TxDOT contract A00206402 bid tabulation

Hazard Elimination & Safety, SH 37 (CR 2460 to CR 2302 (0.23 mi N SL 564)). Let by Texas DOT on January 6, 2026, Wood, Tyler District. 8 bids received; low bid $4,058,410 by Baker & Company Construction, LLC, -1.0% against the engineer's estimate of $4,100,162.

Owner
Texas DOT
Letting
06 JAN 2026
Pay items
90
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Baker & Company Construction, LLC$4,058,410Low-1.0%
2Texas Materials Group, Inc.$4,498,998+11%+10%
3Longview Bridge and Road, LTD.$4,516,185+11%+10%
4Drake Companies LLC$4,599,007+13%+12%
5Roman Emperors Road, LLC$4,733,397+17%+15%
6East Texas Bridge, Inc.$4,758,574+17%+16%
7CDM Holdings$5,004,561+23%+22%
8Highway 19 Construction LLC$6,762,316+67%+65%
TxDOT contract A00206402: bids by rank

Engineer's estimate: $4,100,162.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Baker & Company Construction, LLC2. Texas Materials Group, Inc.3. Longview Bridge and Road, LTD.4. Drake Companies LLC5. Roman Emperors Road, LLC6. East Texas Bridge, Inc.
1Preparing row (100-7002)STA35$2,400.00$1,525.00$1,255.11$2,500.00$1,375.00$3,000.00$2,500.00
2Removing concrete (driveways) (104-7011)SY289$30.00$27.00$26.75$34.00$16.00$30.00$30.00
3Removing concrete (curb & gutter) (104-7017)LF119$10.00$16.30$21.40$14.00$40.00$5.00$15.00
4Remove (3") TRT/untrt base & asphalt pavement (105-7023)SY4,365$6.75$4.40$4.02$8.20$22.00$5.00$15.00
5Remove (4") TRT/untrt base & asphalt pavement (105-7024)SY1,376$12.50$7.00$6.74$9.50$15.50$8.00$15.00
6Excavation (roadway) (110-7001)CY9,325$13.00$5.75$27.26$14.00$14.50$30.00$18.00
7Embankment (final)(OC)(type C) (132-7005)CY9,863$15.00$5.40$28.95$8.00$22.50$35.00$23.00
8Furn & place topsoil (4") (160-7002)SY51,521$3.00$1.50$2.53$2.15$2.00$1.80$2.55
9Bond fiber MTRX seed (permanent)(rural)(sand) (164-7076)SY51,521$0.60$0.90$0.57$0.60$0.60$0.60$0.58
10Bond fiber MTRX seed (temporary)(warm) (164-7077)SY25,762$0.60$0.65$0.56$0.56$0.60$0.60$0.57
11Bond fiber MTRX seed (temporary)(cool) (164-7078)SY25,762$0.40$0.65$0.54$0.57$0.58$0.60$0.55
12Vegetative watering (168-7001)TGL1,134$10.00$1.00$3.37$24.00$12.00$50.00$20.00
13Proof rolling (216-7001)HR40$125.00$135.00$295.53$50.00$70.00$200.00$85.00
14Cement (275-7001)TON393$280.00$276.00$278.09$275.00$285.00$250.00$275.00
15Cement TRT (existing material)(12") (275-7005)SY14,520$4.25$9.00$7.54$3.40$6.00$6.00$4.00
16Prime coat & blotter (MC-30) (310-7010)GAL1,452$6.50$7.65$17.97$11.00$8.50$10.00$6.50
17Emuls asphalt (erosion control)(CSS-1) (314-7010)GAL567$6.50$10.00$16.84$5.50$9.00$10.00$5.00
18SP mixes SP-B PG64-22 (344-7001)TON6,262$145.00$157.00$148.35$160.00$150.00$150.00$162.00
19SP mixes SP-C PG64-22 (level-UP) (344-7012)TON1,031$155.00$158.00$170.42$192.00$175.00$160.00$172.00
20Tack coat (344-7077)GAL1,423$4.00$5.80$5.37$5.20$9.25$5.00$6.00
21TBPFC (membrane) (348-7001)GAL9,313$6.00$5.10$3.75$5.50$5.75$5.00$5.00
22TBPFC-C PG76-22 sac-A (348-7002)TON3,492$170.00$225.00$247.74$228.00$260.00$180.00$220.00
23Flexible pavement structure repair(6") (351-7005)SY100$90.00$217.00$243.78$150.00$240.00$80.00$100.00
24Planing asphalt concrete pavement(0" to 2") (354-7032)SY8,645$3.75$2.70$3.93$3.80$5.20$4.00$6.00
25Planing asphalt concrete pavement (0" to 1.5") (354-7073)SY1,901$5.00$2.70$3.32$2.20$6.50$4.00$6.75
26Planing asphalt concrete pavement (1.5") (354-7074)SY6,045$5.00$2.20$3.32$3.15$3.75$4.00$3.50
27Temporary special shoring (403-7001)SF528$35.00$27.00$52.43$50.00$100.00$40.00$85.00
28Class C concrete (collar) (420-7061)EACH3$1,400.00$3,025.00$1,926.00$1,500.00$2,200.00$1,500.00$2,000.00
29Riprap (concrete)(4 in) (432-7001)CY177$575.00$850.00$760.77$575.00$600.00$520.00$650.00
30Riprap (mow strip)(4 in) (432-7013)CY46$700.00$655.00$1,016.50$600.00$740.00$700.00$675.00
31Riprap (stone common)(dry)(24 in) (432-7034)CY146$225.00$205.00$284.62$196.00$230.00$270.00$200.00
32RC pipe (CL III)(18 in) (464-7003)LF940$70.00$52.00$80.25$47.00$70.00$78.00$70.00
33RC pipe (CL III)(24 in) (464-7005)LF984$100.00$70.00$109.14$65.00$75.00$100.00$90.00
34RC pipe (CL III)(54 in) (464-7012)LF24$300.00$290.00$510.39$320.00$420.00$370.00$325.00
35RC pipe (CL IV)(24 in) (464-7021)LF114$150.00$98.00$119.84$88.00$130.00$140.00$100.00
36Headwall (CH - PW - S) (diameter= 54 in) (466-7123)EACH1$17,000$14,050$19,795$17,000$18,000$15,000$25,000
37Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH32$1,000.00$1,225.00$1,016.50$950.00$925.00$1,800.00$1,000.00
38Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH36$1,650.00$1,570.00$1,605.00$1,500.00$1,350.00$2,000.00$1,400.00
39Clean existing culverts (480-7001)EACH1$2,500.00$3,900.00$2,140.00$10,250$2,500.00$7,000.00$3,500.00
40Removing structure (pipe) (496-7037)EACH34$500.00$571.00$505.04$1,000.00$380.00$500.00$550.00
41Mobilization (500-7001)LS1$338,546$190,000$215,261$450,000$300,000$340,000$400,000
42Barricades, signs and traffic handling (502-7001)MO14$6,000.00$4,470.00$1,023.19$10,500$3,300.00$6,000.00$10,000
43Portable changeable message sign (503-7001)DAY450$100.00$49.00$21.47$110.00$100.00$50.00$100.00
44TMA (stationary) (505-7001)DAY225$150.00$363.00$198.63$225.00$150.00$220.00$200.00
45TMA (mobile operation) (505-7003)DAY18$100.00$440.00$161.05$400.00$150.00$280.00$350.00
46Rock filter dams (install) (type 1) (506-7001)LF105$35.00$60.00$40.66$50.00$44.00$40.00$44.00
47Rock filter dams (install) (type 2) (506-7002)LF180$45.00$227.00$44.95$45.00$50.00$45.00$48.00
48Rock filter dams (remove) (506-7011)LF285$15.00$28.00$11.77$20.00$12.00$15.00$11.00
49Temporary sediment control fence (install) (506-7039)LF3,250$4.00$3.30$4.28$4.50$4.25$4.00$4.50
50Temporary sediment control fence (remove) (506-7041)LF3,250$1.25$1.10$1.07$0.75$1.20$1.00$1.00
51Biodegradable erosion control logs (install) (18") (506-7045)LF135$8.00$8.80$5.35$19.00$5.85$8.00$6.00
52Biodegradable erosion control logs (remove) (506-7046)LF135$2.00$4.40$1.07$1.10$1.20$1.00$1.00
53Intersections (ACP) (530-7002)SY1,189$60.00$44.00$45.38$50.00$68.00$70.00$40.00
54Driveways (concrete) (hes) (530-7007)SY292$115.00$275.00$169.06$112.00$120.00$120.00$135.00
55Driveways (ACP) (530-7010)SY4,142$45.00$35.00$36.74$50.00$48.00$70.00$50.00
56Mill rumble strips (asphalt) (shoulder) (533-7001)LF11,705$0.25$0.30$0.15$0.16$0.58$0.60$0.50
57Mill rumble strips (asphalt) (centerline) (533-7002)LF9,915$0.25$0.30$0.17$0.18$0.58$0.60$0.50
58Metal W-beam guard fence (steel post) (540-7002)LF875$30.00$30.00$26.75$30.00$30.00$32.00$27.50
59Guardrail end treatment (install) (544-7001)EACH2$3,200.00$3,690.00$3,076.25$3,700.00$3,300.00$3,500.00$3,200.00
60Mailbox install-S (TWG-post) type 2 (560-7002)EACH20$325.00$300.00$360.59$300.00$640.00$350.00$375.00
61Mailbox install-D (TWG-post) type 2 (560-7003)EACH4$380.00$350.00$409.81$350.00$875.00$370.00$425.00
62Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH29$610.00$690.00$693.36$700.00$875.00$680.00$715.00
63Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH2$850.00$790.00$852.79$800.00$935.00$625.00$875.00
64Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009)EACH2$800.00$1,185.00$732.95$1,200.00$990.00$800.00$750.00
65Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH1$1,000.00$1,320.00$1,103.17$1,300.00$990.00$1,200.00$1,150.00
66Install small roadside sign support and assembly TYS80(1)SA(U-BM) (644-7034)EACH1$1,250.00$1,645.00$1,300.05$1,650.00$875.00$1,500.00$1,350.00
67Remove SM RD SN sup&AM (644-7073)EACH31$115.00$109.00$108.07$110.00$115.00$125.00$110.00
68Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH19$30.00$28.00$33.17$36.00$29.00$35.00$30.00
69Install object marker assembly (OM-2Z)(WFLX)GND (658-7058)EACH2$95.00$66.00$86.67$70.00$50.00$70.00$50.00
70Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059)EACH1$85.00$66.00$94.16$70.00$64.00$100.00$100.00
71Install OM SM RD sign (1-OM-con)R (658-7080)EACH6$280.00$39.00$86.67$40.00$290.00$35.00$90.00
72Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF11,487$0.50$0.85$0.80$0.66$0.90$0.50$0.85
73Work zone pavement marking non-removing (W)24"(solid) (662-7017)LF118$3.00$4.40$4.28$3.30$4.65$2.00$4.50
74Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH32$1.50$11.25$2.15$2.50$1.45$5.00$2.50
75Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH1,722$0.75$4.50$2.15$2.50$1.45$2.00$2.50
76Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009)LF150$2.00$2.75$2.68$1.40$2.90$2.00$2.75
77Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018)LF95$2.00$2.75$2.68$1.40$2.90$2.00$2.75
78Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF1,125$1.00$1.30$1.23$1.10$1.35$2.00$1.30
79Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF185$6.00$7.15$6.96$11.00$7.60$12.00$7.15
80Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF90$1.00$1.65$1.61$1.10$1.75$2.00$1.65
81Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF15,570$0.50$1.10$1.07$0.60$1.20$1.00$1.10
82Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF3,295$0.50$1.10$1.07$0.66$1.20$1.00$1.10
83Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF17,445$0.50$1.10$1.07$0.60$1.20$1.00$1.10
84Prefabricated PM type C (W)(arrow) (668-7091)EACH15$225.00$248.00$240.75$265.00$265.00$250.00$250.00
85Prefabricated PM type C (W)(LN reduct arrow) (668-7100)EACH2$400.00$358.00$347.75$325.00$380.00$450.00$360.00
86Prefabricated PM type C (W)(word) (668-7103)EACH5$240.00$303.00$294.25$325.00$320.00$340.00$300.00
87Reflectorized pavement marker type I-C (672-7002)EACH64$4.50$5.50$5.35$6.05$5.85$8.00$5.50
88Reflectorized pavement marker type II-A-A (672-7004)EACH553$5.00$5.50$5.35$6.05$5.85$6.00$5.50
89Full - width mowing (730-7019)CYC3$5,400.00$3,850.00$833.75$8,250.00$2,600.00$5,000.00$5,000.00
90Litter removal (734-7002)CYC3$3,550.00$3,850.00$4,163.00$1,500.00$2,200.00$5,000.00$5,000.00
TxDOT contract A00206402: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of January 6, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy