Stateline Construction, LLC: TxDOT bid record

Stateline Construction, LLC submitted 62 bids on Texas DOT contracts in the data, from 09 JAN 2020 to 03 NOV 2022, and was the low bidder on 18 of them (29%). When it was not low, its total sat a median +20% above the low bid.

Owner
Texas DOT
Low bid volume
$48,616,784
Latest bid
03 NOV 2022
Data through
19 NOV 2026
62Bids
18Low bids
29Win rate, percent
+20%Median gap to the low bid when not low, 44 bids

By year

YearBidsLow bidsWin rate
202025728%
202125832%
202212325%
Stateline Construction, LLC, TxDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
Paris District11327%
Lufkin District9556%
Tyler District8338%
Atlanta District5120%
Wichita Falls District4125%
Abilene District4125%
Brownwood District300%
Dallas District3267%
Bryan District200%
Yoakum District200%
Waco District2150%
Lubbock District200%
Stateline Construction, LLC, TxDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Vegetative watering168-7001MG4822 (46%)$12.00$29.97
Temporary sediment control fence (remove)506-7041LF5516 (29%)$1.00$1.00
Preparing row100-7002STA4415 (34%)$1,912.50$2,750.00
Barricades, signs and traffic handling502-7001MO6113 (21%)$2,750.00$5,000.00
Set (type II) (24 in) (RCP) (6: 1) (P)467-7328EACH2012 (60%)$1,025.00$1,900.00
Riprap (mow strip)(4 in)432-7013CY2611 (42%)$435.00$643.00
Portable changeable message sign503-7002EACH279 (33%)$10,000$10,000
Set (type II) (18 in) (RCP) (6: 1) (P)467-7308EACH198 (42%)$675.00$1,300.00
Guardrail end treatment (install)544-7001EACH467 (15%)$2,772.50$3,245.00
Riprap (stone protection)(18 in)432-7043CY217 (33%)$140.00$200.00
Construction exits (remove)506-7024SY187 (39%)$10.00$10.00
Construction exits (install) (type 1)506-7020SY187 (39%)$22.50$30.00
Stateline Construction, LLC, TxDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

Stateline Construction, LLC, TxDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
03 NOV 202211223213Dallas DistrictFM 1385 Rehabilitation of existing road from APPROX 2 MILES NORTH OF FM 428 to FM 4551 of 7$7,569,743Low, 8.0% under the second
02 NOV 202211223011Paris DistrictUS 82 Hazard elimination & safety from COOKE COUNTY LINE to FM 1311 of 7$5,981,039Low, 1.0% under the second
08 SEP 202209223232Paris DistrictFM 271 Rehabilitate existing roadway from SH 78 to PR 243 of 3$7,804,915+10%
07 SEP 202209223011Brownwood DistrictFM 574 Bridge replacement from AT PECAN BAYOU2 of 4$4,194,759+7.0%
07 SEP 202209223016Lufkin DistrictFM 326 Roadway rehabilitation/reconstruction from 0.500 MILES NORTH OF US 69 to US 693 of 3$2,950,488+12%
07 SEP 202209224031Tyler DistrictUS0080 Concrete spall repair from VARIOUS LOCATIONS IN to THE TYLER DISTRICT4 of 5$506,250+58%
03 AUG 202208223032Lufkin DistrictFS 357 Hazard elimination & safety from END OF PAVEMENT to FM 357/FM 2334 of 4$2,355,480+43%
30 JUN 202206223634Paris DistrictCR Bridge replacement from ROLAND RD to AT S BRANCH OF BIG MINERAL CREEK3 of 4$1,145,992+15%
29 JUN 202206223423Abilene DistrictSH 70 Bridge replacement from PLUM CREEK1 of 5$3,716,744Low, 14% under the second
29 JUN 202206223430Paris DistrictCS Bridge replacement from S CEDAR ST to AT DELAWARE CREEK3 of 5$1,345,819+23%
29 JUN 202206223434Paris DistrictUS 380 Bridge maintenance from AT WEST CADDO CREEK7 of 8$1,154,340+100%
29 JUN 202206224429Paris DistrictUS0069 Flexible pavement structure repair from VARIOUS LOCATIONS IN to PARIS DISTRICT3 of 3$5,618,425+89%
12 OCT 202110211202Houston DistrictUS0290 Bridge replacement from US 290 AT HEGAR ROAD to US 290 AT HEGAR ROAD1 of 5$269,956Low, 11% under the second
04 AUG 202108213032Waco DistrictFM 1245 Replace bridge and approaches from @CHRISTMAS CREEK to (#STR #006)1 of 3$2,816,412Low, 18% under the second
04 JUN 202106213225Lufkin DistrictCR Bridge replacement from CR 1060 AT HICKORY CREEK TRIB to CR 1060 AT HICKORY CREEK TRIB1 of 4$1,693,606Low, 2.0% under the second
03 JUN 202106213013Wichita Falls DistrictFM 1954 Bridge replacement from HOLLIDAY CREEK to PANTHER CREEK4 of 4$6,569,989+24%
03 JUN 202106213026Atlanta DistrictFM 2735 Safety treat fixed objects from 8.3 MI. N. OF US 82 to US 825 of 9$1,809,977+21%
03 JUN 202106213029Lufkin DistrictFM 2261 Bridge replacement from AT WOODFIN CREEK to AT WOODFIN CREEK2 of 4$1,436,880+9.0%
06 MAY 202105213230Lufkin DistrictSH 21 Bridge replacement from SH 21 AT ATASCOSO CREEK to SH 21 AT ATASCOSO CREEK1 of 6$5,478,921Low, 4.0% under the second
05 MAY 202105213025Paris DistrictFM 38 Hazard elimination & safety from US 82 to US 824 of 7$1,794,710+3.0%
07 APR 202104213005Atlanta DistrictFM 248 Safety treat fixed objects from SH 43 to MARION C/L4 of 9$2,921,865+8.0%
07 APR 202104213011Austin DistrictCR Bridge replacement from ON CR 103 AT LLANO RIVER to STR AA05960012 of 8$1,750,845+9.0%
07 APR 202104213013Beaumont DistrictFM 1006 Hazard elimination & safety from SH 87, EAST to 0.171 MI N OF FM 21776 of 6$660,832+64%
05 MAR 202103213210Wichita Falls DistrictCR Bridge replacement from CR 196 (CR 416) AT BIRCHAM CREEK1 of 7$2,136,179Low, 2.0% under the second
05 MAR 202103213216Tyler DistrictCR Bridge replacement from CR 2918 AT STEVE CREEK RELIEF to STR#AA2918101, 1.25 MI S OF FM 12563 of 10$1,338,328+7.0%
Stateline Construction, LLC: latest TxDOT bids in the data

How this record was read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Every bid counted here matched its published total to within one dollar; TxDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy