TxDOT contract A00190132 bid tabulation
Bridge Replacement, COUNTY ROAD 139 (CR 139 @ BIG SANDY CREEK to EXISTING (STR#201220AA0291002)). Let by Texas DOT on January 8, 2025, Jasper, Beaumont District. 8 bids received; low bid $1,980,225 by Isi Contracting, Inc., +6.2% against the engineer's estimate of $1,863,815.
- Owner
- Texas DOT
- Letting
- 08 JAN 2025
- Pay items
- 41
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Isi Contracting, Inc. | $1,980,225 | Low | +6.0% |
| 2 | Lakey, Inc. | $2,021,862 | +2.0% | +8.0% |
| 3 | Hodges and Son Construction Company, Inc. | $2,022,615 | +2.0% | +9.0% |
| 4 | STX Civil | $2,046,767 | +3.0% | +10% |
| 5 | Elite Contractors and Equipment LTD | $2,051,286 | +4.0% | +10% |
| 6 | Talbert Companies LLC | $2,122,732 | +7.0% | +14% |
| 7 | Texas Materials Group, Inc. | $2,168,088 | +9.0% | +16% |
| 8 | Project Allied Resources, LLC | $2,275,338 | +15% | +22% |
Engineer's estimate: $1,863,815.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Isi Contracting, Inc. | 2. Lakey, Inc. | 3. Hodges and Son Construction Company, Inc. | 4. STX Civil | 5. Elite Contractors and Equipment LTD | 6. Talbert Companies LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 8.20 | $8,000.00 | $18,163 | $6,961.41 | $8,500.00 | $20,000 | $10,000 | $11,000 |
| 2 | Remove (0"-4") TRT/untrt base & asphalt pavement (105-7001) | SY | 692 | $5.00 | $13.10 | $77.51 | $30.00 | $80.00 | $15.00 | $82.50 |
| 3 | Excavation (roadway) (110-7001) | CY | 313 | $30.00 | $94.00 | $28.87 | $30.00 | $15.00 | $55.00 | $34.10 |
| 4 | Excavation (channel) (110-7002) | CY | 712 | $30.00 | $26.00 | $50.31 | $30.00 | $50.00 | $50.00 | $60.50 |
| 5 | Embankment (final)(DC)(type C) (132-7006) | CY | 693 | $35.00 | $32.60 | $28.28 | $40.00 | $26.00 | $39.00 | $34.10 |
| 6 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 1,622 | $1.00 | $2.85 | $3.45 | $4.00 | $0.60 | $1.00 | $4.21 |
| 7 | Broadcast seed (temporary_warm) (164-7005) | SY | 811 | $1.40 | $2.90 | $2.61 | $2.00 | $0.60 | $1.00 | $3.19 |
| 8 | Broadcast seed (temporary_cool) (164-7006) | SY | 811 | $1.40 | $1.07 | $1.93 | $2.00 | $0.60 | $1.00 | $2.35 |
| 9 | Vegetative watering (168-7001) | TGL | 43.70 | $250.00 | $64.75 | $187.27 | $1.00 | $630.00 | $60.00 | $308.00 |
| 10 | FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176) | CY | 369 | $150.00 | $198.00 | $83.70 | $150.00 | $95.00 | $230.00 | $99.00 |
| 11 | Prime coat (AE-P) (310-7001) | GAL | 164 | $20.00 | $6.18 | $6.24 | $20.00 | $6.00 | $18.00 | $22.00 |
| 12 | D-GR HMA type D PG 64-22 (exempt) (341-7064) | TON | 68 | $200.00 | $129.32 | $449.75 | $300.00 | $445.00 | $340.00 | $495.00 |
| 13 | Tack coat (341-7082) | GAL | 82 | $15.00 | $7.20 | $25.02 | $10.00 | $25.00 | $24.00 | $27.50 |
| 14 | Cem stabil BKFL (400-7010) | CY | 46 | $220.00 | $79.00 | $300.00 | $350.00 | $130.00 | $325.00 | $247.50 |
| 15 | Drilled shaft (24 in) (416-7004) | LF | 1,326 | $300.00 | $320.00 | $317.32 | $190.00 | $327.67 | $340.00 | $264.00 |
| 16 | Class C concrete (abutment) (420-7012) | CY | 38.20 | $1,550.00 | $1,591.00 | $1,362.50 | $2,500.00 | $1,500.00 | $2,600.00 | $1,430.00 |
| 17 | Class C concrete (cap) (420-7022) | CY | 36.30 | $2,000.00 | $1,560.00 | $1,680.74 | $2,600.00 | $1,300.00 | $1,900.00 | $1,595.00 |
| 18 | Class C concrete (column) (420-7038) | CY | 12 | $1,800.00 | $4,353.00 | $1,664.43 | $2,600.00 | $1,300.00 | $3,800.00 | $1,595.00 |
| 19 | Reinforced concrete slab (422-7001) | SF | 4,960 | $32.00 | $30.00 | $29.35 | $45.00 | $25.00 | $25.00 | $28.60 |
| 20 | Approach slab (422-7013) | CY | 92 | $900.00 | $1,047.00 | $838.23 | $1,500.00 | $700.00 | $825.00 | $918.50 |
| 21 | Prestressed concrete slab beam (5SB12) (425-7017) | LF | 367.50 | $153.00 | $275.00 | $330.00 | $300.00 | $265.00 | $210.10 | |
| 22 | Prestressed concrete slab beam (5SB15) (425-7019) | LF | 739.62 | $275.00 | $252.00 | $247.02 | $330.00 | $300.00 | $270.00 | $210.10 |
| 23 | Riprap (stone protection)(12 in) (432-7041) | CY | 378 | $245.00 | $195.00 | $261.92 | $250.00 | $280.00 | $151.00 | $275.00 |
| 24 | Rail (type T223) (450-7008) | LF | 432 | $180.00 | $223.00 | $135.00 | $140.00 | $145.00 | $300.00 | $159.50 |
| 25 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 138 | $220.00 | $180.00 | $243.16 | $180.00 | $270.00 | $350.00 | $286.00 |
| 26 | Removing structure (pipe) (496-7007) | LF | 132 | $30.00 | $55.16 | $40.99 | $40.00 | $40.00 | $48.00 | $48.40 |
| 27 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 2 | $30,000 | $13,121 | $29,209 | $25,000 | $30,000 | $24,000 | $33,000 |
| 28 | Mobilization (500-7001) | LS | 1 | $134,000 | $190,000 | $191,109 | $175,000 | $155,951 | $180,000 | $280,500 |
| 29 | Barricades, signs and traffic handling (502-7001) | MO | 10 | $5,000.00 | $5,000.00 | $11,950 | $4,500.00 | $2,434.35 | $1,900.00 | $14,300 |
| 30 | Portable changeable message sign (503-7002) | EACH | 2 | $461.00 | $17,280 | $25,000 | $19,379 | $5,600.00 | $13,200 | |
| 31 | Rock filter dams (install) (type 2) (506-7002) | LF | 328 | $50.00 | $57.00 | $51.79 | $1.00 | $55.00 | $48.00 | $62.70 |
| 32 | Rock filter dams (remove) (506-7011) | LF | 328 | $14.00 | $12.20 | $17.87 | $1.00 | $20.00 | $8.50 | $22.00 |
| 33 | Temporary sediment control fence (install) (506-7039) | LF | 1,682 | $5.00 | $4.80 | $5.17 | $1.00 | $4.25 | $3.50 | $7.70 |
| 34 | Temporary sediment control fence (remove) (506-7041) | LF | 1,682 | $1.00 | $1.90 | $1.74 | $1.00 | $1.00 | $1.00 | $4.40 |
| 35 | Metal W-beam guard fence (timber post) (540-7001) | LF | 300 | $35.00 | $36.00 | $27.96 | $30.00 | $36.19 | $28.00 | $31.63 |
| 36 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 8 | $1,500.00 | $1,479.00 | $1,249.00 | $1,800.00 | $1,500.09 | $1,350.00 | $1,441.00 |
| 37 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $3,500.00 | $3,739.00 | $3,080.44 | $2,800.00 | $3,793.29 | $3,000.00 | $3,245.00 |
| 38 | Wire fence (type A) (552-7001) | LF | 488 | $35.00 | $30.95 | $23.91 | $25.00 | $25.00 | $28.00 | $27.50 |
| 39 | Remove SM RD SN sup&AM (644-7073) | EACH | 3 | $130.00 | $133.00 | $151.13 | $50.00 | $119.62 | $130.00 | $184.93 |
| 40 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 11 | $40.00 | $31.84 | $45.41 | $40.00 | $32.30 | $16.00 | $55.50 |
| 41 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 17 | $40.00 | $31.84 | $38.81 | $40.00 | $32.30 | $34.00 | $49.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 8, 2025. Compiled by Mirage Metrics.