TxDOT contract A00206363 bid tabulation
Construct Pedestrian Infrastructure, Various (Carpenter Street from SH 164 to Bowie to Bowie St from Carpenter to Lumpkin). Let by Texas DOT on September 4, 2025, McLennan, Waco District. 6 bids received; low bid $995,058 by Ti-Zack Concrete, LLC, -6.8% against the engineer's estimate of $1,067,720.
- Owner
- Texas DOT
- Letting
- 04 SEP 2025
- Pay items
- 69
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ti-Zack Concrete, LLC | $995,058 | Low | -7.0% |
| 2 | Cross Plus Construction, LLC | $1,096,957 | +10% | +3.0% |
| 3 | STX Civil | $1,168,001 | +17% | +9.0% |
| 4 | Highway 19 Construction LLC | $1,224,684 | +23% | +15% |
| 5 | Pmco Construction LLC | $1,275,506 | +28% | +19% |
| 6 | Garret Shields Infrastructure | $1,478,413 | +49% | +38% |
Engineer's estimate: $1,067,720.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ti-Zack Concrete, LLC | 2. Cross Plus Construction, LLC | 3. STX Civil | 4. Highway 19 Construction LLC | 5. Pmco Construction LLC | 6. Garret Shields Infrastructure |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 26.92 | $900.00 | $1,100.00 | $256.00 | $1,500.00 | $2,500.00 | $3,000.00 | $1,000.00 |
| 2 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 3 | $2,000.00 | $1,650.00 | $1,000.00 | $800.00 | $1,000.00 | $3,000.00 | $1,000.00 |
| 3 | Removing concrete (riprap) (104-7006) | SY | 3 | $35.00 | $140.60 | $1,200.00 | $10.00 | $25.00 | $50.00 | $50.00 |
| 4 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 27 | $35.00 | $31.24 | $25.00 | $10.00 | $25.00 | $25.00 | $50.00 |
| 5 | Removing concrete (curb or curb & gutter) (104-7018) | LF | 79 | $15.00 | $32.04 | $15.00 | $10.00 | $10.00 | $25.00 | $40.00 |
| 6 | Remove (0"-12") TRT/untrt base & asphalt pavement (105-7052) | SY | 106 | $20.00 | $31.83 | $55.00 | $20.00 | $15.00 | $50.00 | $30.00 |
| 7 | Excavation (channel) (110-7002) | CY | 715 | $40.00 | $70.79 | $31.00 | $25.00 | $25.00 | $30.00 | $40.00 |
| 8 | Embankment (final)(OC)(type B) (132-7003) | CY | 194 | $60.00 | $86.97 | $40.00 | $45.00 | $100.00 | $40.00 | $50.00 |
| 9 | Furn & place topsoil (4") (160-7002) | SY | 2,867 | $5.00 | $2.94 | $12.00 | $6.00 | $5.00 | $4.50 | $5.00 |
| 10 | Block sodding (162-7002) | SY | 2,867 | $8.00 | $6.60 | $8.50 | $6.00 | $7.00 | $6.00 | $12.00 |
| 11 | Vegetative watering (168-7001) | TGL | 29 | $50.00 | $1.10 | $111.00 | $50.00 | $100.00 | $200.00 | $100.00 |
| 12 | Flexible pavement structure repair(8") (351-7007) | SY | 540 | $185.00 | $80.17 | $250.00 | $125.00 | $350.00 | $185.00 | $110.00 |
| 13 | Class A concrete (collar) (420-7008) | EACH | 4 | $3,000.00 | $1,870.00 | $355.00 | $1,200.00 | $1,500.00 | $1,000.00 | $1,000.00 |
| 14 | Class C concrete (miscellaneous) (420-7067) | CY | 14 | $1,250.00 | $803.92 | $679.00 | $1,200.00 | $1,000.00 | $555.00 | $1,000.00 |
| 15 | Riprap (concrete)(6 in) (432-7003) | CY | 36 | $500.00 | $803.92 | $800.00 | $800.00 | $700.00 | $800.00 | $1,000.00 |
| 16 | Rail (handrail)(type A) (450-7058) | LF | 5 | $200.00 | $550.00 | $2,000.00 | $600.00 | $180.00 | $1,525.00 | $300.00 |
| 17 | Rail (handrail)(type B) (450-7059) | LF | 31 | $200.00 | $275.00 | $375.00 | $250.00 | $180.00 | $605.00 | $200.00 |
| 18 | CMP (gal steel 12 in) (460-7001) | LF | 178 | $80.00 | $165.00 | $50.00 | $100.00 | $35.00 | $185.00 | $80.00 |
