TxDOT contract A00195365 bid tabulation
Bridge Maintenance, Various (VARIOUS to .). Let by Texas DOT on October 9, 2025, Taylor, Abilene District. 9 bids received; low bid $2,254,760 by Scott Tucker Construction Company, LLC, -25% against the engineer's estimate of $2,988,467.
- Owner
- Texas DOT
- Letting
- 09 OCT 2025
- Pay items
- 58
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Scott Tucker Construction Company, LLC | $2,254,760 | Low | -25% |
| 2 | Ragle Construction, Inc. | $2,415,899 | +7.0% | -19% |
| 3 | Blacksmith Ventures LLC | $2,441,851 | +8.0% | -18% |
| 4 | Structural Integrity Group LLC | $2,574,296 | +14% | -14% |
| 5 | Premier Contractors LLC | $2,592,444 | +15% | -13% |
| 6 | Built Right Construction of Oklahoma, LLC | $2,619,800 | +16% | -12% |
| 7 | SCR Civil Construction, LLC | $2,947,088 | +31% | -1.0% |
| 8 | Ti-Zack Concrete, LLC | $3,150,326 | +40% | +5.0% |
| 9 | Grey Sky Construction LLC | $3,654,252 | +62% | +22% |
Engineer's estimate: $2,988,467.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Scott Tucker Construction Company, LLC | 2. Ragle Construction, Inc. | 3. Blacksmith Ventures LLC | 4. Structural Integrity Group LLC | 5. Premier Contractors LLC | 6. Built Right Construction of Oklahoma, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 1 | $10,000 | $3,839.00 | $50,000 | $1,000.00 | $9,500.00 | $10,000 | $1,500.00 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 261 | $60.00 | $60.00 | $15.00 | $150.00 | $54.00 | $50.00 | $20.00 |
| 3 | Excavation (roadway & channel) (110-7004) | CY | 83 | $55.00 | $66.00 | $40.00 | $35.00 | $49.00 | $22.00 | $150.00 |
| 4 | Embankment (final)(OC)(type B) (132-7003) | CY | 203 | $60.00 | $88.00 | $55.00 | $65.00 | $56.00 | $30.00 | $30.00 |
| 5 | Broadcast seed (permanent_urban_sand) (164-7003) | SY | 5,200 | $4.00 | $0.50 | $1.00 | $2.00 | $1.50 | $3.00 | |
| 6 | Vegetative watering (168-7001) | TGL | 41.60 | $180.00 | $150.00 | $100.00 | $100.00 | $100.00 | $250.00 | |
| 7 | Soil ret BLKT(SL_steep_sand_long) (169-7008) | SY | 5,200 | $3.00 | $3.55 | $5.00 | $3.00 | $3.00 | $8.00 | |
| 8 | Flexible pavement structure repair(6") (351-7005) | SY | 5 | $748.00 | $1,000.00 | $1,000.00 | $640.00 | $90.00 | $400.00 | |
| 9 | Planing asphalt concrete pavement(2") (354-7051) | SY | 539 | $15.00 | $50.00 | $23.00 | $35.00 | $43.50 | $9.00 | $25.00 |
| 10 | Cem stabil BKFL (400-7010) | CY | 66 | $400.00 | $235.00 | $160.00 | $375.00 | $265.00 | $200.00 | $400.00 |
| 11 | Flowable backfill (401-7001) | CY | 25 | $550.00 | $425.00 | $370.00 | $750.00 | $790.00 | $100.00 | $400.00 |
| 12 | Temporary special shoring (403-7001) | SF | 632 | $60.00 | $25.00 | $65.00 | $50.00 | $45.00 | $55.00 | $80.00 |
| 13 | Class A concrete (miscellaneous) (420-7002) | CY | 8 | $800.00 | $1,361.00 | $2,200.00 | $500.00 | $1,700.00 | $1,500.00 | $1,300.00 |
| 14 | Class C concrete (wingwalls) (420-7146) | CY | 20.40 | $4,200.00 | $3,827.00 | $1,700.00 | $1,750.00 | $5,375.00 | $3,500.00 | $1,500.00 |
