TxDOT contract A00206315 bid tabulation
Construct Pedestrian Infrastructure, Various (Various locations in City of Coleman to .). Let by Texas DOT on June 3, 2026, Coleman, Brownwood District. 4 bids received; low bid $2,189,861 by 3LW Civil LLC, -14% against the engineer's estimate of $2,544,721.
- Owner
- Texas DOT
- Letting
- 03 JUN 2026
- Pay items
- 97
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | 3LW Civil LLC | $2,189,861 | Low | -14% |
| 2 | Delgado'S Contractors, LLC | $2,365,925 | +8.0% | -7.0% |
| 3 | Ti-Zack Concrete, LLC | $2,696,301 | +23% | +6.0% |
| 4 | Project Allied Resources, LLC | $3,040,500 | +39% | +19% |
Engineer's estimate: $2,544,721.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. 3LW Civil LLC | 2. Delgado'S Contractors, LLC | 3. Ti-Zack Concrete, LLC | 4. Project Allied Resources, LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparation row (tree remove) (0"-12" diameter) (100-7003) | EACH | 2 | $725.00 | $1,000.00 | $250.00 | $660.00 | $2,850.00 |
| 2 | Tree protection (install) (100-7013) | EACH | 14 | $275.00 | $0.10 | $350.00 | $121.00 | $1,950.00 |
| 3 | Tree protection (remove) (100-7015) | EACH | 14 | $60.00 | $0.10 | $75.00 | $55.00 | $977.00 |
| 4 | Removing concrete (medians) (104-7008) | SY | 365 | $40.00 | $35.00 | $15.00 | $21.86 | $24.10 |
| 5 | Removing concrete (pavers) (104-7010) | SY | 360 | $50.00 | $68.41 | $15.00 | $22.17 | $17.00 |
| 6 | Removing concrete (driveways) (104-7011) | SY | 207 | $20.00 | $30.00 | $20.00 | $38.55 | $41.50 |
| 7 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 221 | $22.00 | $30.00 | $20.00 | $36.11 | $21.70 |
| 8 | Removing concrete (curb) (104-7016) | LF | 168 | $16.00 | $24.00 | $15.00 | $9.50 | $7.20 |
| 9 | Removing concrete (curb & gutter) (104-7017) | LF | 890 | $14.00 | $24.00 | $14.00 | $8.97 | $10.70 |
| 10 | Removing concrete (retaining walls) (104-7025) | SY | 5 | $105.00 | $75.00 | $25.00 | $31.92 | $66.00 |
| 11 | Remove (4"-8") TRT/untrt base & asphalt pavement (105-7004) | SY | 163 | $15.00 | $12.50 | $15.00 | $48.96 | $11.70 |
| 12 | Excavation (special) (110-7003) | CY | 25 | $40.00 | $115.00 | $55.00 | $63.84 | $102.00 |
| 13 | Embankment (final)(OC)(type C1) (132-7007) | CY | 30 | $55.00 | $100.00 | $60.00 | $266.00 | $81.00 |
| 14 | Furn & place topsoil (4") (160-7002) | SY | 2,985 | $5.00 | $4.25 | $7.00 | $2.67 | $3.66 |
| 15 | Block sodding (162-7002) | SY | 2,985 | $9.00 | $9.20 | $8.50 | $7.70 | $11.00 |
| 16 | Vegetative watering (168-7001) | TGL | 67 | $100.00 | $150.00 | $50.00 | $1.10 | $94.00 |
| 17 | Fog seal (CSS-1H) (315-7004) | GAL | 1,796 | $10.00 | $9.20 | $10.00 | $8.80 | $8.80 |
| 18 | Cem stabil BKFL (400-7010) | CY | 19 | $288.00 | $400.00 | $200.00 | $286.00 | $610.00 |
| 19 | Flowable backfill (401-7001) | CY | 24 | $474.00 | $400.00 | $200.00 | $302.50 | $702.00 |
| 20 | Temporary special shoring (403-7001) | SF | 31 | $40.00 | $50.00 | $25.00 | $165.00 | $87.00 |
| 21 | Drilled shaft (30 in) (416-7005) | LF | 248 | $350.00 | $250.00 | $300.00 | $327.69 | $328.00 |
| 22 | Drilled shaft (traffic signal pole) (24 in) (416-7042) | LF | 12 | $350.00 | $250.00 | $300.00 | $294.42 | $294.00 |
| 23 | Class A concrete (miscellaneous) (420-7002) | CY | 6 | $735.00 | $1,000.00 | $1,000.00 | $821.58 | $5,070.00 |
| 24 | Retaining wall (cast-in-place) (423-7016) | SF | 32 | $200.00 | $105.29 | $90.00 | $72.53 | $159.00 |
| 25 | Riprap (concrete)(5 in) (432-7002) | CY | 6 | $965.00 | $888.55 | $650.00 | $792.00 | $1,170.00 |
| 26 | Riprap (stone common)(dry)(6 in) (432-7029) | CY | 12 | $400.00 | $500.00 | $295.00 | $385.00 | $291.00 |
| 27 | STR steel (miscellaneous non-bridge) (442-7007) | LB | 1,584 | $20.00 | $32.81 | $25.00 | $1.10 | $17.40 |
| 28 | Rail (handrail)(type A) (450-7058) | LF | 170 | $130.00 | $157.95 | $110.00 | $154.00 | $209.00 |
| 29 | Waterproofing (type 10) (458-7007) | SY | 12 | $150.00 | $65.89 | $75.00 | $330.00 | $167.00 |
| 30 | Concrete box culvert (4 FT X 2 FT) (462-7003) | LF | 14 | $750.00 | $716.03 | $400.00 | $1,063.70 | $775.00 |
| 31 | Concrete box culvert (7 FT X 6 FT) (462-7018) | LF | 16 | $1,100.00 | $1,385.02 | $700.00 | $2,323.20 | $1,730.00 |
| 32 | Concrete box culvert (8 FT X 3 FT) (462-7020) | LF | 12 | $1,000.00 | $1,269.87 | $900.00 | $2,153.80 | $1,480.00 |
| 33 | Wingwall (PW - 1) (HW=5 FT) (466-7175) | EACH | 1 | $24,000 | $19,046 | $12,500 | $34,320 | $23,700 |
| 34 | Wingwall (SW - 0) (HW=3 FT) (466-7202) | EACH | 1 | $9,200.00 | $6,826.00 | $5,000.00 | $6,050.00 | $8,730.00 |
| 35 | Wingwall (SW - 0) (HW=7 FT) (466-7206) | EACH | 1 | $16,000 | $14,705 | $10,000 | $33,000 | $25,200 |
| 36 | Clean existing culverts (480-7001) | EACH | 3 | $5,000.00 | $1,250.00 | $2,000.00 | $605.00 | $2,230.00 |
| 37 | Removing structure (headwall) (496-7006) | EACH | 2 | $2,300.00 | $1,500.00 | $500.00 | $1,100.00 | $1,710.00 |
| 38 | Removing structure (pipe) (496-7007) | LF | 13 | $30.00 | $50.00 | $20.00 | $110.00 | $19.40 |
| 39 | Removing structure (ret wall) (496-7019) | LF | 40 | $69.00 | $100.00 | $50.00 | $66.00 | $46.00 |
| 40 | Mobilization (500-7001) | LS | 1 | $230,000 | $105,525 | $145,000 | $247,289 | $335,000 |
| 41 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $6,500.00 | $5,203.13 | $2,900.00 | $3,850.00 | $4,340.00 |
| 42 | TMA (stationary) (505-7001) | DAY | 152 | $200.00 | $135.00 | $350.00 | $0.11 | $201.00 |
| 43 | TMA (mobile operation) (505-7003) | DAY | 2 | $400.00 | $550.00 | $350.00 | $0.11 | $229.00 |
| 44 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 4,850 | $5.00 | $0.01 | $6.00 | $0.01 | $10.30 |
| 45 | Biodegradable erosion control logs (remove) (506-7046) | LF | 4,850 | $1.25 | $0.01 | $1.50 | $0.01 | $2.88 |
| 46 | Concrete curb (type II) (529-7002) | LF | 2,479 | $38.00 | $32.12 | $45.00 | $60.03 | $19.50 |
| 47 | Concrete curb & gutter (type II) (529-7009) | LF | 1,653 | $40.00 | $50.04 | $45.00 | $60.03 | $41.40 |
| 48 | Concrete C&G (valley gutter) (529-7019) | LF | 2,866 | $55.00 | $55.00 | $50.00 | $71.78 | $50.00 |
| 49 | Intersections (concrete) (530-7001) | SY | 1,100 | $167.00 | $139.59 | $115.00 | $144.68 | $181.00 |
| 50 | Driveways (concrete) (530-7006) | SY | 780 | $127.00 | $122.56 | $115.00 | $142.46 | $159.00 |
| 51 | Concrete sidewalks (4") (531-7001) | SY | 4,342 | $85.00 | $78.49 | $85.00 | $113.88 | $113.00 |
| 52 | Concrete sidewalks (6") (531-7003) | SY | 170 | $125.00 | $99.75 | $115.00 | $142.14 | $170.00 |
| 53 | Curb ramps (type 1) (531-7015) | SY | 340 | $186.00 | $104.49 | $200.00 | $137.28 | $294.00 |
| 54 | Curb ramps (type 3) (531-7017) | SY | 85 | $235.00 | $122.80 | $200.00 | $137.28 | $294.00 |
| 55 | Curb ramps (type 7) (531-7020) | SY | 298 | $185.00 | $116.97 | $220.00 | $137.28 | $294.00 |
| 56 | Curb ramps (type 10) (531-7021) | SY | 143 | $190.00 | $109.58 | $200.00 | $137.28 | $294.00 |
| 57 | Curb ramps (type 21) (531-7023) | SY | 160 | $310.00 | $109.82 | $200.00 | $137.28 | $294.00 |
| 58 | Chain link fence (install) (4') (550-7003) | LF | 35 | $50.00 | $65.00 | $30.00 | $49.50 | $89.00 |
| 59 | Chain link fence (remove) (550-7007) | LF | 35 | $17.00 | $10.00 | $5.00 | $11.00 | $11.90 |
| 60 | Mailbox install-S (TWG-post) type 2 (560-7002) | EACH | 4 | $380.00 | $462.30 | $500.00 | $495.00 | $516.00 |
| 61 | Relocate RD IL asm (trans-base) (610-7004) | EACH | 16 | $3,500.00 | $2,436.04 | $1,354.39 | $1,354.39 | $1,350.00 |
| 62 | Remove RD IL asm (shoe-base) (610-7007) | EACH | 7 | $900.00 | $557.14 | $1,185.36 | $1,185.36 | $1,190.00 |
| 63 | Remove RD IL asm (trans-base) (610-7009) | EACH | 3 | $900.00 | $1,300.00 | $1,238.60 | $1,238.60 | $1,240.00 |
| 64 | In RD IL (type SA) 30S-4 (250W EQ) LED (610-7062) | EACH | 12 | $7,000.00 | $4,332.90 | $5,063.85 | $5,063.85 | $5,060.00 |
| 65 | In RD IL (type SA) 30S-4-4 (250W EQ) LED (610-7063) | EACH | 7 | $7,000.00 | $6,601.21 | $6,128.65 | $6,128.65 | $6,130.00 |
| 66 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 4,980 | $12.00 | $11.44 | $22.11 | $22.11 | $22.10 |
| 67 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 85 | $30.00 | $12.54 | $41.47 | $41.47 | $41.50 |
| 68 | Conduit (PVC) (schedule 40) (3") (bore) (618-7037) | LF | 140 | $75.00 | $39.10 | $49.78 | $49.78 | $49.80 |
| 69 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 975 | $42.00 | $32.20 | $33.88 | $33.94 | $33.90 |
| 70 | Electrical conductor (no.8) bare (620-7007) | LF | 5,435 | $1.90 | $3.06 | $3.08 | $3.08 | $3.08 |
| 71 | Electrical conductor (no.8) insulated (620-7008) | LF | 10,870 | $2.75 | $2.12 | $3.19 | $3.19 | $3.19 |
| 72 | Electrical conductor (no.6) bare (620-7009) | LF | 225 | $3.00 | $5.50 | $3.30 | $3.30 | $3.30 |
| 73 | Ground box type B (122322) (624-7003) | EACH | 14 | $1,200.00 | $1,987.47 | $2,225.30 | $2,225.30 | $2,230.00 |
| 74 | Ground box type B (122322)W/apron (624-7004) | EACH | 27 | $1,300.00 | $1,987.47 | $2,624.60 | $2,624.60 | $2,620.00 |
| 75 | Ground box type C (162911) (624-7005) | EACH | 3 | $1,600.00 | $1,045.73 | $1,826.00 | $1,826.00 | $1,830.00 |
| 76 | Remove ground box (624-7013) | EACH | 2 | $450.00 | $487.50 | $1,959.10 | $1,959.10 | $1,960.00 |
| 77 | Relocate electrical services (628-7001) | EACH | 1 | $5,500.00 | $3,900.00 | $1,492.79 | $1,493.25 | $4,910.00 |
| 78 | Elc SRV type A 120/240 060(NS)SS(E)PS(U) (628-7008) | EACH | 3 | $11,000 | $8,500.00 | $11,748 | $11,748 | $11,700 |
| 79 | Aluminum signs (type A) (636-7001) | SF | 2 | $50.00 | $117.30 | $33.22 | $33.22 | $60.00 |
| 80 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 14 | $780.00 | $1,191.40 | $679.50 | $495.00 | $1,510.00 |
| 81 | Remove SM RD SN sup&AM (644-7073) | EACH | 14 | $100.00 | $125.00 | $120.00 | $55.00 | $360.00 |
| 82 | Reflectorized pavement marking type I (W)6"(lane drop)(100MIL) (666-7012) | LF | 3,921 | $1.40 | $2.75 | $2.64 | $2.64 | $2.64 |
| 83 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 1,910 | $1.50 | $3.30 | $1.49 | $1.49 | $1.49 |
| 84 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 1,619 | $9.50 | $10.45 | $16.23 | $16.23 | $16.20 |
| 85 | Eliminating existing PM & markers (6") (677-7002) | LF | 3,105 | $1.15 | $1.10 | $0.90 | $0.90 | $0.90 |
| 86 | Eliminating existing PM & markers (12") (677-7006) | LF | 1,945 | $2.00 | $2.20 | $3.69 | $3.69 | $3.69 |
| 87 | Eliminating existing PM & markers (double arrow) (677-7010) | EACH | 1 | $95.00 | $93.50 | $138.60 | $138.60 | $139.00 |
| 88 | Pavement surface preparation for marking (6") (678-7002) | LF | 3,921 | $0.50 | $0.11 | $0.07 | $0.07 | $0.07 |
| 89 | Pavement surface preparation for marking (8") (678-7004) | LF | 1,910 | $0.75 | $0.11 | $0.13 | $0.13 | $0.13 |
| 90 | Pavement surface preparation for marking (24") (678-7008) | LF | 1,619 | $1.10 | $1.10 | $1.32 | $1.32 | $1.32 |
| 91 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 2 | $1,000.00 | $1,781.00 | $1,520.00 | $1,527.90 | $1,530.00 |
| 92 | Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007) | LF | 430 | $3.50 | $6.96 | $3.19 | $3.19 | $3.19 |
| 93 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 430 | $2.50 | $7.48 | $3.52 | $3.52 | $3.52 |
| 94 | Pedestrian pole assembly (687-7001) | EACH | 2 | $4,000.00 | $1,521.00 | $1,332.87 | $1,332.87 | $1,330.00 |
| 95 | Pedestrian detect push button (APS) (688-7001) | EACH | 2 | $1,450.00 | $1,833.00 | $1,707.20 | $1,707.20 | $1,710.00 |
| 96 | Remove foundation (690-7196) | EACH | 26 | $500.00 | $1,250.00 | $1,122.83 | $1,122.83 | $1,120.00 |
| 97 | Subsurface util locate (non-paved area) (5061-7001) | EACH | 20 | $300.00 | $550.00 | $500.00 | $110.00 | $1,120.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 3, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.