TxDOT contract A00194720 bid tabulation

Intersection Improvement, SL 375 (1.0 MI N OF SERGEANT MAJOR to 1.0 MI S OF SERGEANT MAJOR). Let by Texas DOT on July 2, 2025, El Paso, El Paso District. 5 bids received; low bid $11,897,786 by Jordan Foster Construction, LLC, -30% against the engineer's estimate of $16,966,233.

Owner
Texas DOT
Letting
02 JUL 2025
Pay items
195
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Jordan Foster Construction, LLC$11,897,786Low-30%
2International Eagle Enterprises, Inc.$12,636,765+6.0%-26%
3Dan Williams Company$12,749,191+7.0%-25%
4Spartan Construction of Texas, Inc.$15,059,265+27%-11%
5C. E. Barker, LTD.$16,639,051+40%-2.0%
TxDOT contract A00194720: bids by rank

Engineer's estimate: $16,966,233.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Jordan Foster Construction, LLC2. International Eagle Enterprises, Inc.3. Dan Williams Company4. Spartan Construction of Texas, Inc.5. C. E. Barker, LTD.
1Removing concrete (pavement) (104-7001)SY14,064$30.00$25.00$35.00$18.00$28.74$50.00
2Removing concrete (riprap) (104-7006)SY5,992$20.00$12.00$20.00$12.00$16.17$50.00
3Removing concrete (medians) (104-7008)SY1,255$40.00$10.00$35.00$12.00$16.17$50.00
4Removing concrete (sidewalk, ramp or shared use path) (104-7013)SY432$48.00$10.00$50.00$15.00$32.34$50.00
5Removing concrete (curb) (104-7016)LF1,308$7.50$4.25$10.00$4.00$7.18$25.00
6Excavation (roadway) (110-7001)CY3,474$20.00$16.00$18.00$25.00$35.93$18.39
7Excavation (special) (110-7003)CY24$30.00$1,250.00$500.00$500.00$179.67$18.39
8Embankment (final)(DC)(type C) (132-7006)CY7,644$45.00$20.00$18.00$31.00$35.93$31.27
9Backfill (type A or B) (134-7004)STA107$250.00$700.00$400.00$650.00$359.34$1,287.51
10Rdside amenity (194-7011)EACH2$100,000$70,000$90,000$75,000$6,611.85$5,923.18
11Proof rolling (216-7001)HR12$200.00$80.00$80.00$83.00$179.67$128.75
12FL BS (compacted in place)(type A GR 1-2) (4") (247-7021)SY4,355$45.00$10.00$13.00$11.50$15.57$14.74
13Cement (275-7001)TON125$300.00$270.00$360.00$325.00$359.34$311.15
14Cement TRT (subgrade)(6") (275-7022)SY23,939$10.00$7.00$3.25$3.00$3.59$6.44
15Prime coat (multi option) (310-7015)GAL5,665$7.50$7.00$7.50$6.00$10.78$9.66
16D-GR HMA type-B PG64-22 (341-7001)TON4,922$120.00$97.00$105.00$120.00$131.75$202.72
17D-GR HMA type D PG64-22 (341-7043)TON481$150.00$108.00$200.00$175.00$143.73$213.98
18Concrete pavement (CRCP) (10") (360-7004)SY2,504$160.00$89.00$85.00$110.00$113.79$114.80
19Concrete pavement (CRCP) (12") (360-7006)SY19,840$180.00$108.00$95.00$120.00$119.78$118.02
20Struct excavation (400-7001)CY63$20.00$7.00$200.00$1.00$53.90$42.92
21Cem stabil BKFL (400-7010)CY618$225.00$165.00$120.00$225.00$200.41$189.91
22Flowable backfill (401-7001)CY151$275.00$180.00$120.00$250.00$194.42$183.47
23Drilled shaft (18 in) (416-7002)LF180$240.00$265.00$330.00$300.00$299.45$500.00
24Drilled shaft (36 in) (416-7006)LF2,000$300.00$325.00$460.00$325.00$329.39$600.00
25Drilled shaft (roadway illumination pole) (30 in) (416-7040)LF240$350.00$355.00$390.00$375.00$421.62$377.45
26Drilled shaft (traffic signal pole) (36 in) (416-7044)LF39$450.00$400.00$445.00$450.00$479.12$428.01
27Class C concrete (abutment)(HPC) (420-7013)CY131$1,650.00$1,200.00$900.00$1,050.00$1,437.36$1,512.82
28Class C concrete (cap)(HPC) (420-7023)CY115.60$1,600.00$1,260.00$1,500.00$1,700.00$1,976.37$1,512.82
29Class C concrete (column)(HPC) (420-7039)CY104.80$1,600.00$1,300.00$1,200.00$1,000.00$1,557.14$1,512.82
30Class C concrete (rail foundation) (420-7052)CY149$675.00$585.00$800.00$500.00$598.90$1,512.82
31Reinforced concrete slab (HPC) (422-7002)SF28,761$30.00$24.00$26.00$34.00$33.53$34.41
32Approach slab (HPC) (422-7014)CY324.70$700.00$410.00$700.00$600.00$718.68$869.07
33Prestressed concrete girder (TX34) (425-7002)LF3,815.52$300.00$237.00$280.00$250.00$441.66$272.62
34Concrete paint finish (427-7002)SF11,000$0.75$2.25$2.00$2.40$2.09$26.82
35Concrete structure repair (epoxy mortar) (429-7002)SF50$342.00$190.00$300.00$225.00$323.21$321.88
36Riprap (concrete)(4 in) (432-7001)CY579$600.00$455.00$380.00$525.00$778.57$577.59
37Riprap (concrete) (CL B) (4 in) (432-7007)CY557$700.00$500.00$380.00$500.00$808.51$577.59
38Riprap (stone type R)(grout)(8 in) (432-7026)CY244$230.00$360.00$580.00$200.00$359.34$81.14
39Cleaning and sealing existing joints (438-7001)LF624$50.25$40.00$24.00$14.00$95.82$53.65
40Rail (type SSTR)(HPC) (450-7025)LF544$70.00$120.00$90.00$75.00$89.83$211.08
41Rail (type T80PP-TS) (450-7053)LF433$550.00$530.00$150.00$450.00$119.78$486.63
42Sealed expansion joint (4 in) (SEJ - M) (454-7004)LF251$240.00$280.00$275.00$215.00$239.56$241.41
43RC pipe (CL III)(24 in) (464-7005)LF159$110.00$170.00$170.00$250.00$131.75$134.12
44RC pipe (CL III)(30 in) (464-7007)LF174$380.00$215.00$190.00$300.00$155.71$187.76
45Headwall (CH - PW - S) (diameter= 24 in) (466-7116)EACH4$9,500.00$10,600$13,000$17,500$8,085.15$8,851.61
46Headwall (CH - PW - S) (diameter= 30 in) (466-7118)EACH6$13,500$13,000$15,000$17,500$12,936$16,684
47Clean existing culverts (480-7001)EACH14$10,432$4,000.00$4,000.00$1,275.00$2,395.60$2,145.85
48Removing structure (set) (496-7004)EACH10$1,200.00$1,170.00$1,000.00$575.00$718.68$1,072.92
49Removing structure (bridge 100 - 499 FT length) (496-7010)EACH2$150,000$61,000$180,000$175,000$107,802$75,000
50Removing structure (approach slab) (496-7022)EACH4$3,000.00$3,500.00$20,000$3,000.00$26,352$8,583.38
51Mobilization (500-7001)LS1$1,600,000$916,000$850,000$1,000,000$1,087,688$1,500,000
52Barricades, signs and traffic handling (502-7001)MO15$30,000$12,000$15,000$15,000$13,780$9,119.85
53Portable changeable message sign (503-7002)EACH2$15,000$14,000$16,000$10,000$3,593.40$21,458
54TMA (stationary) (505-7001)DAY22$275.00$300.00$150.00$200.00$479.12$1,072.92
