TxDOT contract A00205962 bid tabulation
Bridge Maintenance, US 67 (US 67 SB at Wheatland Road to .). Let by Texas DOT on July 1, 2025, Dallas, Dallas District. 6 bids received; low bid $4,922,876 by Ragle Construction, Inc., -24% against the engineer's estimate of $6,466,326.
- Owner
- Texas DOT
- Letting
- 01 JUL 2025
- Pay items
- 61
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ragle Construction, Inc. | $4,922,876 | Low | -24% |
| 2 | Gibson & Associates, Inc. | $5,477,163 | +11% | -15% |
| 3 | Built Right Construction of Oklahoma, LLC | $5,948,520 | +21% | -8.0% |
| 4 | Silver Creek Construction, Inc. | $6,511,605 | +32% | +1.0% |
| 5 | Grey Sky Construction LLC | $7,009,921 | +42% | +8.0% |
| 6 | Indus Road & Bridge, Inc. | $9,542,962 | +94% | +48% |
Engineer's estimate: $6,466,326.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ragle Construction, Inc. | 2. Gibson & Associates, Inc. | 3. Built Right Construction of Oklahoma, LLC | 4. Silver Creek Construction, Inc. | 5. Grey Sky Construction LLC | 6. Indus Road & Bridge, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7004) | CY | 96.21 | $195.00 | $332.20 | $25.00 | $300.00 | $500.00 | $140.00 | |
| 2 | Removing concrete (riprap) (104-7006) | SY | 1.50 | $130.00 | $652.30 | $25.00 | $75.00 | $1,000.00 | $140.00 | |
| 3 | Compost manuf topsoil (4") (161-7002) | SY | 2,195 | $1.75 | $6.60 | $5.00 | $4.00 | $10.00 | $3.20 | |
| 4 | Block sodding (162-7002) | SY | 2,195 | $12.00 | $7.43 | $9.00 | $7.00 | $10.00 | $7.00 | |
| 5 | Vegetative watering (168-7001) | TGL | 328 | $10.00 | $80.00 | $250.00 | $99.00 | $50.00 | $0.10 | |
| 6 | Full-depth rep(BR appr slab)(9"-13") (361-7047) | CY | 9.20 | $850.00 | $2,450.00 | $1,000.00 | $1,800.00 | $2,400.00 | $5,000.00 | $2,800.00 |
| 7 | Flowable backfill (401-7001) | CY | 2 | $700.00 | $608.30 | $500.00 | $650.00 | $650.00 | $450.00 | |
| 8 | Penetrating concrete surface treatment (428-7001) | SY | 11,653 | $4.50 | $12.25 | $10.00 | $17.00 | $15.00 | $44.45 | |
| 9 | Concrete structure repair(rapid deck rep(PRT DPT) (429-7004) | SF | 378 | $85.00 | $45.00 | $91.00 | $325.00 | $200.00 | $500.00 | $110.00 |
| 10 | Concrete structure repair(rapid deck rep(full DPT)) (429-7006) | SF | 38 | $165.00 | $400.00 | $400.00 | $900.00 | $500.00 | $180.00 | |
| 11 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 2,013 | $245.00 | $150.00 | $187.00 | $275.00 | $249.00 | $265.00 | $250.00 |
| 12 | Riprap (concrete)(4 in) (432-7001) | CY | 2 | $1,180.00 | $1,320.00 | $2,500.00 | $1,500.00 | $650.00 | $2,800.00 | |
| 13 | Riprap (mow strip)(4 in) (432-7013) | CY | 77.01 | $680.00 | $797.50 | $850.00 | $975.00 | $550.00 | $865.00 | |
| 14 | Riprap (stone protection)(24 in) (432-7045) | CY | 105 | $215.00 | $301.40 | $350.00 | $450.00 | $250.00 | $310.00 | |
| 15 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 168 | $35.00 | $35.00 | $16.50 | $65.00 | $64.00 | $100.00 | $56.00 |
| 16 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 544 | $30.00 | $40.00 | $33.00 | $65.00 | $42.00 | $100.00 | $65.00 |
| 17 | Cleaning and sealing joints (foam) (438-7010) | LF | 971 | $55.00 | $104.50 | $140.00 | $100.00 | $500.00 | $155.00 | |
| 18 | Cleaning & sealing existing joint (SEJ) (438-7013) | LF | 76 | $100.00 | $121.00 | $65.00 | $200.00 | $100.00 | $118.00 | |
| 19 | Concrete overlay (2 in) (439-7002) | SY | 3,263 | $100.00 | $125.00 | $165.00 | $100.00 | $45.00 | $88.00 | |
| 20 | Polyester polymer concrete overlay (3/4") (439-7015) | SY | 8,430 | $150.00 | $107.00 | $108.00 | $130.00 | $135.00 | $130.00 | $208.00 |
| 21 | Spot clean & paint existing structure(special protection sys) (446-7019) | LS | 1 | $1,507,440 | $1,475,000 | $1,381,820 | $1,300,000 | $1,400,000 | $1,500,000 | $1,751,136 |
| 22 | Retrofit rail (type T402) (451-7012) | LF | 72 | $515.00 | $1,250.00 | $150.00 | $220.00 | $350.00 | $750.00 | |
| 23 | Milling concrete slab (1 in) (483-7003) | SY | 3,263 | $14.50 | $21.73 | $20.00 | $26.00 | $25.00 | $15.00 | |
| 24 | Hydro-demolition (1 in) (483-7008) | SY | 3,263 | $90.00 | $125.00 | $140.00 | $63.00 | $140.00 | $170.00 | |
| 25 | Raising existing struct (495-7002) | EACH | 1 | $17,500 | $37,000 | $50,000 | $175,000 | $145,000 | $250,000 | |
| 26 | Adjust steel shoes (499-7001) | EACH | 1 | $18,500 | $15,500 | $5,000.00 | $18,000 | $16,500 | $25,000 | |
| 27 | Mobilization (500-7001) | LS | 1 | $650,000 | $490,000 | $420,000 | $500,000 | $650,000 | $700,000 | $950,000 |
| 28 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $55,000 | $30,333 | $24,700 | $4,000.00 | $40,000 | $15,000 | $165,000 |
| 29 | Portable changeable message sign (503-7002) | EACH | 5 | $20,000 | $15,000 | $15,500 | $4,000.00 | $25,000 | $20,000 | $40,000 |
| 30 | TMA (stationary) (505-7001) | DAY | 400 | $225.00 | $100.00 | $160.00 | $300.00 | $500.00 | $250.00 | $260.00 |
| 31 | TMA (mobile operation) (505-7003) | DAY | 54 | $225.00 | $100.00 | $160.00 | $350.00 | $1,000.00 | $550.00 | $740.00 |
| 32 | Temporary sediment control fence (install) (506-7039) | LF | 3,500 | $3.60 | $4.40 | $7.00 | $6.00 | $4.00 | $3.70 | |
| 33 | Temporary sediment control fence (remove) (506-7041) | LF | 3,500 | $1.25 | $1.10 | $2.00 | $1.25 | $2.00 | $1.30 | |
| 34 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 2,500 | $6.50 | $8.80 | $20.00 | $10.00 | $18.00 | $6.60 | |
| 35 | Biodegradable erosion control logs (remove) (506-7046) | LF | 2,500 | $1.25 | $1.10 | $5.00 | $1.25 | $9.00 | $1.30 | |
| 36 | Metal W-beam guard fence (timber post) (540-7001) | LF | 1,518.75 | $24.00 | $26.40 | $30.00 | $30.00 | $30.00 | $35.00 | |
| 37 | Metal W-beam guard fence (steel post) (540-7002) | LF | 262.50 | $30.00 | $33.00 | $36.00 | $40.00 | $50.00 | $44.00 | |
| 38 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 16 | $2,000.00 | $2,200.00 | $3,200.00 | $2,600.00 | $1,850.00 | $2,400.00 | |
| 39 | Downstream anchor terminal section (540-7015) | EACH | 1 | $1,200.00 | $1,320.00 | $2,000.00 | $1,900.00 | $1,850.00 | $1,500.00 | |
| 40 | Remove metal beam guard fence (542-7001) | LF | 2,100 | $5.00 | $5.50 | $7.00 | $4.00 | $3.00 | $7.00 | |
| 41 | Remove terminal anchor section (542-7002) | EACH | 3 | $250.00 | $275.00 | $500.00 | $550.00 | $500.00 | $370.00 | |
| 42 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 43 | $25.00 | $27.50 | $35.00 | $28.00 | $100.00 | $35.00 | |
| 43 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 551 | $0.50 | $2.00 | $1.38 | $2.50 | $1.25 | $3.00 | $4.20 |
| 44 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 1,650 | $0.50 | $2.00 | $1.38 | $2.50 | $1.25 | $3.00 | $4.20 |
| 45 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 1,650 | $0.50 | $2.00 | $1.38 | $2.50 | $1.25 | $3.00 | $4.20 |
| 46 | Pavement sler 6" (666-7347) | LF | 14,891 | $0.50 | $0.30 | $0.77 | $0.50 | $0.70 | $3.00 | $0.50 |
| 47 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 551 | $0.50 | $3.00 | $1.93 | $4.00 | $1.75 | $3.00 | $6.70 |
| 48 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 7,170 | $0.50 | $1.50 | $1.65 | $2.00 | $1.50 | $3.00 | $3.30 |
| 49 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 7,055 | $0.50 | $1.50 | $1.65 | $2.00 | $1.50 | $3.00 | $3.30 |
| 50 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 44 | $5.00 | $13.00 | $55.00 | $17.00 | $50.00 | $6.00 | $28.00 |
| 51 | Eliminating existing PM & markers (4") (677-7001) | LF | 8,281 | $1.00 | $2.75 | $1.30 | $2.50 | $2.00 | $2.20 | |
| 52 | Pavement surface preparation for marking (6") (678-7002) | LF | 14,891 | $0.50 | $0.50 | $0.66 | $1.00 | $0.60 | $3.00 | $1.10 |
| 53 | Longt crack cleaning and sealing (CRCP) (713-7005) | LF | 30 | $10.00 | $100.00 | $8.00 | $20.00 | $200.00 | $74.00 | |
| 54 | Tree trimming / brush removal (752-7001) | MI | 0.90 | $5,000.00 | $12,000 | $5,000.00 | $15,000 | $10,000 | $17,700 | |
| 55 | Concrete rail repair (in-kind) (778-7001) | LF | 45 | $1,250.00 | $400.00 | $550.00 | $350.00 | $210.00 | $350.00 | $1,000.00 |
| 56 | CNC crack repair (discrete)(gravity) (780-7001) | LF | 1,125 | $45.00 | $25.00 | $16.50 | $25.00 | $50.00 | $100.00 | $50.00 |
| 57 | CNC crack repair (discrete)(inject) (780-7002) | LF | 57 | $120.00 | $25.00 | $150.00 | $125.00 | $210.00 | $100.00 | $180.00 |
| 58 | Rep steel bridge MBR (weld repair) (784-7022) | EACH | 2 | $2,500.00 | $1,500.00 | $3,000.00 | $10,000 | $15,000 | $12,500 | |
| 59 | Bridge joint repair (armor) (785-7004) | LF | 75 | $60.00 | $175.00 | $915.00 | $750.00 | $1,000.00 | $1,000.00 | $1,200.00 |
| 60 | Bridge joint replacement (SEJ) (785-7011) | LF | 111 | $400.00 | $917.00 | $650.00 | $1,200.00 | $1,000.00 | $500.00 | |
| 61 | Bent cap/abutment cap cleaning (7001-7002) | EACH | 8 | $2,000.00 | $1,200.00 | $1,100.00 | $1,500.00 | $2,000.00 | $6,500.00 | $3,600.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 1, 2025. Compiled by Mirage Metrics.