SJ&J Construction, LLC: TxDOT bid record
SJ&J Construction, LLC submitted 99 bids on Texas DOT contracts in the data, from 10 JAN 2020 to 03 DEC 2024, and was the low bidder on 12 of them (12%). When it was not low, its total sat a median +21% above the low bid.
- Owner
- Texas DOT
- Low bid volume
- $9,431,993
- Latest bid
- 03 DEC 2024
- Data through
- 19 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 42 | 3 | 7% |
| 2021 | 37 | 8 | 22% |
| 2022 | 12 | 1 | 8% |
| 2023 | 7 | 0 | 0% |
| 2024 | 1 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Waco District | 10 | 1 | 10% |
| Tyler District | 9 | 0 | 0% |
| Austin District | 8 | 1 | 13% |
| Bryan District | 7 | 0 | 0% |
| Yoakum District | 7 | 1 | 14% |
| Corpus Christi District | 7 | 1 | 14% |
| Lufkin District | 6 | 2 | 33% |
| Dallas District | 6 | 0 | 0% |
| Fort Worth District | 5 | 0 | 0% |
| Brownwood District | 5 | 0 | 0% |
| Beaumont District | 5 | 3 | 60% |
| San Antonio District | 4 | 1 | 25% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| TMA (stationary) | 505-7001 | DAY | 83 | 47 (57%) | $100.00 | $230.00 |
| Vegetative watering | 168-7001 | MG | 51 | 27 (53%) | $10.00 | $29.97 |
| Temporary sediment control fence (remove) | 506-7041 | LF | 62 | 20 (32%) | $1.00 | $1.00 |
| Temporary sediment control fence (install) | 506-7039 | LF | 62 | 13 (21%) | $3.00 | $4.00 |
| Metal beam guard fence trans (thrie-beam) | 540-7005 | EACH | 32 | 13 (41%) | $1,700.00 | $2,140.00 |
| Preparing row | 100-7002 | STA | 28 | 13 (46%) | $1,000.00 | $2,750.00 |
| Flowable backfill | 401-7001 | CY | 26 | 13 (50%) | $210.00 | $350.00 |
| Rock filter dams (install) (type 2) | 506-7002 | LF | 16 | 10 (63%) | $18.00 | $40.00 |
| RC pipe (CL III)(24 in) | 464-7005 | LF | 21 | 9 (43%) | $96.00 | $108.13 |
| Biodegradable erosion control logs (remove) | 506-7046 | LF | 34 | 8 (24%) | $2.00 | $1.40 |
| Crash cushion attenuator (move & reset) | 545-7002 | EACH | 16 | 8 (50%) | $1,000.00 | $1,535.40 |
| Guardrail end treatment (install) | 544-7001 | EACH | 36 | 7 (19%) | $2,800.00 | $3,245.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| FNH Construction, LLC | 45 | 4 of 45 |
| Talbran Enterprises LLC | 22 | 15 of 22 |
| 3LW Civil LLC | 20 | 14 of 20 |
| Encino Landscape, Inc. | 18 | 10 of 18 |
| Beck-Reit & Sons, LTD. | 18 | 13 of 18 |
| Highway 19 Construction LLC | 15 | 9 of 15 |
| Altus Construction LLC | 15 | 5 of 15 |
| Dbi Services, LLC | 14 | 7 of 14 |
| East Texas Bridge, Inc. | 12 | 2 of 12 |
| Cross Plus Construction, LLC | 11 | 9 of 11 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 03 DEC 2024 | A00209528 | Pharr District | Bridge Maintenance, SH 336 (SH 336 @ HACKNEY LAKE FLOODWAY to 3.50 MI S OF US 83 NBI#211090062101007) | 6 of 7 | $62,850 | +228% |
| 28 JUN 2023 | 06233626 | Yoakum District | BS 35-H Drainage improvements from AT 12TH STREET | 2 of 2 | $3,680,283 | +15% |
| 27 JUN 2023 | 06233454 | Corpus Christi District | US 181 Bridge maintenance from NB AND SB FRONTAGE ROADS to AT POESTA CREEK | 4 of 8 | $221,320 | +55% |
| 02 JUN 2023 | 06233235 | Tyler District | PW State park improvements from VARIOUS LOCATION WITHIN to OLD SABINE BOTTOM WMA | 5 of 8 | $1,620,243 | +89% |
| 02 JUN 2023 | 06234211 | Tyler District | FM2422 Culvert repair from VARIOUS ROADWAYS IN to THE TYLER DISTRICT | 7 of 9 | $497,097 | +33% |
