00 | $33.00 | $31.00 | $37.13 | $32.85 |
| 99 | Conduit (RM) (1") (618-7072) | LF | 675 | $35.00 | $37.00 | $40.00 | $37.00 | $44.31 | $38.80 |
| 100 | Conduit (prepare) (618-7090) | LF | 3,680 | $5.50 | $4.00 | $5.00 | $3.95 | $4.79 | $4.21 |
| 101 | Electrical conductor (no.14) insulated (620-7002) | LF | 440 | $1.85 | $1.40 | $1.75 | $1.45 | $2.39 | $1.51 |
| 102 | Electrical conductor (no.12) insulated (620-7004) | LF | 400 | $2.30 | $1.85 | $2.00 | $1.85 | $2.69 | $1.98 |
| 103 | Electrical conductor (no.8) insulated (620-7008) | LF | 36,165 | $3.15 | $3.00 | $3.25 | $2.95 | $3.59 | $3.15 |
| 104 | Electrical conductor (no.6) insulated (620-7010) | LF | 2,850 | $3.15 | $3.40 | $3.75 | $3.40 | $4.79 | $3.64 |
| 105 | ITS GND box (poly) type 1 (243648)W/aprn (623-7018) | EACH | 3 | $4,000.00 | $3,640.00 | $4,025.00 | $3,635.00 | $4,354.00 | $3,900.08 |
| 106 | ITS GND box (poly) type 2 (366048)W/aprn (623-7024) | EACH | 1 | $6,500.00 | $6,100.00 | $6,745.00 | $6,100.00 | $7,306.58 | $6,536.25 |
| 107 | Ground box type A (122311)W/apron (624-7002) | EACH | 16 | $1,700.00 | $1,400.00 | $1,550.00 | $1,400.00 | $1,736.81 | $1,500.14 |
| 108 | Ground box type D (162922)W/apron (624-7008) | EACH | 3 | $2,000.00 | $1,800.00 | $870.00 | $1,800.00 | $2,156.04 | $1,912.53 |
| 109 | Remove ground box (624-7013) | EACH | 24 | $750.00 | $475.00 | $525.00 | $475.00 | $598.90 | $506.08 |
| 110 | Aluminum signs (type A) (636-7001) | SF | 91.25 | $40.00 | $32.00 | $37.00 | $32.00 | $47.91 | $33.45 |
| 111 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 9 | $1,100.00 | $1,025.00 | $1,225.00 | $1,025.00 | $1,257.69 | $1,098.86 |
| 112 | Install small roadside sign support and assembly type 10BWG(1)SB(T) (644-7012) | EACH | 2 | $800.00 | $1,080.00 | $1,300.00 | $1,080.00 | $1,317.58 | $1,156.11 |
| 113 | Install small roadside sign support and assembly type 10BWG(2)SA(P) (644-7017) | EACH | 2 | $1,200.00 | $1,650.00 | $2,395.00 | $1,645.00 | $2,036.26 | $1,761.85 |
| 114 | In bridge MNT clearance sign assembly(type N) (644-7061) | EACH | 2 | $5,000.00 | $2,950.00 | $3,665.00 | $2,945.00 | $3,593.40 | $3,155.68 |
| 115 | In bridge MNT clearance sign assembly(type S) (644-7062) | EACH | 2 | $3,800.00 | $2,950.00 | $3,665.00 | $2,945.00 | $3,593.40 | $3,155.68 |
| 116 | Install small roadside sign support and assembly (inst sign only) (644-7064) | EACH | 1 | $315.00 | $103.00 | $1,645.00 | $105.00 | $125.76 | $110.08 |
| 117 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 9 | $750.00 | $750.00 | $718.00 | $750.00 | $898.35 | $796.07 |
| 118 | Remove SM RD SN sup&AM (644-7073) | EACH | 18 | $230.00 | $120.00 | $180.00 | $120.00 | $143.73 | $127.06 |
| 119 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 52 | $45.00 | $50.00 | $22.00 | $75.00 | $65.87 | $56.33 |
| 120 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032) | EACH | 12 | $55.00 | $70.00 | $95.00 | $75.00 | $71.86 | $64.38 |
| 121 | Work zone pavement marking removing (reflectorized) type I-C (662-7049) | EACH | 897 | $1.20 | $8.00 | $11.40 | $6.85 | $8.20 | $7.35 |
| 122 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 2,452 | $1.20 | $8.00 | $11.00 | $6.85 | $8.14 | $7.35 |
| 123 | Work zone pavement marking removing (traffic BTN) type W (662-7057) | EACH | 597 | $1.20 | $7.00 | $9.50 | $6.00 | $7.18 | $6.44 |
| 124 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 13,226 | $2.50 | $2.75 | $3.75 | $2.45 | $2.89 | $2.60 |
| 125 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 11,740 | $1.00 | $2.00 | $2.75 | $1.75 | $2.09 | $1.88 |
| 126 | Reflectorized pavement marking type I (W)6"(DOT)(090MIL) (666-7008) | LF | 598 | $0.35 | $2.00 | $2.75 | $1.75 | $2.09 | $1.88 |
| 127 | Reflectorized pavement marking type I (W)6"(lane drop)(090MIL) (666-7011) | LF | 1,284 | $2.00 | $1.20 | $1.65 | $1.05 | $1.24 | $1.12 |
| 128 | Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023) | LF | 3,332 | $1.50 | $1.75 | $2.46 | $1.60 | $1.88 | $1.68 |
| 129 | Reflectorized pavement marking type I (W)12"(solid)(090MIL) (666-7029) | LF | 1,246 | $3.35 | $4.60 | $6.40 | $4.15 | $4.93 | $4.42 |
| 130 | Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035) | LF | 215 | $9.00 | $9.75 | $13.40 | $8.75 | $10.78 | $9.37 |
| 131 | Reflectorized pavement marking type I (W)(arrow)(090MIL) (666-7041) | EACH | 18 | $150.00 | $170.00 | $235.00 | $155.00 | $180.86 | $162.01 |
| 132 | Reflectorized pavement marking type I(W)(double arrow)(090MIL) (666-7044) | EACH | 6 | $200.00 | $245.00 | $335.00 | $220.00 | $263.51 | $232.82 |
| 133 | Reflectorized pavement marking type I(W)(lane drop arrow)(090MIL) (666-7059) | EACH | 6 | $380.00 | $380.00 | $535.00 | $340.00 | $407.25 | $363.72 |
| 134 | Reflectorized pavement marking type I (W)(word)(090MIL) (666-7065) | EACH | 18 | $165.00 | $170.00 | $235.00 | $155.00 | $182.06 | $163.08 |
| 135 | Reflectorized pavement marking type I (W)(bike arrow)(090MIL) (666-7092) | EACH | 8 | $175.00 | $160.00 | $220.00 | $145.00 | $173.68 | $154.50 |
| 136 | Reflectorized pavement marking type I(W)(bike syml)(090MIL) (666-7098) | EACH | 8 | $215.00 | $207.00 | $290.00 | $185.00 | $221.59 | $198.49 |
| 137 | Reflectorized pavement marking type II (W) 6" (broken) (666-7172) | LF | 3,253 | $0.50 | $0.60 | $0.86 | $0.55 | $0.65 | $0.59 |
| 138 | Reflectorized pavement marking type II (W) 6" (DOT) (666-7173) | LF | 598 | $1.40 | $1.25 | $1.70 | $1.10 | $1.31 | $1.17 |
| 139 | Reflectorized pavement marking type II (W) 6" (lane drop) (666-7174) | LF | 1,284 | $1.90 | $0.75 | $1.00 | $0.65 | $0.74 | $0.67 |
| 140 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 18,716 | $0.50 | $0.30 | $0.40 | $0.25 | $0.29 | $0.27 |
| 141 | Reflectorized pavement marking type II (W) 8" (solid) (666-7179) | LF | 3,332 | $0.75 | $0.90 | $1.25 | $0.80 | $0.95 | $0.85 |
| 142 | Reflectorized pavement marking type II (W) 12" (solid) (666-7182) | LF | 1,246 | $2.00 | $3.75 | $5.00 | $3.20 | $3.83 | $3.43 |
| 143 | Reflectorized pavement marking type II (W) 24" (solid) (666-7184) | LF | 215 | $5.00 | $6.20 | $8.65 | $5.50 | $6.58 | $5.86 |
| 144 | Reflectorized pavement marking type II (W) (arrow) (666-7186) | EACH | 18 | $120.00 | $255.00 | $355.00 | $230.00 | $275.49 | $244.63 |
| 145 | Reflectorized pavement marking type II (W) (double arrow) (666-7187) | EACH | 6 | $130.00 | $150.79 | $220.00 | $135.00 | $161.70 | $141.63 |
| 146 | Reflectorized pavement marking type II (W) (LN reduct arrow) (666-7192) | EACH | 6 | $185.00 | $180.00 | $260.00 | $160.00 | $191.64 | $169.52 |
| 147 | Reflectorized pavement marking type II (W) (word) (666-7194) | EACH | 18 | $130.00 | $105.00 | $145.00 | $95.00 | $119.78 | $100.85 |
| 148 | Reflectorized pavement marking type II (W) (bike arrow) (666-7203) | EACH | 7 | $80.00 | $95.00 | $130.00 | $81.00 | $119.78 | $86.91 |
| 149 | Reflectorized pavement marking type II (W) (bike symbol) (666-7205) | EACH | 7 | $85.00 | $80.00 | $110.00 | $71.00 | $119.78 | $76.18 |
| 150 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 17,095 | $0.60 | $0.30 | $0.40 | $0.30 | $0.33 | $0.28 |
| 151 | Reflectorized pavement marking type I (W)6"(broken)(090MIL) (666-7407) | LF | 3,253 | $1.00 | $1.75 | $2.50 | $1.60 | $1.91 | $1.68 |
| 152 | Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410) | LF | 18,716 | $1.00 | $1.05 | $1.50 | $0.95 | $1.13 | $1.01 |
| 153 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 17,095 | $1.00 | $1.00 | $1.50 | $0.90 | $1.07 | $0.97 |
| 154 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 6 | $6.00 | $10.00 | $18.45 | $8.95 | $10.78 | $9.58 |
| 155 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 488 | $6.00 | $10.00 | $14.00 | $8.95 | $10.78 | $9.57 |
| 156 | Eliminating existing PM & markers (4") (677-7001) | LF | 10,134 | $0.75 | $0.70 | $1.00 | $0.65 | $0.74 | $0.65 |
| 157 | Eliminating existing PM & markers (12") (677-7006) | LF | 1,039 | $1.75 | $3.50 | $4.60 | $3.05 | $3.65 | $3.25 |
| 158 | Eliminating existing PM & markers (24") (677-7008) | LF | 224 | $3.00 | $8.50 | $11.45 | $7.45 | $8.98 | $7.97 |
| 159 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 8 | $130.00 | $190.00 | $320.00 | $167.00 | $203.62 | $179.18 |
| 160 | Eliminating existing PM & markers (double arrow) (677-7010) | EACH | 4 | $110.00 | $240.00 | $332.00 | $208.00 | $251.53 | $223.17 |
| 161 | Eliminating existing PM & markers (word) (677-7015) | EACH | 8 | $145.00 | $220.00 | $304.00 | $191.00 | $228.78 | $204.93 |
| 162 | Eliminating existing PM & markers (symbol) (677-7020) | EACH | 4 | $80.00 | $170.00 | $275.00 | $149.00 | $179.67 | $159.87 |
| 163 | Eliminating existing PM & marks (bike arrow) (677-7025) | EACH | 4 | $50.00 | $200.00 | $332.00 | $175.00 | $215.60 | $187.76 |
| 164 | Eliminating existing PM & marks (bike symbol) (677-7027) | EACH | 4 | $70.00 | $200.00 | $332.00 | $175.00 | $215.60 | $187.76 |
| 165 | Pavement surface preparation for marking (6") (678-7002) | LF | 40,946 | $0.50 | $0.55 | $0.75 | $0.50 | $0.59 | $0.52 |
| 166 | Pavement surface preparation for marking (8") (678-7004) | LF | 3,332 | $0.30 | $0.65 | $0.90 | $0.60 | $0.67 | $0.60 |
| 167 | Pavement surface preparation for marking (12") (678-7006) | LF | 1,246 | $0.50 | $0.75 | $1.45 | $0.70 | $0.83 | $0.72 |
| 168 | Pavement surface preparation for marking (24") (678-7008) | LF | 215 | $3.00 | $0.95 | $2.00 | $0.85 | $1.01 | $0.89 |
| 169 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 24 | $27.00 | $60.00 | $83.00 | $51.00 | $61.08 | $54.72 |
| 170 | Pavement surface preparation for marking (double arrow) (678-7010) | EACH | 6 | $32.00 | $170.00 | $295.00 | $150.00 | $179.67 | $158.79 |