| 19 | CMP (gal steel 18 in) (460-7003) | LF | 96 | $120.00 | $220.00 | $50.00 | $110.00 | $55.00 | $200.00 | $120.00 |
| 20 | Set (type II) (12 in) (CMP) (6: 1) (P) (467-7288) | EACH | 14 | $1,500.00 | $2,200.00 | $670.00 | $800.00 | $700.00 | $2,000.00 | $1,400.00 |
| 21 | Set (type II) (18 in) (CMP) (6: 1) (C) (467-7303) | EACH | 6 | $2,500.00 | $2,200.00 | $799.00 | $1,500.00 | $1,100.00 | $2,200.00 | $1,200.00 |
| 22 | Grate & frame (471-7003) | EACH | 52 | $2,000.00 | $1,391.31 | $1,250.00 | $2,900.00 | $1,800.00 | $2,000.00 | $2,000.00 |
| 23 | Adjusting manholes (water valve box) (479-7007) | EACH | 5 | $1,500.00 | $1,687.20 | $290.00 | $800.00 | $350.00 | $650.00 | $1,000.00 |
| 24 | Adjusting manholes (water meter) (479-7008) | EACH | 1 | $1,000.00 | $843.60 | $200.00 | $800.00 | $300.00 | $650.00 | $1,000.00 |
| 25 | Clean existing culverts (480-7001) | EACH | 2 | $1,000.00 | $605.00 | $1,000.00 | $4,000.00 | $5,000.00 | $2,500.00 | $5,000.00 |
| 26 | Removing structure (pipe) (496-7007) | LF | 205 | $50.00 | $16.50 | $16.00 | $20.00 | $50.00 | $25.00 | $20.00 |
| 27 | Remove STR (rail) (496-7017) | LF | 5 | $300.00 | $38.50 | $10.00 | $25.00 | $50.00 | $500.00 | $50.00 |
| 28 | Mobilization (500-7001) | LS | 1 | $93,705 | $103,143 | $80,000 | $90,000 | $167,000 | $127,000 | $100,000 |
| 29 | Barricades, signs and traffic handling (502-7001) | MO | 5 | $5,000.00 | $1,650.00 | $3,500.00 | $2,800.00 | $5,000.00 | $4,000.00 | $5,000.00 |
| 30 | Portable changeable message sign (503-7001) | DAY | 112 | $155.00 | $0.11 | $100.00 | $75.00 | $100.00 | $100.00 | $100.00 |
| 31 | TMA (stationary) (505-7001) | DAY | 56 | $200.00 | $0.11 | $1.00 | $225.00 | $500.00 | $200.00 | $400.00 |
| 32 | TMA (mobile operation) (505-7002) | HR | 40 | $100.00 | $0.11 | $1.00 | $45.00 | $100.00 | $200.00 | $400.00 |
| 33 | Rock filter dams (install) (type 2) (506-7002) | LF | 81 | $40.00 | $0.11 | $1.00 | $45.00 | $35.00 | $50.00 | $30.00 |
| 34 | Rock filter dams (remove) (506-7011) | LF | 81 | $15.00 | $0.11 | $1.00 | $10.00 | $10.00 | $11.00 | $5.00 |
| 35 | Sandbags for erosion control (506-7035) | EACH | 20 | $15.00 | $0.11 | $1.00 | $10.00 | $5.00 | $100.00 | $5.00 |
| 36 | Temporary sediment control fence (install) (506-7039) | LF | 1,062 | $6.00 | $0.12 | $6.00 | $5.00 | $4.00 | $5.00 | $6.00 |
| 37 | Temporary sediment control fence (remove) (506-7041) | LF | 1,062 | $2.00 | $0.11 | $1.00 | $1.00 | $1.00 | $1.10 | $1.00 |
| 38 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 80 | $9.00 | $0.11 | $1.00 | $8.00 | $5.00 | $6.00 | $6.00 |
| 39 | Biodegradable erosion control logs (remove) (506-7046) | LF | 80 | $3.00 | $0.11 | $1.00 | $2.00 | $1.00 | $1.10 | $1.00 |
| 40 | Concrete curb (type I) (529-7001) | LF | 227 | $30.00 | $51.41 | $75.00 | $35.00 | $35.00 | $100.00 | $20.00 |
| 41 | Concrete curb (type II) (529-7002) | LF | 1,306 | $40.00 | $51.41 | $75.00 | $35.00 | $35.00 | $50.00 | $25.00 |
| 42 | Concrete curb & gutter (type I) (529-7008) | LF | 10 | $40.00 | $51.41 | $75.00 | $100.00 | $30.00 | $125.00 | $40.00 |
| 43 | Concrete curb & gutter (type II) (529-7009) | LF | 174 | $50.00 | $51.41 | $75.00 | $80.00 | $45.00 | $125.00 | $40.00 |
| 44 | Concrete curb & gutter (armor curb) (529-7018) | LF | 56 | $400.00 | $343.12 | $175.00 | $450.00 | $80.00 | $300.00 | $80.00 |
| 45 | Concrete C&G (valley gutter) (529-7019) | LF | 205 | $70.00 | $77.11 | $76.00 | $50.00 | $25.00 | $85.00 | $40.00 |
| 46 | Driveways (concrete) (hes) (530-7007) | SY | 98 | $150.00 | $115.73 | $120.00 | $150.00 | $110.00 | $125.00 | $120.00 |
| 47 | Driveways (ACP) (530-7010) | SY | 332 | $100.00 | $76.89 | $175.00 | $120.00 | $75.00 | $105.00 | $120.00 |
| 48 | Concrete sidewalks (4") (531-7001) | SY | 895 | $100.00 | $92.40 | $85.00 | $100.00 | $75.00 | $90.00 | $100.00 |
| 49 | Curb ramps (type 1) (531-7015) | SY | 20 | $165.00 | $139.09 | $140.00 | $280.00 | $150.00 | $150.00 | $3,000.00 |
| 50 | Curb ramps (type 2) (531-7016) | SY | 12 | $165.00 | $139.09 | $140.00 | $280.00 | $180.00 | $150.00 | $3,000.00 |
| 51 | Curb ramps (type 3) (531-7017) | SY | 56 | $165.00 | $139.09 | $140.00 | $280.00 | $180.00 | $150.00 | $3,000.00 |
| 52 | Curb ramps (type 6) (531-7019) | SY | 28 | $165.00 | $139.81 | $138.00 | $280.00 | $180.00 | $150.00 | $3,000.00 |
| 53 | Curb ramps (type 7) (531-7020) | SY | 62 | $165.00 | $139.09 | $142.00 | $280.00 | $150.00 | $150.00 | $3,000.00 |
| 54 | Concrete sidewalks (special) (531-7025) | SY | 582 | $225.00 | $267.97 | $325.00 | $350.00 | $350.00 | $300.00 | $150.00 |
| 55 | Relocate existing mailbox (560-7012) | EACH | 3 | $380.00 | $0.11 | $120.00 | $450.00 | $100.00 | $825.00 | $500.00 |
| 56 | Aluminum signs (type A) (636-7001) | SF | 24 | $70.00 | $44.00 | $100.00 | $200.00 | $35.00 | $335.00 | $50.00 |
| 57 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 14 | $850.00 | $495.00 | $750.00 | $900.00 | $850.00 | $1,250.00 | $800.00 |
| 58 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 3 | $700.00 | $385.00 | $650.00 | $150.00 | $300.00 | $650.00 | $1,000.00 |
| 59 | Remove SM RD SN sup&AM (644-7073) | EACH | 3 | $150.00 | $27.50 | $50.00 | $250.00 | $100.00 | $125.00 | $500.00 |
| 60 | Reflectorized pavement marking type II (W) 4" (solid) (666-7171) | LF | 165 | $1.00 | $3.58 | $4.00 | $1.00 | $25.00 | $2.00 | $3.00 |
| 61 | Pavement sler 4" (666-7346) | LF | 165 | $1.00 | $0.66 | $4.00 | $2.00 | $10.00 | $1.00 | $2.00 |
| 62 | Pavement sler 24" (666-7352) | LF | 220 | $5.00 | $2.75 | $40.00 | $7.00 | $10.00 | $6.00 | $2.50 |
| 63 | Pavement sler (word) (666-7354) | EACH | 2 | $50.00 | $38.50 | $400.00 | $230.00 | $20.00 | $500.00 | $110.00 |
| 64 | Pavement sler (symbol) (666-7363) | EACH | 1 | $50.00 | $44.00 | $152.00 | $200.00 | $20.00 | $500.00 | $110.00 |
| 65 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 220 | $18.00 | $28.60 | $32.00 | $20.00 | $10.00 | $25.00 | $25.00 |
| 66 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 2 | $300.00 | $275.00 | $423.00 | $500.00 | $250.00 | $2,000.00 | $500.00 |
| 67 | Pre PM type C (WHT)(acc PRK)(symbl only) (668-7132) | EACH | 1 | $400.00 | $220.00 | $321.00 | $700.00 | $350.00 | $2,000.00 | $500.00 |
| 68 | Pavement surface preparation for marking (24") (678-7008) | LF | 220 | $3.00 | $1.38 | $15.00 | $7.00 | $20.00 | $5.00 | $2.00 |
| 69 | Rec rapid flash beacon (2-way solar) (6073-7001) | EACH | 2 | $9,500.00 | $11,000 | $9,457.00 | $22,000 | $5,000.00 | $10,000 | $10,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.