Project Allied Resources, LLC: TxDOT bid record
Project Allied Resources, LLC submitted 51 bids on Texas DOT contracts in the data, from 06 FEB 2020 to 03 JUN 2026, and was the low bidder on 7 of them (14%). When it was not low, its total sat a median +25% above the low bid.
- Owner
- Texas DOT
- Low bid volume
- $12,805,278
- Latest bid
- 03 JUN 2026
- Data through
- 19 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 10 | 1 | 10% |
| 2021 | 13 | 2 | 15% |
| 2022 | 10 | 3 | 30% |
| 2023 | 1 | 1 | 100% |
| 2024 | 13 | 0 | 0% |
| 2025 | 3 | 0 | 0% |
| 2026 | 1 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Beaumont District | 9 | 3 | 33% |
| Waco District | 7 | 1 | 14% |
| Brownwood District | 6 | 0 | 0% |
| Yoakum District | 5 | 1 | 20% |
| Bryan District | 5 | 0 | 0% |
| Paris District | 5 | 0 | 0% |
| Abilene District | 4 | 1 | 25% |
| Lufkin District | 2 | 1 | 50% |
| Fort Worth District | 2 | 0 | 0% |
| Atlanta District | 1 | 0 | 0% |
| Dallas District | 1 | 0 | 0% |
| Corpus Christi District | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| TMA (stationary) | 505-7001 | DAY | 33 | 10 (30%) | $202.00 | $230.00 |
| Preparing row | 100-7002 | STA | 31 | 8 (26%) | $2,860.00 | $2,750.00 |
| Removing concrete (driveways) | 104-7011 | SY | 15 | 7 (47%) | $17.00 | $21.00 |
| Furnishing and placing topsoil (4") | 160-6003 | SY | 14 | 7 (50%) | $1.95 | $3.00 |
| Vegetative watering | 168-7001 | MG | 41 | 5 (12%) | $70.00 | $29.97 |
| Excavation (roadway) | 110-7001 | CY | 32 | 5 (16%) | $27.35 | $20.00 |
| Broadcast seed (temporary) (cool) | 164-6011 | SY | 11 | 5 (45%) | $0.76 | $0.30 |
| Portable changeable message sign | 503-7002 | EACH | 19 | 4 (21%) | $9,130.00 | $10,000 |
| Broadcast seed (temporary) (warm) | 164-6009 | SY | 11 | 4 (36%) | $0.99 | $0.30 |
| Driveways (ACP) | 530-7010 | SY | 9 | 4 (44%) | $72.00 | $60.00 |
| Barricades, signs and traffic handling | 502-7001 | MO | 51 | 3 (6%) | $3,840.00 | $5,000.00 |
| Install delineator assembly (D-SW)SZ (BRF)CTB (BI) | 658-6014 | EACH | 20 | 3 (15%) | $32.55 | $25.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Hodges and Son Construction Company, Inc. | 19 | 13 of 19 |
| FNH Construction, LLC | 19 | 4 of 19 |
| Encino Landscape, Inc. | 16 | 7 of 16 |
| Ti-Zack Concrete, LLC | 14 | 8 of 14 |
| Knife River Corporation - South | 13 | 12 of 13 |
| SJ&J Construction, LLC | 9 | 3 of 9 |
| Talbert Companies LLC | 8 | 7 of 8 |
| Texas Materials Group, Inc. | 7 | 3 of 7 |
| Fuqua Construction Co., Inc. | 6 | 4 of 6 |
| Stateline Construction, LLC | 6 | 4 of 6 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 03 JUN 2026 | A00206315 | Brownwood District | Construct Pedestrian Infrastructure, Various (Various locations in City of Coleman to .) | 4 of 4 | $3,040,500 | +39% |
| 04 MAR 2025 | A00133339 | Fort Worth District | Bridge Replacement, COUNTY ROAD 270 (CR 270 AT TRIBUTARY TO NORTH BOSQUE to .) | 5 of 8 | $1,529,611 | +8.0% |
| 06 FEB 2025 | A00138685 | Wichita Falls District | Bridge Replacement, SH 25 (SH 25 to At Middle Fork Little Wichita River) | 2 of 7 | $6,619,747 | +2.0% |
| 08 JAN 2025 | A00190132 | Beaumont District | Bridge Replacement, COUNTY ROAD 139 (CR 139 @ BIG SANDY CREEK to EXISTING (STR#201220AA0291002)) | 8 of 8 | $2,275,338 | +15% |