| 171 | Pavement surface preparation for marking (word) (678-7016) | EACH | 18 | $32.00 | $185.00 | $260.00 | $166.00 | $198.83 | $178.11 |
| 172 | Pavement surface preparation for marking (bike arrow) (678-7026) | EACH | 7 | $32.00 | $158.00 | $316.00 | $141.00 | $173.68 | $151.28 |
| 173 | Pavement surface preparation for marking (bike symbol) (678-7028) | EACH | 7 | $40.00 | $100.00 | $190.00 | $88.50 | $107.08 | $94.95 |
| 174 | Removing traffic signals (680-7004) | EACH | 1 | $15,000 | $10,700 | $11,750 | $15,000 | $12,816 | $11,392 |
| 175 | Install highway traffic signal (upgrade) (680-7011) | EACH | 1 | $38,000 | $10,300 | $11,400 | $15,000 | $12,337 | $11,041 |
| 176 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 5 | $450.00 | $330.00 | $375.00 | $330.00 | $395.27 | $352.78 |
| 177 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 6 | $445.00 | $330.00 | $370.00 | $330.00 | $395.27 | $352.78 |
| 178 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 9 | $435.00 | $330.00 | $370.00 | $330.00 | $395.27 | $352.78 |
| 179 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 2 | $425.00 | $330.00 | $390.00 | $330.00 | $395.27 | $352.78 |
| 180 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 9 | $435.00 | $330.00 | $370.00 | $330.00 | $395.27 | $352.78 |
| 181 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 1 | $430.00 | $330.00 | $445.00 | $330.00 | $395.27 | $352.78 |
| 182 | Backplate W/reflectorized border(3 sec)aluminum (682-7039) | EACH | 9 | $330.00 | $165.00 | $180.00 | $165.00 | $203.62 | $172.90 |
| 183 | Backplate W/reflectorized border(5 sec)aluminum (682-7041) | EACH | 1 | $330.00 | $215.00 | $330.00 | $215.00 | $263.51 | $226.06 |
| 184 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 410 | $6.75 | $3.00 | $3.15 | $2.85 | $3.59 | $3.06 |
| 185 | Traffic signal CBL (type A)(14 AWG)(20 conductor) (684-7046) | LF | 1,260 | $8.00 | $9.50 | $10.45 | $9.50 | $11.97 | $10.10 |
| 186 | Ins traffic signal PL AM(S)1 arm(36')lum (686-7039) | EACH | 2 | $16,000 | $14,000 | $15,300 | $15,000 | $16,769 | $14,824 |
| 187 | Ins traffic signal PL AM(S)1 arm(44')lum (686-7047) | EACH | 1 | $17,000 | $16,000 | $17,000 | $17,500 | $18,566 | $16,482 |
| 188 | CNC crack repair (discrete)(inject) (780-7002) | LF | 83 | $123.00 | $140.00 | $25.00 | $50.00 | $143.73 | $160.94 |
| 189 | Relocate RVDS (6008-7007) | EACH | 3 | $2,000.00 | $1,270.00 | $1,400.00 | $1,275.00 | $1,796.70 | $1,352.96 |
| 190 | Radar presence detector comm cable (6008-7009) | LF | 1,350 | $3.75 | $4.00 | $4.50 | $3.95 | $4.79 | $4.24 |
| 191 | Ground box (prepare) (6013-7006) | EACH | 9 | $600.00 | $525.00 | $580.00 | $525.00 | $1,197.80 | $563.28 |
| 192 | Fiber optic fusion splice (6027-7004) | EACH | 108 | $140.00 | $115.00 | $125.00 | $115.00 | $149.72 | $120.61 |
| 193 | FO splice enclosure (type 1) (6027-7009) | EACH | 1 | $2,700.00 | $2,500.00 | $2,745.00 | $2,500.00 | $2,994.50 | $2,660.85 |
| 194 | FO CBL (12 SMF) (6027-7028) | LF | 440 | $11.00 | $8.00 | $8.35 | $7.55 | $11.97 | $8.09 |
| 195 | Remove existing cables (power) (6106-7002) | LF | 605 | $1.30 | $19.00 | $20.70 | $18.75 | $23.95 | $19.97 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 2, 2025. Compiled by Mirage Metrics.