55TMA (mobile operation) (505-7003)DAY20$550.00$405.00$300.00$650.00$419.23$1,072.92
56Rock filter dams (install) (type 2) (506-7002)LF3,584$60.00$40.00$25.00$1.00$17.96$59.01
57Rock filter dams (remove) (506-7011)LF3,584$15.00$10.00$10.00$1.00$9.58$21.46
58Construction exits (install) (type 1) (506-7020)SY312$35.00$25.00$35.00$32.00$35.93$59.01
59Construction exits (remove) (506-7024)SY312$13.00$10.00$15.00$10.00$11.97$21.46
60Temporary sediment control fence (install) (506-7039)LF9,267$5.50$5.00$4.50$8.00$3.89$6.44
61Temporary sediment control fence (remove) (506-7041)LF9,267$1.50$3.00$1.00$5.00$0.95$1.88
62Constructing detours (508-7001)SY492$70.00$100.00$120.00$125.00$167.69$95.00
63Portable concrete traffic barrier (des source)(F-shape)(type 1) (512-7017)LF5,970$50.00$15.00$8.00$10.00$33.53$50.00
64Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029)LF5,040$15.00$7.00$5.00$3.50$21.56$12.88
65Portable concrete traffic barrier (stockpile)(F-shape)(type 1) (512-7041)LF5,970$22.00$8.00$8.00$7.00$23.95$18.24
66Permanent CTB(single slope)(type 1)(42)(HPC) (514-7018)LF630$115.00$180.00$75.00$115.00$503.07$105.15
67Concrete curb (type II) (529-7002)LF6,177$50.00$12.00$12.00$12.00$21.56$42.92
68Fixed bollard (531-7027)EACH5$1,648.05$1,000.00$1,500.00$1,500.00$479.12$536.46
69Concrete median (536-7002)SY453$150.00$70.00$50.00$60.00$167.69$193.13
70Metal W-beam guard fence (timber post) (540-7001)LF3,050$35.00$30.00$36.00$30.00$37.13$33.26
71Metal beam guard fence trans (thrie-beam) (540-7005)EACH4$2,750.00$3,000.00$2,200.00$2,400.00$3,892.85$3,487.00
72Transition adjustment (540-7012)EACH6$2,000.00$200.00$2,000.00$1,400.00$1,347.52$1,207.04
73Downstream anchor terminal section (540-7015)EACH6$1,500.00$2,000.00$2,500.00$1,750.00$2,156.04$1,877.62
74Remove metal beam guard fence (542-7001)LF2,525$5.00$2.50$4.00$5.00$7.18$6.44
75Remove terminal anchor section (542-7002)EACH3$1,000.00$225.00$800.00$350.00$718.68$643.75
76RM metal beam guard fence trans (thrie-beam) (542-7004)EACH4$350.00$225.00$500.00$350.00$718.68$643.75
77Cable barrier system (install)(TL-4) (543-7002)LF602$20.00$90.00$40.00$28.00$53.90$48.28
78Cable barrier terminal sec (install)(TL-4) (543-7018)EACH2$3,750.00$6,000.00$7,000.00$5,000.00$9,582.40$8,046.92
79Cable barrier (remove) (543-7037)LF859$6.00$4.00$10.00$4.00$4.79$4.29
80Cable barrier terminal section (remove) (543-7038)EACH2$900.00$450.00$600.00$400.00$1,557.14$1,072.92
81Guardrail end treatment (install) (544-7001)EACH6$3,500.00$3,400.00$2,500.00$3,500.00$4,551.64$4,023.46
82Guardrail end treatment (remove) (544-7003)EACH3$300.00$250.00$800.00$350.00$479.12$429.17
83Crash cushion attenuator (move & reset) (545-7002)EACH4$1,500.00$950.00$1,500.00$750.00$1,437.36$3,755.23
84Crash cushion attenuator (remove) (545-7004)EACH4$1,200.00$950.00$800.00$700.00$1,497.25$1,341.15
85Crash cushion attenuator (install)(L)(N)(TL3) (545-7006)EACH4$22,000$29,000$35,000$35,000$32,341$37,552
86Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH4$20,500$12,000$40,000$10,000$11,978$37,552
87Chain link fence (remove) (550-7007)LF101$15.00$8.00$40.00$12.00$8.38$10.73
88Relocate RD IL asm (trans-base) (610-7004)EACH16$3,300.00$3,102.00$3,400.00$3,105.00$3,715.57$3,327.80
89Relocate RD IL asm (U/P) (610-7005)EACH6$1,300.00$1,207.00$1,340.00$1,210.00$1,445.74$1,294.40
90In RD IL (U/P) (type 1) (150W EQ) LED (610-7014)EACH2$1,500.00$2,183.00$2,415.00$2,185.00$2,614.79$2,341.95
91In RD IL (type SA) 50T-4 (400W EQ) LED (610-7194)EACH8$5,200.00$5,156.00$5,700.00$5,160.00$6,175.85$5,531.18
92Conduit (PVC) (schedule 40) (1") (bore) (618-7022)LF320$27.00$24.00$25.00$23.50$28.74$24.78
93Conduit (PVC) (schedule 40) (2") (618-7030)LF6,630$30.00$21.00$22.00$20.00$23.95$21.42
94Conduit (PVC) (schedule 40) (2") (bore) (618-7031)LF370$28.00$29.00$31.00$28.50$35.93$30.22
95Conduit (PVC) (schedule 40) (3") (618-7036)LF355$31.00$30.00$31.00$29.00$35.93$30.62
96Conduit (PVC) (schedule 40) (4") (618-7040)LF15$35.00$55.00$75.00$55.00$65.87$59.01
97Conduit (PVC) (schedule 40) (4") (bore) (618-7041)LF405$42.00$37.00$40.00$37.00$47.91$39.49
98Conduit (PVC) (schedule 80) (2") (bore) (618-7055)LF415$37.00$31.00$33.00$31.00$37.13$32.85
99Conduit (RM) (1") (618-7072)LF675$35.00$37.00$40.00$37.00$44.31$38.80
100Conduit (prepare) (618-7090)LF3,680$5.50$4.00$5.00$3.95$4.79$4.21
101Electrical conductor (no.14) insulated (620-7002)LF440$1.85$1.40$1.75$1.45$2.39$1.51
102Electrical conductor (no.12) insulated (620-7004)LF400$2.30$1.85$2.00$1.85$2.69$1.98
103Electrical conductor (no.8) insulated (620-7008)LF36,165$3.15$3.00$3.25$2.95$3.59$3.15
104Electrical conductor (no.6) insulated (620-7010)LF2,850$3.15$3.40$3.75$3.40$4.79$3.64
105ITS GND box (poly) type 1 (243648)W/aprn (623-7018)EACH3$4,000.00$3,640.00$4,025.00$3,635.00$4,354.00$3,900.08
106ITS GND box (poly) type 2 (366048)W/aprn (623-7024)EACH1$6,500.00$6,100.00$6,745.00$6,100.00$7,306.58$6,536.25
107Ground box type A (122311)W/apron (624-7002)EACH16$1,700.00$1,400.00$1,550.00$1,400.00$1,736.81$1,500.14
108Ground box type D (162922)W/apron (624-7008)EACH3$2,000.00$1,800.00$870.00$1,800.00$2,156.04$1,912.53
109Remove ground box (624-7013)EACH24$750.00$475.00$525.00$475.00$598.90$506.08
110Aluminum signs (type A) (636-7001)SF91.25$40.00$32.00$37.00$32.00$47.91$33.45
111Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH9$1,100.00$1,025.00$1,225.00$1,025.00$1,257.69$1,098.86
112Install small roadside sign support and assembly type 10BWG(1)SB(T) (644-7012)EACH2$800.00$1,080.00$1,300.00$1,080.00$1,317.58$1,156.11
113Install small roadside sign support and assembly type 10BWG(2)SA(P) (644-7017)EACH2$1,200.00$1,650.00$2,395.00$1,645.00$2,036.26$1,761.85
114In bridge MNT clearance sign assembly(type N) (644-7061)EACH2$5,000.00$2,950.00$3,665.00$2,945.00$3,593.40$3,155.68
115In bridge MNT clearance sign assembly(type S) (644-7062)EACH2$3,800.00$2,950.00$3,665.00$2,945.00$3,593.40$3,155.68
116Install small roadside sign support and assembly (inst sign only) (644-7064)EACH1$315.00$103.00$1,645.00$105.00$125.76$110.08
117Relocate SM RD SN sup&AM type 10BWG (644-7065)EACH9$750.00$750.00$718.00$750.00$898.35$796.07
118Remove SM RD SN sup&AM (644-7073)EACH18$230.00$120.00$180.00$120.00$143.73$127.06
119Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018)EACH52$45.00$50.00$22.00$75.00$65.87$56.33
120Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032)EACH12$55.00$70.00$95.00$75.00$71.86$64.38
121Work zone pavement marking removing (reflectorized) type I-C (662-7049)EACH897$1.20$8.00$11.40$6.85$8.20$7.35
122Work zone pavement marking removing (reflectorized) type II-A-A (662-7051)EACH2,452$1.20$8.00$11.00$6.85$8.14$7.35
123Work zone pavement marking removing (traffic BTN) type W (662-7057)EACH597$1.20$7.00$9.50$6.00$7.18$6.44
124Work zone pavement marking removing (W)6"(solid) (662-7068)LF13,226$2.50$2.75$3.75$2.45$2.89$2.60
125Work zone pavement marking removing (Y)6"(solid) (662-7100)LF11,740$1.00$2.00$2.75$1.75$2.09$1.88
126Reflectorized pavement marking type I (W)6"(DOT)(090MIL) (666-7008)LF598$0.35$2.00$2.75$1.75$2.09$1.88
127Reflectorized pavement marking type I (W)6"(lane drop)(090MIL) (666-7011)LF1,284$2.00$1.20$1.65$1.05$1.24$1.12
128Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023)LF3,332$1.50$1.75$2.46$1.60$1.88$1.68
129Reflectorized pavement marking type I (W)12"(solid)(090MIL) (666-7029)LF1,246$3.35$4.60$6.40$4.15$4.93$4.42
130Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035)LF215$9.00$9.75$13.40$8.75$10.78$9.37
131Reflectorized pavement marking type I (W)(arrow)(090MIL) (666-7041)EACH18$150.00$170.00$235.00$155.00$180.86$162.01
132Reflectorized pavement marking type I(W)(double arrow)(090MIL) (666-7044)EACH6$200.00$245.00$335.00$220.00$263.51$232.82
133Reflectorized pavement marking type I(W)(lane drop arrow)(090MIL) (666-7059)EACH6$380.00$380.00$535.00$340.00$407.25$363.72
134Reflectorized pavement marking type I (W)(word)(090MIL) (666-7065)EACH18$165.00$170.00$235.00$155.00$182.06$163.08
135Reflectorized pavement marking type I (W)(bike arrow)(090MIL) (666-7092)EACH8$175.00$160.00$220.00$145.00$173.68$154.50
136Reflectorized pavement marking type I(W)(bike syml)(090MIL) (666-7098)EACH8$215.00$207.00$290.00$185.00$221.59$198.49
137Reflectorized pavement marking type II (W) 6" (broken) (666-7172)LF3,253$0.50$0.60$0.86$0.55$0.65$0.59
138Reflectorized pavement marking type II (W) 6" (DOT) (666-7173)LF598$1.40$1.25$1.70$1.10$1.31$1.17
139Reflectorized pavement marking type II (W) 6" (lane drop) (666-7174)LF1,284$1.90$0.75$1.00$0.65$0.74$0.67
140Reflectorized pavement marking type II (W) 6" (solid) (666-7175)LF18,716$0.50$0.30$0.40$0.25$0.29$0.27
141Reflectorized pavement marking type II (W) 8" (solid) (666-7179)LF3,332$0.75$0.90$1.25$0.80$0.95$0.85
142Reflectorized pavement marking type II (W) 12" (solid) (666-7182)LF1,246$2.00$3.75$5.00$3.20$3.83$3.43
143Reflectorized pavement marking type II (W) 24" (solid) (666-7184)LF215$5.00$6.20$8.65$5.50$6.58$5.86
144Reflectorized pavement marking type II (W) (arrow) (666-7186)EACH18$120.00$255.00$355.00$230.00$275.49$244.63
145Reflectorized pavement marking type II (W) (double arrow) (666-7187)EACH6$130.00$150.79$220.00$135.00$161.70$141.63
146Reflectorized pavement marking type II (W) (LN reduct arrow) (666-7192)EACH6$185.00$180.00$260.00$160.00$191.64$169.52
147Reflectorized pavement marking type II (W) (word) (666-7194)EACH18$130.00$105.00$145.00$95.00$119.78$100.85
148Reflectorized pavement marking type II (W) (bike arrow) (666-7203)EACH7$80.00$95.00$130.00$81.00$119.78$86.91
149Reflectorized pavement marking type II (W) (bike symbol) (666-7205)EACH7$85.00$80.00$110.00$71.00$119.78$76.18
150Reflectorized pavement marking type II (Y) 6" (solid) (666-7213)LF17,095$0.60$0.30$0.40$0.30$0.33$0.28
151Reflectorized pavement marking type I (W)6"(broken)(090MIL) (666-7407)LF3,253$1.00$1.75$2.50$1.60$1.91$1.68
152Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410)LF18,716$1.00$1.05$1.50$0.95$1.13$1.01
153Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422)LF17,095$1.00$1.00$1.50$0.90$1.07$0.97
154Reflectorized pavement marker type II-A-A (672-7004)EACH6$6.00$10.00$18.45$8.95$10.78$9.58
155Reflectorized pavement marker type II-C-R (672-7006)EACH488$6.00$10.00$14.00$8.95$10.78$9.57
156Eliminating existing PM & markers (4") (677-7001)LF10,134$0.75$0.70$1.00$0.65$0.74$0.65
157Eliminating existing PM & markers (12") (677-7006)LF1,039$1.75$3.50$4.60$3.05$3.65$3.25
158Eliminating existing PM & markers (24") (677-7008)LF224$3.00$8.50$11.45$7.45$8.98$7.97
159Eliminating existing PM & markers (arrow) (677-7009)EACH8$130.00$190.00$320.00$167.00$203.62$179.18
160Eliminating existing PM & markers (double arrow) (677-7010)EACH4$110.00$240.00$332.00$208.00$251.53$223.17
161Eliminating existing PM & markers (word) (677-7015)EACH8$145.00$220.00$304.00$191.00$228.78$204.93
162Eliminating existing PM & markers (symbol) (677-7020)EACH4$80.00$170.00$275.00$149.00$179.67$159.87
163Eliminating existing PM & marks (bike arrow) (677-7025)EACH4$50.00$200.00$332.00$175.00$215.60$187.76
164Eliminating existing PM & marks (bike symbol) (677-7027)EACH4$70.00$200.00$332.00$175.00$215.60$187.76
165Pavement surface preparation for marking (6") (678-7002)LF40,946$0.50$0.55$0.75$0.50$0.59$0.52
166Pavement surface preparation for marking (8") (678-7004)LF3,332$0.30$0.65$0.90$0.60$0.67$0.60
167Pavement surface preparation for marking (12") (678-7006)LF1,246$0.50$0.75$1.45$0.70$0.83$0.72
168Pavement surface preparation for marking (24") (678-7008)LF215$3.00$0.95$2.00$0.85$1.01$0.89
169Pavement surface preparation for marking (arrow) (678-7009)EACH24$27.00$60.00$83.00$51.00$61.08$54.72
170Pavement surface preparation for marking (double arrow) (678-7010)EACH6$32.00$170.00$295.00$150.00$179.67$158.79
171Pavement surface preparation for marking (word) (678-7016)EACH18$32.00$185.00$260.00$166.00$198.83$178.11
172Pavement surface preparation for marking (bike arrow) (678-7026)EACH7$32.00$158.00$316.00$141.00$173.68$151.28
173Pavement surface preparation for marking (bike symbol) (678-7028)EACH7$40.00$100.00$190.00$88.50$107.08$94.95
174Removing traffic signals (680-7004)EACH1$15,000$10,700$11,750$15,000$12,816$11,392
175Install highway traffic signal (upgrade) (680-7011)EACH1$38,000$10,300$11,400$15,000$12,337$11,041
176Vehicle signal section (12")LED(green) (682-7001)EACH5$450.00$330.00$375.00$330.00$395.27$352.78
177Vehicle signal section (12")LED(green arrow) (682-7002)EACH6$445.00$330.00$370.00$330.00$395.27$352.78
178Vehicle signal section (12")LED(yel) (682-7003)EACH9$435.00$330.00$370.00$330.00$395.27$352.78
179Vehicle signal section (12")LED(yel arrow) (682-7004)EACH2$425.00$330.00$390.00$330.00$395.27$352.78
180Vehicle signal section (12")LED(red) (682-7005)EACH9$435.00$330.00$370.00$330.00$395.27$352.78
181Vehicle signal section (12")LED(red arrow) (682-7006)EACH1$430.00$330.00$445.00$330.00$395.27$352.78
182Backplate W/reflectorized border(3 sec)aluminum (682-7039)EACH9$330.00$165.00$180.00$165.00$203.62$172.90
183Backplate W/reflectorized border(5 sec)aluminum (682-7041)EACH1$330.00$215.00$330.00$215.00$263.51$226.06
184Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031)LF410$6.75$3.00$3.15$2.85$3.59$3.06
185Traffic signal CBL (type A)(14 AWG)(20 conductor) (684-7046)LF1,260$8.00$9.50$10.45$9.50$11.97$10.10
186Ins traffic signal PL AM(S)1 arm(36')lum (686-7039)EACH2$16,000$14,000$15,300$15,000$16,769$14,824
187Ins traffic signal PL AM(S)1 arm(44')lum (686-7047)EACH1$17,000$16,000$17,000$17,500$18,566$16,482
188CNC crack repair (discrete)(inject) (780-7002)LF83$123.00$140.00$25.00$50.00$143.73$160.94
189Relocate RVDS (6008-7007)EACH3$2,000.00$1,270.00$1,400.00$1,275.00$1,796.70$1,352.96
190Radar presence detector comm cable (6008-7009)LF1,350$3.75$4.00$4.50$3.95$4.79$4.24
191Ground box (prepare) (6013-7006)EACH9$600.00$525.00$580.00$525.00$1,197.80$563.28
192Fiber optic fusion splice (6027-7004)EACH108$140.00$115.00$125.00$115.00$149.72$120.61
193FO splice enclosure (type 1) (6027-7009)EACH1$2,700.00$2,500.00$2,745.00$2,500.00$2,994.50$2,660.85
194FO CBL (12 SMF) (6027-7028)LF440$11.00$8.00$8.35$7.55$11.97$8.09
195Remove existing cables (power) (6106-7002)LF605$1.30$19.00$20.70$18.75$23.95$19.97
TxDOT contract A00194720: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of July 2, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy