TxDOT contract A00206565 bid tabulation
Hazard Elimination & Safety, FM 227 (FM 2544 to 3.3 MILES EAST OF FM 2544). Let by Texas DOT on June 3, 2026, Houston, Lufkin District. 9 bids received; low bid $4,462,648 by Pinto Construction Co., Inc., -12% against the engineer's estimate of $5,065,573.
- Owner
- Texas DOT
- Letting
- 03 JUN 2026
- Pay items
- 88
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Pinto Construction Co., Inc. | $4,462,648 | Low | -12% |
| 2 | Big Creek Construction, LTD. | $4,876,249 | +9.0% | -4.0% |
| 3 | L. S. Equipment Co., Inc. | $4,944,496 | +11% | -2.0% |
| 4 | A. L. Helmcamp, Inc. | $5,121,216 | +15% | +1.0% |
| 5 | THK Construction LLC | $5,289,681 | +19% | +4.0% |
| 6 | Longview Bridge and Road, LTD. | $5,638,747 | +26% | +11% |
| 7 | Environmental Allies, Inc. | $5,796,845 | +30% | +14% |
| 8 | Garret Shields Infrastructure | $6,144,210 | +38% | +21% |
| 9 | Drewery Construction Company, Incorporated | $6,561,594 | +47% | +30% |
Engineer's estimate: $5,065,573.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Pinto Construction Co., Inc. | 2. Big Creek Construction, LTD. | 3. L. S. Equipment Co., Inc. | 4. A. L. Helmcamp, Inc. | 5. THK Construction LLC | 6. Longview Bridge and Road, LTD. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 175 | $1,500.00 | $1,600.00 | $2,500.00 | $1,500.00 | $3,000.00 | $1,800.00 | $2,500.00 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 51 | $25.00 | $23.10 | $30.00 | $10.00 | $22.00 | $20.00 | $28.00 |
| 3 | Subgr widen (OC) (112-7001) | STA | 175 | $300.00 | $342.55 | $500.00 | $500.00 | $500.00 | $260.00 | $950.00 |
| 4 | Embankment (vehicle)(OC)(type B) (132-7015) | CY | 7,491 | $20.00 | $20.33 | $29.00 | $20.00 | $1.00 | $15.00 | $18.00 |
| 5 | Backfill (type B) (134-7002) | STA | 175 | $200.00 | $196.38 | $250.00 | $200.00 | $400.00 | $210.00 | $115.00 |
| 6 | Blading (150-7001) | STA | 175 | $250.00 | $164.28 | $250.00 | $150.00 | $230.00 | $153.00 | $75.00 |
| 7 | Spec excavation work (hyd excavator) (158-7002) | HR | 20 | $150.00 | $52.50 | $150.00 | $100.00 | $51.00 | $100.00 | $235.00 |
| 8 | Block sodding (162-7002) | SY | 1,641 | $6.00 | $5.60 | $6.00 | $6.10 | $5.00 | $5.25 | $6.25 |
| 9 | Broadcast seed (temporary_warm) (164-7005) | SY | 48,453 | $0.10 | $0.12 | $0.15 | $0.13 | $0.13 | $0.14 | $0.15 |
| 10 | Broadcast seed (temporary_cool) (164-7006) | SY | 48,453 | $0.10 | $0.12 | $0.15 | $0.13 | $0.13 | $0.14 | $0.15 |
| 11 | Bond fiber MTRX seed (permanent)(rural)(sand) (164-7073) | SY | 96,905 | $0.60 | $0.53 | $0.55 | $0.60 | $0.54 | $0.56 | $0.60 |
| 12 | Vegetative watering (168-7001) | TGL | 3,909.80 | $10.00 | $0.01 | $1.00 | $0.01 | $5.00 | $1.00 | $21.00 |
| 13 | Soil ret BLKT(SL_steep_sand_short) (169-7007) | SY | 367 | $1.50 | $2.15 | $2.50 | $2.44 | $2.00 | $1.05 | $2.60 |
| 14 | Sprinkling (dust control) (204-7001) | TGL | 544.40 | $50.00 | $0.01 | $35.00 | $0.01 | $0.01 | $30.00 | $21.00 |
| 15 | FL BS (roadway del) (type D GR 3) (247-7210) | TON | 20,271 | $50.00 | $50.37 | $45.00 | $51.00 | $46.00 | $65.00 | $63.00 |
| 16 | Cement (275-7001) | TON | 980 | $220.00 | $211.51 | $225.00 | $200.00 | $230.00 | $230.00 | $270.00 |
| 17 | Cement treat (MX ext metal/NW base) (13") (275-7033) | SY | 54,444 | $5.00 | $3.34 | $3.50 | $4.00 | $4.50 | $4.00 | $3.50 |
| 18 | Emuls asphalt (erosion control)(SS-1) (314-7008) | GAL | 2,333 | $3.00 | $5.61 | $5.00 | $5.50 | $4.00 | $7.21 | $4.70 |
| 19 | Asphalt (RC-250) (316-7032) | TON | 57.89 | $1,000.00 | $1,243.53 | $1,250.00 | $1,400.00 | $1,220.00 | $1,802.50 | $1,425.00 |
| 20 | Asphalt (AC-15P or CRS-2P) (316-7088) | TON | 97.26 | $900.00 | $1,048.89 | $1,000.00 | $1,174.00 | $990.00 | $1,699.50 | $1,240.00 |
| 21 | Aggregate (type E or L, GR-5) (316-7254) | CY | 389 | $185.00 | $154.31 | $150.00 | $180.00 | $250.00 | $195.00 | $205.00 |
| 22 | Aggregate (type E or L, PE or PL GR 4) (316-7268) | CY | 403 | $185.00 | $160.34 | $150.00 | $180.00 | $240.00 | $210.00 | $230.00 |
| 23 | D-GR HMA type D PG 64-22 (exempt) (341-7064) | TON | 65 | $160.00 | $192.89 | $275.00 | $225.00 | $290.00 | $231.75 | $270.00 |
| 24 | SP mixes SP-C sac-A PG70-22 (344-7020) | TON | 5,989 | $150.00 | $165.88 | $135.00 | $169.00 | $160.00 | $193.07 | $165.00 |
| 25 | Cem stabil BKFL (400-7010) | CY | 5 | $275.00 | $372.75 | $500.00 | $200.00 | $360.00 | $300.00 | $550.00 |
| 26 | Temporary special shoring (403-7001) | SF | 608 | $50.00 | $36.75 | $45.00 | $50.00 | $35.00 | $30.00 | $50.00 |
| 27 | Class C concrete (collar) (420-7061) | EACH | 10 | $1,000.00 | $1,249.50 | $500.00 | $2,600.00 | $1,200.00 | $1,000.00 | $1,320.00 |
| 28 | Riprap (concrete)(4 in) (432-7001) | CY | 16 | $800.00 | $735.00 | $800.00 | $1,000.00 | $710.00 | $750.00 | $690.00 |
| 29 | Riprap (stone common)(dry)(24 in) (432-7034) | CY | 37 | $225.00 | $229.95 | $225.00 | $350.00 | $221.00 | $200.00 | $470.00 |
| 30 | RC pipe (CL III)(18 in) (464-7003) | LF | 692 | $65.00 | $71.40 | $80.00 | $59.00 | $69.00 | $50.00 | $54.00 |
| 31 | RC pipe (CL III)(24 in) (464-7005) | LF | 96 | $100.00 | $99.75 | $100.00 | $90.00 | $95.00 | $65.00 | $106.00 |
| 32 | RC pipe (CL III)(30 in) (464-7007) | LF | 34 | $225.00 | $229.95 | $225.00 | $125.00 | $221.00 | $85.00 | $152.00 |
| 33 | Junction box(complete)(PJB)(4FTX4FT) (465-7006) | EACH | 2 | $7,000.00 | $7,927.50 | $8,000.00 | $6,500.00 | $7,625.00 | $5,000.00 | $6,600.00 |
| 34 | Headwall (CH - FW - 0) (diameter= 60 in) (466-7013) | EACH | 1 | $20,000 | $14,070 | $14,000 | $19,000 | $13,534 | $20,000 | $15,720 |
| 35 | Headwall (CH - PW - 0) (diameter= 30 in) (466-7103) | EACH | 1 | $7,000.00 | $9,450.00 | $10,000 | $14,500 | $9,090.00 | $10,000 | $9,200.00 |
| 36 | Headwall (CH - PW - 0) (diameter= 48 in) (466-7107) | EACH | 2 | $12,900 | $10,500 | $12,000 | $18,000 | $10,100 | $16,000 | $13,420 |
| 37 | Headwall (CH - PW - 0) (diameter= 60 in) (466-7109) | EACH | 2 | $25,000 | $16,800 | $17,500 | $31,000 | $16,160 | $20,000 | $17,250 |
| 38 | Headwall (CH - PW - S) (diameter= 54 in) (466-7123) | EACH | 1 | $20,000 | $15,750 | $16,000 | $30,000 | $15,150 | $20,000 | $20,480 |
| 39 | Headwall (CH - PW - S) (diameter= 72 in) (466-7126) | EACH | 2 | $30,000 | $18,900 | $20,000 | $36,000 | $18,180 | $20,000 | $25,550 |
| 40 | Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306) | EACH | 5 | $1,000.00 | $771.75 | $800.00 | $900.00 | $740.00 | $1,000.00 | $985.00 |
| 41 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 38 | $1,000.00 | $840.00 | $900.00 | $975.00 | $808.00 | $750.00 | $1,095.00 |
| 42 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 4 | $1,500.00 | $1,260.00 | $1,250.00 | $1,300.00 | $1,212.00 | $1,000.00 | $1,470.00 |
| 43 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 4 | $1,800.00 | $1,365.00 | $1,500.00 | $1,390.00 | $1,313.00 | $1,000.00 | $1,700.00 |
| 44 | Set (type II) (30 in) (RCP) (4: 1) (C) (467-7346) | EACH | 5 | $3,000.00 | $1,756.65 | $1,800.00 | $3,000.00 | $1,690.00 | $1,250.00 | $1,895.00 |
| 45 | Clean existing culverts (480-7001) | EACH | 4 | $1,500.00 | $1,575.00 | $2,000.00 | $1,000.00 | $1,515.00 | $2,000.00 | $1,900.00 |
| 46 | Removing structure (ret wall) (496-7019) | LF | 44 | $2,500.00 | $73.50 | $100.00 | $200.00 | $71.00 | $75.00 | $100.00 |
| 47 | Removing structure (pipe) (496-7037) | EACH | 17 | $500.00 | $367.50 | $500.00 | $200.00 | $354.00 | $100.00 | $740.00 |
| 48 | Mobilization (500-7001) | LS | 1 | $500,000 | $302,000 | $475,000 | $500,000 | $425,000 | $450,000 | $500,000 |
| 49 | Barricades, signs and traffic handling (502-7001) | MO | 15 | $3,500.00 | $1,500.00 | $5,000.00 | $2,500.00 | $15,000 | $1,017.66 | $2,500.00 |
| 50 | Portable changeable message sign (503-7002) | EACH | 3 | $10,000 | $5,000.00 | $12,500 | $10,000 | $15,000 | $10,000 | $20,000 |
| 51 | TMA (stationary) (505-7001) | DAY | 294 | $150.00 | $75.00 | $250.00 | $100.00 | $250.00 | $200.00 | $250.00 |
| 52 | TMA (mobile operation) (505-7003) | DAY | 38 | $150.00 | $50.00 | $500.00 | $100.00 | $100.00 | $200.00 | $350.00 |
| 53 | Rock filter dams (install) (type 2) (506-7002) | LF | 1,430 | $40.00 | $30.75 | $40.00 | $34.00 | $37.00 | $38.85 | $34.00 |
| 54 | Rock filter dams (remove) (506-7011) | LF | 1,430 | $10.00 | $9.75 | $12.00 | $3.00 | $11.00 | $11.55 | $11.00 |
| 55 | Construction exits (install) (type 1) (506-7020) | SY | 180 | $35.00 | $15.00 | $35.00 | $40.00 | $10.00 | $1.00 | $42.00 |
| 56 | Construction exits (remove) (506-7024) | SY | 180 | $10.00 | $6.00 | $10.00 | $5.00 | $5.00 | $1.00 | $13.00 |
| 57 | Temporary sediment control fence (install) (506-7039) | LF | 7,076 | $4.00 | $3.50 | $5.00 | $3.65 | $3.80 | $3.94 | $4.00 |
| 58 | Temporary sediment control fence (remove) (506-7041) | LF | 7,076 | $1.00 | $0.95 | $0.50 | $1.00 | $0.25 | $0.27 | $1.10 |
| 59 | Driveways (concrete) (530-7006) | SY | 51 | $300.00 | $131.25 | $150.00 | $165.00 | $126.00 | $100.00 | $267.00 |
| 60 | Driveways (ACP) (530-7010) | SY | 1,976 | $65.00 | $55.06 | $55.00 | $51.00 | $96.00 | $43.00 | $57.00 |
| 61 | Turnouts (ACP) (530-7018) | SY | 330 | $100.00 | $53.34 | $75.00 | $65.00 | $32.00 | $64.00 | $115.00 |
| 62 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 34,764 | $0.30 | $0.31 | $0.30 | $0.25 | $0.22 | $0.17 | $0.25 |
| 63 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 17,500 | $0.30 | $0.33 | $0.31 | $0.25 | $0.22 | $0.27 | $0.35 |
| 64 | Metal W-beam guard fence (timber post) (540-7001) | LF | 425 | $25.00 | $29.40 | $35.00 | $26.00 | $28.00 | $27.66 | $29.50 |
| 65 | Remove metal beam guard fence (542-7001) | LF | 600 | $2.50 | $3.15 | $3.00 | $3.50 | $3.00 | $2.58 | $2.75 |
| 66 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,000.00 | $3,307.50 | $3,500.00 | $4,000.00 | $3,182.00 | $3,244.50 | $3,465.00 |
| 67 | Guardrail end treatment (remove) (544-7003) | EACH | 6 | $200.00 | $315.00 | $350.00 | $300.00 | $303.00 | $206.00 | $220.00 |
| 68 | Wire fence (type A) (552-7001) | LF | 1,000 | $30.00 | $20.00 | $25.00 | $20.00 | $7.50 | $25.00 | $27.50 |
| 69 | Gate (type 1) (552-7006) | EACH | 1 | $950.00 | $2,500.00 | $2,500.00 | $1,500.00 | $950.00 | $1,000.00 | $1,100.00 |
| 70 | Mailbox install-M (TWG-post) type 1 (560-7001) | EACH | 1 | $600.00 | $1,050.00 | $500.00 | $710.00 | $1,010.00 | $720.52 | $769.50 |
| 71 | Mailbox install-S (WC-post) type 3 (560-7004) | EACH | 15 | $250.00 | $157.50 | $250.00 | $293.00 | $152.00 | $285.27 | $305.00 |
| 72 | Mailbox install-D (WC-post) type 3 (560-7005) | EACH | 3 | $317.00 | $252.00 | $300.00 | $350.00 | $242.00 | $332.14 | $355.00 |
| 73 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 10 | $693.00 | $315.00 | $800.00 | $755.00 | $303.00 | $771.47 | $825.00 |
| 74 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 2 | $1,044.00 | $525.00 | $1,000.00 | $1,280.00 | $505.00 | $1,310.16 | $1,400.00 |
| 75 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 10 | $602.00 | $315.00 | $450.00 | $436.00 | $303.00 | $444.96 | $475.00 |
| 76 | Remove SM RD SN sup&AM (644-7073) | EACH | 24 | $94.00 | $84.00 | $90.00 | $105.00 | $101.00 | $104.03 | $111.00 |
| 77 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 7 | $24.00 | $36.75 | $35.00 | $25.00 | $35.00 | $25.75 | $27.50 |
| 78 | Install object marker assembly (OM-2Z)(WFLX)SRFHH(BI) (658-7261) | EACH | 31 | $400.00 | $147.00 | $150.00 | $275.00 | $141.00 | $275.01 | $295.00 |
| 79 | Install OM SM RD sign (1-OM-PW)Y (658-7317) | EACH | 10 | $25.00 | $21.00 | $80.00 | $56.00 | $20.00 | $55.62 | $60.00 |
| 80 | Install OM SM RD sign (1-OM-PW)R (658-7318) | EACH | 2 | $25.00 | $21.00 | $80.00 | $56.00 | $20.00 | $55.62 | $60.00 |
| 81 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 61,520 | $0.50 | $0.26 | $0.25 | $0.27 | $0.25 | $0.26 | $0.28 |
| 82 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 3,942 | $1.00 | $2.36 | $3.00 | $1.00 | $1.00 | $2.00 | $2.20 |
| 83 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 1,904 | $0.50 | $2.50 | $1.50 | $1.00 | $1.00 | $1.00 | $2.65 |
| 84 | Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410) | LF | 34,764 | $0.50 | $0.53 | $0.55 | $0.55 | $0.51 | $0.52 | $0.80 |
| 85 | Reflectorized pavement marking type I (Y)6"(broken)(090MIL) (666-7419) | LF | 1,451 | $1.50 | $0.58 | $0.55 | $0.60 | $0.56 | $0.57 | $0.90 |
| 86 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 29,309 | $1.50 | $0.53 | $0.55 | $0.55 | $0.51 | $0.52 | $0.80 |
| 87 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 566 | $4.00 | $5.51 | $6.00 | $5.75 | $5.30 | $5.41 | $6.05 |
| 88 | Bonding course (3007-7001) | GAL | 2,722 | $5.00 | $6.30 | $4.50 | $7.00 | $4.75 | $5.00 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 3, 2026. Compiled by Mirage Metrics.