TxDOT contract A00138685 bid tabulation
Bridge Replacement, SH 25 (SH 25 to At Middle Fork Little Wichita River). Let by Texas DOT on February 6, 2025, Archer, Wichita Falls District. 7 bids received; low bid $6,506,472 by Altus Construction LLC, -5.1% against the engineer's estimate of $6,856,853.
- Owner
- Texas DOT
- Letting
- 06 FEB 2025
- Pay items
- 91
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Altus Construction LLC | $6,506,472 | Low | -5.0% |
| 2 | Project Allied Resources, LLC | $6,619,747 | +2.0% | -3.0% |
| 3 | MP Heavy Construction Inc | $6,794,460 | +4.0% | -1.0% |
| 4 | THK Construction LLC | $6,840,236 | +5.0% | 0.0% |
| 5 | A. L. Helmcamp, Inc. | $8,717,606 | +34% | +27% |
| 6 | Earth Builders, L.P. | $8,762,932 | +35% | +28% |
| 7 | Hodges and Son Construction Company, Inc. | $9,279,389 | +43% | +35% |
Engineer's estimate: $6,856,853.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Altus Construction LLC | 2. Project Allied Resources, LLC | 3. MP Heavy Construction Inc | 4. THK Construction LLC | 5. A. L. Helmcamp, Inc. | 6. Earth Builders, L.P. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 19.70 | $7,350.00 | $32,698 | $3,000.00 | $13,200 | $11,700 | $5,000.00 | $10,000 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 390 | $33.39 | $8.70 | $45.00 | $25.00 | $48.00 | $20.00 | |
| 3 | Remove (7"-13") TRT/untrt base & asphalt pavement (105-7058) | SY | 3,323 | $13.00 | $13.35 | $16.00 | $13.00 | $25.00 | $16.00 | $20.00 |
| 4 | Excavation (roadway) (110-7001) | CY | 959 | $28.00 | $19.86 | $16.70 | $32.00 | $25.00 | $35.00 | $25.00 |
| 5 | Excavation (channel) (110-7002) | CY | 985 | $30.00 | $23.87 | $26.10 | $32.00 | $25.00 | $40.00 | $25.00 |
| 6 | Embankment (final)(OC)(type C) (132-7005) | CY | 15,329 | $18.00 | $15.60 | $26.10 | $45.00 | $25.00 | $47.00 | $45.00 |
| 7 | Drill seed (permanent_rural_sand) (164-7041) | ACRE | 0.58 | $1,000.00 | $0.29 | $11,400 | $12,414 | $11,380 | $6,300.00 | $6,000.00 |
| 8 | Drill seed (temporary_warm_cool) (164-7047) | ACRE | 0.58 | $3,000.00 | $425.18 | $5,680.00 | $12,414 | $11,380 | $6,300.00 | $6,000.00 |
| 9 | Vegetative watering (168-7001) | TGL | 41 | $27.00 | $30.53 | $84.00 | $56.00 | $100.00 | $50.00 | $50.00 |
| 10 | Soil retention blankets (CL 1) (type B) (169-7043) | SY | 8,526 | $1.10 | $1.10 | $2.10 | $2.40 | $2.20 | $2.50 | $3.00 |
| 11 | Cement (275-7001) | TON | 85 | $400.00 | $229.54 | $254.00 | $270.67 | $400.00 | $320.00 | $500.00 |
| 12 | Cement treat (subgrade) (8") (275-7017) | SY | 6,537 | $8.00 | $4.03 | $6.90 | $4.50 | $22.00 | $12.00 | $20.00 |
| 13 | Prime coat (MC-30) (310-7004) | GAL | 1,502 | $6.00 | $6.68 | $12.00 | $9.42 | $29.09 | $10.00 | $25.00 |
| 14 | D-GR HMA type-B PG64-22 (341-7001) | TON | 2,113 | $108.96 | $111.85 | $149.00 | $121.34 | $206.98 | $160.00 | $230.00 |
| 15 | D-GR HMA type D sac-B PG70-28 (341-7054) | TON | 674 | $180.00 | $193.29 | $172.00 | $128.00 | $329.89 | $225.00 | $320.00 |
| 16 | Struct excavation (box) (400-7002) | CY | 342 | $41.73 | $14.50 | $30.00 | $25.00 | $30.00 | $25.00 | |
| 17 | Cut & restore asphalt paving (400-7008) | SY | 96 | $184.67 | $126.00 | $172.50 | $150.00 | $215.00 | $225.00 | |
| 18 | Cem stabil BKFL (400-7010) | CY | 132 | $120.00 | $187.80 | $385.00 | $230.00 | $350.00 | $300.00 | $400.00 |
| 19 | Flowable backfill (401-7001) | CY | 68 | $375.60 | $385.00 | $362.80 | $300.00 | $270.00 | $400.00 | |
| 20 | Trench excavation protection (402-7001) | LF | 50 | $5.56 | $1,010.00 | $39.43 | $20.00 | $95.00 | $1.00 | |
| 21 | Temporary special shoring (403-7001) | SF | 950 | $23.00 | $33.39 | $63.00 | $49.95 | $40.00 | $120.00 | $30.00 |
| 22 | Drilled shaft (36 in) (416-7006) | LF | 1,645 | $330.00 | $231.08 | $280.00 | $288.00 | $251.07 | $400.00 | $330.00 |
| 23 | Class C concrete (abutment)(HPC) (420-7013) | CY | 89.80 | $1,050.00 | $1,857.06 | $1,680.00 | $1,295.00 | $1,400.00 | $3,200.00 | $2,400.00 |
| 24 | Class C concrete (cap)(HPC) (420-7023) | CY | 107 | $2,000.00 | $1,625.43 | $1,940.00 | $1,295.00 | $1,500.00 | $2,700.00 | $2,400.00 |
| 25 | Class C concrete (column)(HPC) (420-7039) | CY | 51.80 | $1,510.00 | $1,567.12 | $1,750.00 | $1,687.00 | $2,500.00 | $2,700.00 | $2,400.00 |
| 26 | Reinforced concrete slab (box beam)(HPC) (422-7006) | SF | 18,639 | $45.00 | $21.81 | $22.10 | $24.65 | $24.00 | $45.00 | $35.00 |
| 27 | Approach slab (HPC) (422-7014) | CY | 136 | $865.00 | $991.16 | $763.00 | $480.00 | $900.00 | $1,600.00 | $1,400.00 |
| 28 | Shear key (422-7020) | CY | 89.60 | $650.00 | $542.54 | $343.00 | $480.00 | $750.00 | $850.00 | $2,000.00 |
| 29 | Prestressed concrete X-beam (4XB20) (425-7034) | LF | 2,499 | $295.00 | $296.39 | $322.00 | $269.21 | $309.32 | $320.00 | $350.00 |
| 30 | Prestressed concrete X-beam (5XB20) (425-7035) | LF | 1,666 | $325.34 | $310.80 | $322.00 | $269.21 | $309.32 | $330.00 | $350.00 |
| 31 | Penetrating concrete surface treatment (428-7001) | SY | 108 | $10.00 | $25.04 | $139.00 | $12.84 | $20.00 | $40.00 | $20.00 |
| 32 | Riprap (mow strip)(4 in) (432-7013) | CY | 118 | $525.00 | $481.73 | $677.00 | $525.00 | $800.00 | $1,000.00 | $550.00 |
| 33 | Riprap (stone protection)(12 in) (432-7041) | CY | 1,589 | $212.00 | $128.92 | $201.00 | $120.12 | $130.00 | $140.00 | $240.00 |
| 34 | Riprap (stone protection)(18 in) (432-7043) | CY | 113 | $236.00 | $211.00 | $132.13 | $150.00 | $200.00 | $250.00 | |
| 35 | Rail (type T223)(HPC) (450-7009) | LF | 904 | $130.00 | $129.17 | $176.00 | $149.35 | $180.00 | $280.00 | $200.00 |
| 36 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 178 | $220.00 | $271.23 | $316.00 | $220.35 | $250.00 | $300.00 | $270.00 |
| 37 | Concrete box culvert (9 FT X 6 FT) (462-7028) | LF | 118 | $1,172.13 | $1,730.00 | $1,032.04 | $1,400.00 | $1,850.00 | $1,800.00 | |
| 38 | Wingwall (PW - 2) (HW=8 FT) (466-7192) | EACH | 2 | $14,587 | $45,300 | $25,000 | $65,000 | $62,000 | $50,000 | |
| 39 | Removing structure (box culvert) (496-7001) | EACH | 1 | $5,564.50 | $26,400 | $4,833.33 | $20,000 | $40,000 | $65,000 | |
| 40 | Removing structure (wingwall) (496-7005) | EACH | 2 | $2,086.69 | $2,500.00 | $2,421.25 | $2,000.00 | $20,000 | $30,000 | |
| 41 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 2 | $130,000 | $72,943 | $81,000 | $76,800 | $25,000 | $90,000 | $95,000 |
| 42 | Mobilization (500-7001) | LS | 1 | $639,440 | $647,396 | $662,000 | $1,207,500 | $600,000 | $650,000 | $800,000 |
| 43 | Barricades, signs and traffic handling (502-7001) | MO | 19 | $10,500 | $15,302 | $3,280.00 | $3,498.69 | $1,875.39 | $10,500 | $5,000.00 |
| 44 | Portable changeable message sign (503-7002) | EACH | 6 | $12,100 | $18,808 | $6,560.00 | $13,500 | $20,000 | $15,000 | $18,000 |
| 45 | TMA (stationary) (505-7001) | DAY | 10 | $220.00 | $185.52 | $265.00 | $350.00 | $350.00 | $300.00 | $350.00 |
| 46 | TMA (mobile operation) (505-7003) | DAY | 20 | $200.00 | $208.67 | $233.00 | $450.00 | $350.00 | $650.00 | $650.00 |
| 47 | Rock filter dams (install) (type 1) (506-7001) | LF | 158 | $37.00 | $33.39 | $48.00 | $38.40 | $27.50 | $60.00 | $65.00 |
| 48 | Rock filter dams (install) (type 2) (506-7002) | LF | 32 | $45.32 | $53.00 | $55.20 | $55.00 | $70.00 | $75.00 | |
| 49 | Rock filter dams (remove) (506-7011) | LF | 190 | $12.70 | $14.21 | $16.00 | $18.00 | $10.00 | $30.00 | $26.00 |
| 50 | Construction exits (install) (type 1) (506-7020) | SY | 536 | $31.13 | $27.27 | $37.30 | $26.40 | $1.00 | $25.00 | $65.00 |
| 51 | Construction exits (remove) (506-7024) | SY | 536 | $10.55 | $10.56 | $13.10 | $12.00 | $1.00 | $10.00 | $10.00 |
| 52 | Temporary sediment control fence (install) (506-7039) | LF | 3,091 | $3.80 | $3.81 | $4.95 | $6.18 | $4.40 | $4.00 | $4.00 |
| 53 | Temporary sediment control fence (remove) (506-7041) | LF | 3,091 | $1.00 | $1.15 | $1.41 | $1.26 | $1.10 | $2.00 | $2.00 |
| 54 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 980 | $4.90 | $5.53 | $7.10 | $6.30 | $5.24 | $6.00 | $7.00 |
| 55 | Biodegradable erosion control logs (remove) (506-7046) | LF | 980 | $1.00 | $1.67 | $1.87 | $1.80 | $1.10 | $2.00 | $2.00 |
| 56 | Constructing detours (508-7001) | SY | 40 | $125.00 | $108.26 | $195.00 | $150.00 | $100.00 | $1,000.00 | $250.00 |
| 57 | One-way traffic control (port traffic signal) (510-7003) | MO | 12 | $8,000.00 | $6,489.60 | $4,250.00 | $6,383.33 | $4,166.67 | $5,000.00 | $5,000.00 |
| 58 | Portable concrete traffic barrier (furnish and install)(F-shape)(type 1) (512-7005) | LF | 1,260 | $50.00 | $39.65 | $85.00 | $25.00 | $100.00 | $120.00 | $100.00 |
| 59 | Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029) | LF | 1,260 | $20.00 | $13.77 | $13.70 | $10.00 | $20.00 | $30.00 | $15.00 |
| 60 | Portable concrete traffic barrier (remove)(F-shape)(type 1) (512-7053) | LF | 1,260 | $20.00 | $17.56 | $25.20 | $10.00 | $20.00 | $50.00 | $15.00 |
| 61 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 1,282 | $0.24 | $2.18 | $10.20 | $10.06 | $7.01 | $10.00 | $10.00 |
| 62 | Metal W-beam guard fence (timber post) (540-7001) | LF | 850 | $25.00 | $23.95 | $24.80 | $27.00 | $24.75 | $27.00 | $26.00 |
| 63 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 8 | $2,200.00 | $2,086.69 | $2,090.00 | $2,280.00 | $1,705.00 | $2,500.00 | $1,900.00 |
| 64 | Metal beam guard fence (long span system) (540-7027) | EACH | 2 | $1,262.12 | $1,430.00 | $1,560.00 | $1,265.00 | $1,500.00 | $1,600.00 | |
| 65 | Remove metal beam guard fence (542-7001) | LF | 1,150 | $3.00 | $2.69 | $2.75 | $3.00 | $10.00 | $3.50 | $5.00 |
| 66 | Remove terminal anchor section (542-7002) | EACH | 4 | $229.95 | $275.00 | $300.00 | $100.00 | $350.00 | $200.00 | |
| 67 | Guardrail end treatment (install) (544-7001) | EACH | 12 | $3,250.00 | $2,780.75 | $3,250.00 | $3,540.00 | $3,795.00 | $3,500.00 | $3,500.00 |
| 68 | Guardrail end treatment (remove) (544-7003) | EACH | 8 | $300.00 | $267.10 | $275.00 | $300.00 | $100.00 | $350.00 | $400.00 |
| 69 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 4 | $2,200.00 | $1,373.04 | $2,130.00 | $2,000.00 | $2,750.00 | $3,500.00 | $3,500.00 |
| 70 | Crash cushion attenuator (remove) (545-7004) | EACH | 4 | $1,716.00 | $834.68 | $1,280.00 | $1,200.00 | $1,100.00 | $3,500.00 | $1,200.00 |
| 71 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 4 | $8,765.00 | $7,679.01 | $7,220.00 | $8,000.00 | $9,735.00 | $12,000 | $12,000 |
| 72 | Wire fence (type C) (552-7003) | LF | 200 | $20.00 | $25.04 | $42.80 | $78.00 | $30.00 | $23.00 | $30.00 |
| 73 | Install small roadside sign support and assembly tytwt(1)WS(T) (644-7058) | EACH | 8 | $600.00 | $490.37 | $749.00 | $786.00 | $1,000.00 | $750.00 | $1,500.00 |
| 74 | Remove SM RD SN sup&AM (644-7073) | EACH | 4 | $95.99 | $163.00 | $174.00 | $250.00 | $100.00 | $150.00 | |
| 75 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 12 | $28.00 | $30.05 | $24.20 | $22.20 | $19.80 | $50.00 | $25.00 |
| 76 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 31 | $39.00 | $31.43 | $26.40 | $25.80 | $27.50 | $60.00 | $45.00 |
| 77 | Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059) | EACH | 4 | $75.12 | $152.00 | $126.00 | $110.00 | $150.00 | $75.00 | |
| 78 | Remove delin & object marker assms (658-7078) | EACH | 21 | $25.00 | $16.69 | $51.00 | $42.00 | $10.00 | $25.00 | $10.00 |
| 79 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 420 | $5.00 | $7.68 | $9.90 | $7.55 | $9.24 | $9.00 | $10.00 |
| 80 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 8,560 | $0.80 | $1.64 | $2.18 | $1.41 | $1.65 | $2.00 | $2.00 |
| 81 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 70 | $8.00 | $17.64 | $33.00 | $19.02 | $11.00 | $30.00 | $15.00 |
| 82 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 17,040 | $1.00 | $1.71 | $2.18 | $1.39 | $1.65 | $2.00 | $2.00 |
| 83 | Reflectorized profile pavement marking type I(W)6"(solid)(090MIL) (666-7265) | LF | 3,978 | $0.75 | $1.18 | $7.90 | $1.27 | $6.05 | $7.00 | $7.00 |
| 84 | Reflectorized profile pavement marking type I(Y)6"(solid)(090MIL) (666-7269) | LF | 3,555 | $0.65 | $0.99 | $7.90 | $1.07 | $6.05 | $7.00 | $7.00 |
| 85 | Reflectorized profile pavement marking type I(Y)6"(broken)(090MIL) (666-7273) | LF | 110 | $1.01 | $11.90 | $1.09 | $5.50 | $11.00 | $6.00 | |
| 86 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 61 | $4.00 | $9.76 | $23.70 | $10.52 | $11.00 | $21.00 | $12.00 |
| 87 | Traffic button type B (672-7009) | EACH | 12 | $11.13 | $99.00 | $12.00 | $22.00 | $90.00 | $25.00 | |
| 88 | Eliminating existing PM & markers (4") (677-7001) | LF | 3,916 | $0.45 | $1.17 | $3.23 | $1.26 | $4.40 | $2.50 | $5.00 |
| 89 | Bonding course (3007-7001) | GAL | 245 | $4.50 | $3.96 | $33.40 | $8.00 | $2.20 | $16.00 | $4.00 |
| 90 | Rem lead-containing coating (4" strip) (5011-7004) | EACH | 216 | $160.00 | $255.55 | $46.60 | $212.11 | $260.24 | $270.00 | $200.00 |
| 91 | Rem lead-contatining coating (6" strip) (5011-7005) | EACH | 48 | $260.00 | $312.54 | $46.60 | $245.70 | $343.30 | $370.00 | $200.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 6, 2025. Compiled by Mirage Metrics.