| 04 MAY 2023 | 05234003 | Austin District | SL0111 Bridge repair from FM 969 to AT WALNUT CREEK | 3 of 6 | $488,005 | +20% |
| 07 MAR 2023 | 03234017 | Dallas District | US0077 Bridge preventative maintenance from AT CHAMBERS CREEK to ON US 77 | 7 of 9 | $775,600 | +52% |
| 01 FEB 2023 | 02234037 | Bryan District | SH0030 Metal beam guard fence repair from VARIOUS to VARIOUS | 3 of 4 | $659,675 | +20% |
| 01 DEC 2022 | 12223025 | Corpus Christi District | VA Construct pedestrian infrastructure from AT VARIOUS LOCATIONS IN KINGSVILLE to ON KENNEDY, LOTT, 17TH, 19TH, AND 2 | 5 of 6 | $1,102,742 | +38% |
| 08 SEP 2022 | 09224203 | Laredo District | IH0035 Tic public water system ground storage from LAREDO TRAVEL INFORMATION CENTER to LAREDO TRAVEL INFORMATION CENTER | 2 of 2 | $400,000 | +14% |
| 08 SEP 2022 | 09224213 | Lufkin District | US0059 Bridge preventative maintenance from WITHIN THE LUFKIN DISTRICT to VARIOUS LOCATIONS | 5 of 10 | $515,622 | +20% |
| 08 SEP 2022 | 09224220 | Waco District | SH0317 Miscellaneous concrete repair from VARIOUS LOCATIONS to ACROSS DISTRICT | 4 of 6 | $1,918,210 | +19% |
| 07 SEP 2022 | 09224024 | Lufkin District | US0059 Bridge preventative maintenance from WITHIN THE LUFKIN DISTRICT to VARIOUS LOCATIONS | 6 of 9 | $304,599 | +28% |
| 03 AUG 2022 | 08223045 | Waco District | FM 436 Hazard elimination & safety from SH 95 to BU190J | 4 of 5 | $2,368,059 | +14% |
| 29 JUN 2022 | 06223429 | Laredo District | VA State park improvements from LAKE CASA BLANCA PARK | 2 of 5 | $1,706,825 | +5.0% |
| 29 JUN 2022 | 06224432 | Wichita Falls District | FM0172 Culvert replacement from VARIOUS LOCATIONS IN ARCHER, YOUNG to AND THROCKMORTON COUNTIES | 6 of 6 | $716,155 | +43% |
| 02 JUN 2022 | 06223240 | Brownwood District | FM 101 Hazard elimination & safety from SH 112 to PHILADELPHIA ST | 4 of 6 | $516,382 | +25% |
| 07 APR 2022 | 04223228 | Corpus Christi District | IH 37 Bridge maintenance from AT INTERSECTION OF IH37/FM99 | 6 of 8 | $588,470 | +57% |
| 03 MAR 2022 | 03223019 | Lufkin District | US 59 Bridge maintenance from AT PROCELLA CREEK to AT PROCELLA CREEK | 1 of 6 | $281,620 | Low, 2.0% under the second |
| 07 JAN 2022 | 01223226 | Yoakum District | VA Bridge maintenance from AUSTIN, COLORADO, WHARTON & MATAGOR | 6 of 7 | $852,880 | +49% |
| 27 OCT 2021 | 10211107 | Lufkin District | US0287 Metal beam guard fence repair from VARIOUS LOCATION IN THE HOUSTON COU to MAINTENANCE SECTION | 1 of 3 | $219,650 | Low, 20% under the second |
| 26 OCT 2021 | 10211802 | Dallas District | FM2860 Bridge preventative maintenance from 0.30 MILE OF US 175 ON FM 2860 to AT WILLOW CREEK | 3 of 7 | $85,165 | +23% |
| 26 OCT 2021 | 10211807 | Dallas District | FM3041 Bridge preventative maintenance from AT CHAMBERS CREEK to ON FM 3041 | 3 of 8 | $165,670 | +13% |
| 26 OCT 2021 | 10211808 | Dallas District | FM0813 Bridge preventative maintenance from RED OAK CREEK to RED OAK CREEK | 4 of 5 | $186,990 | +38% |
| 26 OCT 2021 | 10212001 | Beaumont District | SH0012 Bridge repair from VARIOUS LOCATIONS to VARIOUS LOCATIONS | 1 of 4 | $135,310 | Low, 6.0% under the second |
How this record was read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; TxDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.