| 03 DEC 2024 | A00194464 | Brownwood District | Bridge Replacement, COUNTY ROAD 508 (CR 508 at Draw to .) | 8 of 9 | $2,066,790 | +41% |
| 06 NOV 2024 | A00197743 | Paris District | Construct Pedestrian Infrastructure, BU 271B (18th SE to 34th SE) | 3 of 9 | $2,357,714 | +6.0% |
| 10 JUL 2024 | 07243229 | San Angelo District | CS Construct pedestrian infrastructure from VARIOUS LOCATIONS IN ELDORADO, TEXA | 3 of 8 | $886,198 | +15% |
| 09 JUL 2024 | 07243025 | Childress District | CR Bridge replacement and approaches from @ BEAVER CREEK | 5 of 6 | $1,076,566 | +54% |
| 06 JUN 2024 | 06243237 | Abilene District | SH 176 Bridge replacement from AT SULPHUR SPRINGS DRAW | 4 of 5 | $3,131,365 | +31% |
| 03 MAY 2024 | 05243232 | Beaumont District | CR Bridge replacement from W.PINESHADOWS @ CLEMMONS GULLY to STR# 201010AA1065001 | 3 of 3 | $4,665,504 | +22% |
| 04 APR 2024 | 04243013 | Abilene District | US 277 Bridge replacement from US 277 NB to PAINT CREEK | 4 of 6 | $5,740,155 | +23% |
| 04 APR 2024 | 04243024 | Waco District | SH 164 Bicycle and pedestrian improvements from N. DOUGLAS ST. to N. FRONT ST. | 6 of 6 | $1,893,267 | +31% |
| 06 MAR 2024 | 03243211 | Brownwood District | CR Bridge replacement from CR 260 AT SOUTH LEON RIVER | 2 of 3 | $4,738,006 | +24% |
| 05 MAR 2024 | 03243036 | Fort Worth District | CS Construct pedestrian infrastructure from ON BAILEY RANCH FROM HS to FM 1187 | 9 of 10 | $659,417 | +41% |
| 02 FEB 2024 | 02243242 | Bryan District | FM 46 Bridge replacement from AT CEDAR CREEK | 5 of 9 | $2,106,646 | +20% |
| 01 FEB 2024 | 02243034 | Paris District | CR Bridge replacement from AT ELBA CREEK to , ETC. | 6 of 7 | $2,040,560 | +28% |
| 05 JAN 2024 | 01243227 | Abilene District | FM 576 Bridge replacement from FM 576 to AT DEEP CREEK | 2 of 4 | $2,785,968 | +15% |
| 02 JUN 2023 | 06233224 | Abilene District | US 283 Bridge replacement from @ CLEAR CREEK | 1 of 3 | $3,377,698 | Low, 4.0% under the second |
| 01 DEC 2022 | 12223026 | Waco District | CR Bridge replacement from CR 274 @ CLEAR CREEK to (MAP #029) | 5 of 5 | $967,361 | +44% |
| 02 NOV 2022 | 11223017 | Beaumont District | VA Construct pedestrian infrastructure from ON FM 2799 FROM MAIN ST. to PARK LANE | 2 of 4 | $1,462,429 | +5.0% |
| 02 NOV 2022 | 11223021 | Waco District | CR Bridge replacement from CR 118 @ GARY CREEK to (MAP #007) | 3 of 4 | $1,080,121 | +35% |
| 07 SEP 2022 | 09223023 | Yoakum District | VA Construct pedestrian infrastructure from VARIOUS LOCATION IN CITY OF WHARTON | 4 of 4 | $839,920 | +26% |
| 30 JUN 2022 | 06223628 | Beaumont District | FM 364 Hazard elimination & safety from 300' N OF SPURLOCK, SOUTH to SH 105 | 3 of 3 | $1,442,474 | +66% |
| 29 JUN 2022 | 06223436 | Beaumont District | CR Bridge replacement from CR 101 AT FLAT CYPRESS CREEK to (STR 201010AA0101001) | 1 of 3 | $937,939 | Low, 6.0% under the second |
| 07 APR 2022 | 04223220 | Beaumont District | VA Construct pedestrian infrastructure from ON FM 2799 FROM MAIN ST. to PARK LANE | 1 of 3 | $1,571,675 | Low, 3.0% under the second |
How this record was read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; TxDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.