TxDOT contract A00199664 bid tabulation

Widen Road - Add Shoulders, FM 3349 (CR 404 to FM 1660). Let by Texas DOT on June 5, 2025, Williamson, Austin District. 8 bids received; low bid $4,662,191 by Hunter Industries, LTD., -10% against the engineer's estimate of $5,189,368.

Owner
Texas DOT
Letting
05 JUN 2025
Pay items
98
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Hunter Industries, LTD.$4,662,191Low-10%
2Jordan Foster Construction, LLC$5,170,343+11%0.0%
3Chasco Constructors$5,198,378+12%0.0%
4Texas Road LLC$5,235,504+12%+1.0%
5Dan Williams Company$5,486,521+18%+6.0%
6Aaron Concrete Contractors, LLC$5,605,328+20%+8.0%
7Joe Bland Construction LLC$5,690,119+22%+10%
8Patin Construction LLC$5,792,679+24%+12%
TxDOT contract A00199664: bids by rank

Engineer's estimate: $5,189,368.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Hunter Industries, LTD.2. Jordan Foster Construction, LLC3. Chasco Constructors4. Texas Road LLC5. Dan Williams Company6. Aaron Concrete Contractors, LLC
1Preparing row (100-7002)STA106$2,000.00$907.98$3,935.00$540.00$2,500.00$3,500.00$1,500.00
2Remove (7") TRT/untrt base & asphalt pavement (105-7027)SY4,535$8.50$10.38$5.00$22.00$9.50$10.00$16.00
3Excavation (roadway) (110-7001)CY9,275$17.50$12.74$7.00$15.00$21.00$15.00$13.00
4Embankment (final)(OC)(type B) (132-7003)CY3,060$22.50$16.28$27.00$19.00$16.00$35.00$15.00
5Furn & place topsoil (4") (160-7002)SY71,341$2.00$1.61$1.40$3.00$1.00$1.50$1.10
6Broadcast seed (temporary_warm_cool) (164-7007)SY71,341$0.20$0.12$0.16$0.20$0.17$0.29$0.15
7Drill seed (permanent_rural_clay) (164-7010)SY71,341$0.25$0.16$0.16$0.25$0.18$0.35$0.15
8Vegetative watering (168-7001)TGL1,199$30.00$27.68$1.00$17.00$31.00$10.00$42.00
9Soil ret BLKT(SL_mod_clay_long) (169-7002)SY71,341$1.20$0.83$1.30$1.25$1.40$2.00$0.90
10FL BS (compacted in place)(type A GR 5)(final pos) (247-7179)CY4,403$80.00$79.93$88.00$81.00$74.00$70.00$78.00
11Lime (com or QK)(slurry) (260-7005)TON410$350.00$385.00$375.00$330.00$350.00$325.00$383.00
12Lime TRT (subgrade) (8") (260-7020)SY22,657$6.00$3.72$7.00$8.00$11.50$4.00$7.00
13Prime coat(MC-30 or AE-P) (310-7013)GAL3,909$5.00$5.11$3.80$4.00$3.95$3.50$4.30
14D-GR HMA type-C PG76-22 (341-7030)TON1,964$140.00$120.10$120.00$126.00$131.00$125.00$142.00
15D-GR HMA type D PG76-22 (level-UP) (341-7059)TON4,618$145.00$117.74$118.00$122.00$127.00$122.00$138.00
16Tom-C PG76-22 sac-B (347-7002)TON2,396$155.00$141.78$158.00$165.00$171.00$160.00$185.00
17Flexible pavement structure repair(4") (351-7003)SY8,000$40.00$31.83$38.00$41.00$40.00$34.00$42.00
18Cut & restoring pavement (400-7006)SY93$165.00$97.20$118.00$365.00$240.00$100.00$360.00
19Cem stabil BKFL (400-7010)CY134$233.00$323.99$200.00$200.00$300.00$225.00$240.00
20Trench excavation protection (402-7001)LF100$150.00$27.00$17.00$61.00$56.00$1.00$6.00
21Temporary special shoring (403-7001)SF168$60.00$172.80$3.15$60.00$56.00$125.00$43.00
22Riprap (concrete)(CL B) (432-7005)CY79$750.00$658.78$825.00$800.00$550.00$500.00$890.00
23Riprap (mow strip)(4 in) (432-7013)CY48$500.00$626.38$675.00$708.00$570.00$700.00$795.00
24Rirrap (stone common)(dry)(15 in) (432-7032)CY104$200.00$269.99$210.00$260.00$200.00$150.00$214.00
25Concrete box culvert (4 FT X 2 FT) (462-7003)LF120$400.00$640.11$390.00$367.00$410.00$450.00$390.00
26Concrete box culvert (8 FT X 4 FT) (462-7021)LF168$1,350.00$1,295.10$900.00$990.00$1,200.00$1,100.00$995.00
27Concrete box culvert (8 FT X 4 FT)(extend) (462-7076)LF102$1,500.00$1,211.73$1,450.00$1,180.00$1,100.00$1,000.00$1,600.00
28RC pipe (CL III)(18 in) (464-7003)LF76$68.00$124.20$132.00$87.00$87.00$90.00$126.00