| 15 | Concrete structure repair(deck rep(part depth)) (429-7003) | SF | 240 | $250.00 | $105.00 | $45.00 | $95.00 | $185.00 | $250.00 | $325.00 |
| 16 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 3,130 | $190.00 | $132.00 | $125.00 | $145.00 | $184.70 | $350.00 | $225.00 |
| 17 | Riprap (concrete)(4 in) (432-7001) | CY | 13 | $1,200.00 | $731.00 | $800.00 | $600.00 | $750.00 | $1,000.00 | $800.00 |
| 18 | Riprap (concrete)(flume) (432-7012) | CY | 85 | $948.00 | $625.00 | $500.00 | $900.00 | $1,000.00 | $700.00 | |
| 19 | Riprap (stone common)(dry)(18 in) (432-7033) | CY | 20 | $312.00 | $340.00 | $199.00 | $270.00 | $250.00 | $300.00 | |
| 20 | Riprap (stone protection)(12 in) (432-7041) | CY | 475 | $690.00 | $237.00 | $215.00 | $199.00 | $250.00 | $250.00 | $225.00 |
| 21 | Riprap (stone protection)(18 in) (432-7043) | CY | 54 | $300.00 | $264.00 | $175.00 | $199.00 | $268.00 | $250.00 | $250.00 |
| 22 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 486 | $55.00 | $44.00 | $18.00 | $45.00 | $38.00 | $55.00 | $60.00 |
| 23 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 414 | $60.00 | $41.00 | $23.00 | $45.00 | $58.00 | $55.00 | $60.00 |
| 24 | Cleaning existing joints (438-7008) | LF | 114 | $30.00 | $26.00 | $25.00 | $45.00 | $26.00 | $550.00 | $50.00 |
| 25 | Cleaning and sealing joints (foam) (438-7010) | LF | 280 | $100.00 | $129.00 | $65.00 | $100.00 | $140.00 | $50.00 | $110.00 |
| 26 | Clean and seal JNTS (pan girders) (CL7) (438-7012) | LF | 221 | $75.00 | $51.00 | $65.00 | $45.00 | $68.00 | $50.00 | $50.00 |
| 27 | Polyester polymer concrete overlay (2") (439-7017) | SY | 539 | $275.00 | $498.00 | $425.00 | $255.00 | $376.00 | $15.00 | $200.00 |
| 28 | Retrofit rail (type T131RC) (451-7049) | LF | 217 | $300.00 | $261.00 | $178.50 | $325.00 | $250.00 | $250.00 | $250.00 |
| 29 | Gabion mattresses (galvanized) (459-7002) | CY | 74 | $750.00 | $425.00 | $530.00 | $300.00 | $400.00 | $250.00 | $350.00 |
| 30 | Raising existing struct (495-7002) | EACH | 2 | $25,000 | $29,556 | $45,000 | $50,000 | $10,000 | $25,000 | $55,000 |
| 31 | Removing structure (wingwall) (496-7005) | EACH | 4 | $5,000.00 | $5,099.00 | $2,600.00 | $2,000.00 | $4,500.00 | $7,000.00 | $1,200.00 |
| 32 | Mobilization (500-7001) | LS | 1 | $260,000 | $225,444 | $240,000 | $325,000 | $255,000 | $250,000 | $245,000 |
| 33 | Barricades, signs and traffic handling (502-7001) | MO | 17 | $15,000 | $4,495.00 | $19,250 | $7,500.00 | $11,000 | $10.00 | $5,000.00 |
| 34 | Portable changeable message sign (503-7002) | EACH | 5 | $12,000 | $10,064 | $20,000 | $5,000.00 | $5,000.00 | $10.00 | $3,500.00 |
| 35 | TMA (stationary) (505-7001) | DAY | 222 | $300.00 | $375.00 | $250.00 | $450.00 | $1.00 | $10.00 | $300.00 |
| 36 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 740 | $3.00 | $7.00 | $15.00 | $8.00 | $10.00 | $20.00 | |
| 37 | Biodegradable erosion control logs (remove) (506-7046) | LF | 740 | $2.00 | $2.00 | $1.00 | $2.00 | $1.00 | $3.00 | |
| 38 | Metal W-beam guard fence (timber post) (540-7001) | LF | 875 | $35.00 | $56.00 | $22.50 | $40.00 | $68.00 | $30.00 | $30.00 |
| 39 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,800.00 | $3,249.00 | $1,550.00 | $3,000.00 | $1,950.00 | $1,000.00 | $2,000.00 |
| 40 | Metal beam guard fence (long span system) (540-7027) | EACH | 2 | $1,500.00 | $2,532.00 | $1,200.00 | $4,000.00 | $1,400.00 | $1,150.00 | $1,800.00 |
| 41 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $3,800.00 | $3,563.00 | $3,000.00 | $4,000.00 | $3,100.00 | $3,300.00 | $3,700.00 |
| 42 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 6 | $80.00 | $42.00 | $45.00 | $50.00 | $25.00 | $25.00 | $50.00 |
| 43 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 24 | $60.00 | $42.00 | $45.00 | $50.00 | $40.00 | $30.00 | $50.00 |
| 44 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 1,100 | $3.60 | $8.00 | $2.50 | $5.00 | $1.75 | $1.00 | $10.00 |
| 45 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 150 | $3.60 | $11.00 | $2.50 | $10.00 | $2.00 | $1.00 | $10.00 |
| 46 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 500 | $3.60 | $9.00 | $2.50 | $5.00 | $1.50 | $1.00 | $10.00 |
| 47 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 17 | $12.00 | $52.00 | $10.00 | $30.00 | $8.00 | $6.00 | $30.00 |
| 48 | Eliminating existing PM & markers (4") (677-7001) | LF | 1,180 | $2.00 | $8.00 | $2.00 | $1.00 | $1.10 | $2.00 | $9.00 |
| 49 | Pavement surface preparation for marking (6") (678-7002) | LF | 1,750 | $1.25 | $6.00 | $0.50 | $10.00 | $1.00 | $2.00 | $6.00 |
| 50 | Concrete CRCK repair(discrete)(rout and seal) (780-7003) | LF | 25 | $71.00 | $150.00 | $100.00 | $316.00 | $150.00 | $50.00 | |
| 51 | Rep steel bridge member (beam) (784-7002) | EACH | 8 | $4,566.00 | $10,000 | $12,000 | $18,000 | $10,000 | $15,000 | |
| 52 | Rep steel bridge member (diaphragm) (784-7003) | EACH | 2 | $5,132.00 | $7,500.00 | $15,000 | $7,000.00 | $10,000 | $9,000.00 | |
| 53 | Rep steel bridge MBR (weld repair) (784-7022) | EACH | 2 | $5,132.00 | $3,500.00 | $15,000 | $5,000.00 | $10,000 | $9,000.00 | |
| 54 | Bridge joint replacement (armor) (785-7010) | LF | 268 | $600.00 | $358.00 | $375.00 | $500.00 | $565.00 | $500.00 | $500.00 |
| 55 | Bridge joint replacement (header) (785-7013) | LF | 74 | $216.00 | $125.00 | $425.00 | $144.00 | $500.00 | $500.00 | |
| 56 | Carbon fiber reinforced polymer protection (786-7001) | SF | 458 | $97.00 | $80.00 | $125.00 | $93.00 | $70.00 | $85.00 | |
| 57 | Steel bridge zone painting (4010-7013) | LS | 1 | $110,000 | $32,691 | $100,000 | $60,000 | $59,000 | $45,000 | $92,500 |
| 58 | Bent cap/abutment cap cleaning (7001-7002) | EACH | 4 | $1,600.00 | $150.00 | $400.00 | $1,500.00 | $400.00 | $2,000.00 | $450.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 9, 2025. Compiled by Mirage Metrics.