29RC pipe (CL III)(24 in) (464-7005)LF730$110.00$153.36$134.00$108.00$110.00$105.00$134.00
30Wingwall (PW - 1) (HW=6 FT) (466-7176)EACH2$21,000$46,285$46,000$39,000$44,000$45,000$67,000
31Set (type I)(S= 4 FT)(HW= 3 FT)(6:1)(P) (467-7070)EACH8$10,000$12,420$12,500$6,200.00$9,500.00$7,000.00$8,300.00
32Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH2$1,500.00$1,403.96$1,400.00$3,300.00$3,600.00$2,650.00$2,300.00
33Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH48$2,500.00$1,824.07$1,800.00$3,600.00$4,200.00$4,000.00$2,700.00
34Clean existing culverts (480-7001)EACH1$4,200.00$2,699.92$5,121.40$1,990.00$5,000.00$2,000.00$3,100.00
35Removing structure (set) (496-7004)EACH38$700.00$1,025.97$340.00$460.00$690.00$400.00$10,000
36Removing structure (headwall) (496-7006)EACH2$3,500.00$2,699.92$3,800.00$1,780.00$3,800.00$3,000.00$15,000
37Removing structure (pipe) (496-7007)LF630$20.00$44.28$14.00$33.00$18.00$18.00$44.00
38Mobilization (500-7001)LS1$385,000$375,028$500,000$435,000$336,000$540,000$400,000
39Barricades, signs and traffic handling (502-7001)MO14$7,500.00$3,846.40$6,700.00$3,800.00$8,000.00$25,000$785.00
40Portable changeable message sign (503-7002)EACH2$15,000$8,118.75$10,000$22,000$30,000$15,000$10,300
41TMA (stationary) (505-7001)DAY350$275.00$270.62$350.00$360.00$84.00$150.00$245.00
42TMA (mobile operation) (505-7003)DAY19$650.00$433.00$850.00$1,400.00$45.00$650.00$918.00
43Rock filter dams (install) (type 2) (506-7002)LF94$50.00$211.89$36.00$95.00$39.00$45.00$73.00
44Rock filter dams (install) (type 4) (506-7004)LF120$75.00$60.17$62.00$112.00$66.00$52.00$87.00
45Rock filter dams (remove) (506-7011)LF214$16.00$23.48$15.00$36.00$18.00$21.00$26.00
46Construction exits (install) (type 1) (506-7020)SY312$35.00$41.24$21.00$77.00$23.00$41.00$45.00
47Construction exits (remove) (506-7024)SY312$12.00$15.57$10.50$24.00$12.00$13.00$17.00
48Temporary sediment control fence (install) (506-7039)LF6,180$4.50$4.09$3.20$6.00$3.50$6.00$4.50
49Temporary sediment control fence (remove) (506-7041)LF6,180$2.00$1.21$1.05$2.00$1.05$3.00$1.32
50Biodegradable erosion control logs (install) (12") (506-7044)LF300$8.00$13.93$6.35$22.00$6.60$8.00$15.25
51Biodegradable erosion control logs (remove) (506-7046)LF300$3.00$1.69$1.05$3.00$1.10$3.00$1.85
52Constructing detours (508-7001)SY312$80.00$50.16$220.00$245.00$140.00$225.00$263.14
53Driveways (ACP) (530-7010)SY1,044$70.00$50.16$95.00$110.00$105.00$100.00$105.41
54Turnouts (ACP) (530-7018)SY299$70.00$50.16$85.00$123.00$120.00$85.00$81.66
55Metal W-beam guard fence (timber post) (540-7001)LF400$35.00$27.50$26.00$30.00$31.00$45.00$33.67
56Metal W - beam guard fence (low fill culvert) (540-7018)LF150$90.00$90.00$114.00$98.00$101.00$150.00$110.18
57Guardrail end treatment (install) (544-7001)EACH4$3,500.00$3,450.00$3,800.00$3,760.00$3,900.00$5,000.00$4,223.47
58Mailbox install-S (TWW-post) type 4 (560-7008)EACH8$360.00$345.41$315.00$545.00$340.00$350.00$605.98
59Mailbox install-D (TWW-post) type 4 (560-7009)EACH2$380.00$345.41$370.00$600.00$396.00$350.00$649.00
60Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009)EACH10$660.00$838.71$770.00$790.00$850.00$800.00$900.00
61Install small roadside sign support and assembly type 10BWG(1)SB(T) (644-7012)EACH5$680.00$1,144.18$900.00$926.00$960.00$1,200.00$1,200.00
62Relocate SM RD SN sup&AM type 10BWG (644-7065)EACH1$650.00$367.00$475.00$490.00$510.00$500.00$830.00
63Relocate SM RD SN sup&AM(hist marker) (644-7070)EACH1$550.00$838.71$475.00$490.00$800.00$800.00$918.00
64Remove SM RD SN sup&AM (644-7073)EACH12$160.00$134.93$105.00$109.00$113.00$200.00$184.00
65Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH10$60.00$38.50$51.00$36.00$40.00$85.00$47.00
66Install object marker assembly (OM-2Z)(WFLX)GND (658-7058)EACH32$70.00$98.50$107.00$105.00$113.00$125.00$120.00
67Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF20,986$0.50$0.39$0.30$0.45$0.45$0.39$0.40
68Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF20,986$0.45$0.39$0.30$0.45$0.45$0.39$0.40
69Work zone pavement marking removing (W)6"(solid) (662-7068)LF12,593$1.20$0.82$1.00$0.90$0.95$0.82$1.10
70Work zone pavement marking removing (W)24"(solid) (662-7077)LF96$24.00$14.00$12.50$15.00$16.00$14.00$15.00
71Work zone pavement marking removing (Y)6"(solid) (662-7100)LF20,986$0.80$0.65$0.95$0.70$0.75$0.65$1.10
72Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH30$1.20$1.63$2.10$20.00$2.35$2.50$1.00
73Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH2,099$1.20$1.63$2.10$9.00$2.35$2.50$1.90
74Reflectorized pavement marking type I (W)8"(DOT)(090MIL) (666-7017)LF38$1.85$1.85$3.20$2.00$2.20$1.85$3.70
75Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023)LF540$1.25$1.10$1.60$1.20$1.30$1.10$1.85
76Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035)LF24$10.00$13.00$8.50$14.00$15.00$13.00$9.80
77Reflectorized pavement marking type I (W)(arrow)(090MIL) (666-7041)EACH4$180.00$190.00$185.00$200.00$223.00$190.00$215.00
78Reflectorized pavement marking type I (W)(word)(090MIL) (666-7065)EACH4$250.00$200.00$215.00$210.00$235.00$200.00$245.00
79Reflectorized pavement marking type II (W) 6" (solid) (666-7175)LF21,064$0.45$0.26$0.36$0.30$0.30$0.26$0.40
80Reflectorized pavement marking type II (W) 8" (DOT) (666-7177)LF38$5.25$1.15$2.15$1.25$1.35$1.15$2.45
81Reflectorized pavement marking type II (W) 8" (solid) (666-7179)LF540$0.60$0.65$0.60$0.70$0.75$0.65$0.70
82Reflectorized pavement marking type II (W) 24" (solid) (666-7184)LF24$5.25$2.90$5.35$3.25$3.40$2.90$6.10
83Reflectorized pavement marking type II (W) (arrow) (666-7186)EACH4$106.00$80.00$105.00$82.00$94.00$80.00$123.00
84Reflectorized pavement marking type II (W) (word) (666-7194)EACH4$160.00$90.00$135.00$92.00$105.00$90.00$153.00
85Reflectorized pavement marking type II (Y) 6" (broken) (666-7211)LF1,970$0.60$0.28$0.40$0.30$0.30$0.28$0.40
86Reflectorized pavement marking type II (Y) 6" (solid) (666-7213)LF6,692$0.60$0.26$0.40$0.30$0.30$0.26$0.40
87Reflectorized profile pavement marking type I(W)6"(solid)(090MIL) (666-7265)LF21,064$1.15$1.05$1.25$1.20$1.25$1.05$1.50
88Reflectorized profile pavement marking type I(Y)6"(solid)(090MIL) (666-7269)LF6,692$1.20$1.05$1.25$1.20$1.25$1.05$1.50
89Reflectorized profile pavement marking type I(Y)6"(broken)(090MIL) (666-7273)LF1,970$5.50$1.10$1.25$1.20$1.30$1.10$1.50
90PRFB rumble strip (BLK)(1')(centerline) (668-7002)LF2,055$5.50$5.00$5.80$5.50$5.80$5.00$6.70
91PRFB rumble strip (BLK)(1')(edgeline) (668-7137)LF3,860$5.50$5.00$5.80$5.50$5.80$5.00$6.70
92Reflectorized pavement marker type I-C (672-7002)EACH30$6.00$10.00$6.15$11.00$11.50$10.00$7.00
93Reflectorized pavement marker type II-A-A (672-7004)EACH258$5.50$7.00$6.15$7.50$8.20$7.00$7.00
94Eliminating existing PM & markers (4") (677-7001)LF8,840$1.50$1.00$1.50$1.00$1.20$1.00$1.75
95Bonding course (3007-7001)GAL7,648$5.25$3.65$3.70$4.00$3.90$3.50$4.30
96Install bridge identification numbers (4019-7001)EACH2$1,200.00$1,336.34$370.00$3,300.00$566.00$500.00$612.00
97Subsurface util locate (outside rdbed) (7019-7001)EACH20$1,000.00$3,500.00$485.00$108.00$760.00$1,000.00$630.00
98Subsurface util locate (within rdbed) (7019-7002)EACH10$2,700.00$3,500.00$600.00$270.00$4,150.00$1,500.00$2,200.00
TxDOT contract A00199664: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of June 5, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy