TxDOT contract A00206629 bid tabulation

Intersection Improvements With Right And/Or Left Turn Lanes, SH 90 (0.16 Mi N of FM 244 to 0.31 Mi S of FM 244). Let by Texas DOT on June 2, 2026, Grimes, Bryan District. 7 bids received; low bid $1,241,183 by Larry Young Paving, Inc., -2.6% against the engineer's estimate of $1,274,704.

Owner
Texas DOT
Letting
02 JUN 2026
Pay items
78
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Larry Young Paving, Inc.$1,241,183Low-3.0%
2Knife River Corporation - South$1,252,642+1.0%-2.0%
3Big Creek Construction, LTD.$1,279,779+3.0%0.0%
4Cornerstone Paving and Construction, L.L.C.$1,335,711+8.0%+5.0%
5Forde Construction Company, Inc.$1,396,390+13%+10%
6Brazos Paving, Inc.$1,405,648+13%+10%
7Acme Bridge Company, Inc.$1,708,701+38%+34%
TxDOT contract A00206629: bids by rank

Engineer's estimate: $1,274,704.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Larry Young Paving, Inc.2. Knife River Corporation - South3. Big Creek Construction, LTD.4. Cornerstone Paving and Construction, L.L.C.5. Forde Construction Company, Inc.6. Brazos Paving, Inc.
1Remove (14"-18") TRT/untrt base & asphalt pavement (105-7014)SY508$12.00$3.75$15.00$30.00$18.50$49.00$22.10
2Excavation (roadway) (110-7001)CY1,555$43.00$16.00$10.00$25.00$32.00$13.00$7.35
3Embankment (final)(DC)(type C) (132-7006)CY1,550$15.00$13.00$5.00$25.00$32.00$23.00$14.10
4Backfill (type A) (134-7001)STA27.50$215.00$320.00$168.00$185.00$450.00$650.00$958.80
5Furn & place topsoil (4") (160-7002)SY7,781$2.98$1.50$2.20$1.00$3.50$2.50$1.45
6Broadcast seed (permanent_rural_sand) (164-7001)SY7,781$0.20$0.50$0.40$0.42$0.38$0.40$0.47
7Broadcast seed (temporary_warm) (164-7005)SY3,890$0.55$0.25$0.30$0.28$0.25$0.27$0.31
8Broadcast seed (temporary_cool) (164-7006)SY3,890$0.42$0.25$0.30$0.28$0.25$0.27$0.31
9Vegetative watering (168-7001)TGL77$99.57$34.00$45.00$40.00$25.00$115.00$60.00
10Soil retention blankets (CL 1) (type B) (169-7043)SY472$6.70$1.50$1.30$2.00$1.25$2.00$1.55
11FL BS (compacted in place)(type A GR 1-2) (14") (247-7353)SY3,774$35.00$53.00$49.00$40.00$60.00$41.00$46.10
12Lime (com or QK)(slurry) or QK(dry) (260-7001)TON12$552.19$410.00$387.00$375.00$350.00$375.00$394.40
13Lime TRT (subgrade) (8") (260-7020)SY1,053$3.50$18.00$26.50$12.00$6.00$13.00$11.55
14Cement (275-7001)TON52$251.00$200.00$239.00$250.00$350.00$335.00$267.75
15Cement TRT (subgrade) (8") (275-7018)SY4,553$5.00$4.75$4.00$4.50$6.00$6.50$2.70
16Emuls asphalt (BS or subgr TRT)(CSS-1H) (314-7004)GAL755$3.32$7.75$3.00$4.00$5.00$6.00$12.20
17SP mixes SP-B PG64-22 (344-7001)TON831$100.00$120.00$131.00$125.00$133.00$153.00$136.90
18SP mixes SP-C sac-A PG70-22 (344-7020)TON1,863$151.16$140.00$134.00$145.00$142.00$167.00$143.00
19Tack coat (344-7077)GAL2,072$4.75$5.25$4.40$4.75$5.00$6.00$4.80
20Plane & text asphalt concrete pavement(0" to 2") (354-7002)SY1,956$2.59$5.00$3.00$4.00$2.00$10.00$6.00
21Plane & text asphalt concrete pavement(0" to 4") (354-7004)SY503$2.59$18.00$8.00$15.50$5.00$34.00$11.85
22Temporary special shoring (403-7001)SF875$29.56$25.00$38.00$40.00$40.00$40.00$47.65
23Drilled shaft (roadway illumination pole) (30 in) (416-7040)LF24$357.99$280.00$144.50$357.50$135.00$150.00$164.30
24Riprap (concrete) (CL B) (4 in) (432-7007)CY1$651.70$960.00$1,709.00$880.00$800.00$990.00$1,944.50
25Riprap (stone common)(grout)(18 in) (432-7039)CY11$247.03$200.00$217.00$220.00$200.00$248.00$470.00
26Riprap (stone protection)(24 in) (432-7045)CY28$203.50$170.00$272.00$275.00$250.00$309.00$300.00
27Concrete box culvert (10 FT X 5 FT) (462-7033)LF13$1,229.08$2,000.00$1,087.00$1,100.00$1,500.00$1,235.00$1,760.00
28RC pipe (CL III)(18 in) (464-7003)LF96$92.90$79.00$71.00$71.50$65.00$80.00$95.70
29RC pipe (CL III)(24 in) (464-7005)LF48$130.33$96.00$141.00$143.00$130.00$160.00$123.65
30Wingwall (PW - 1) (HW=7 FT) (466-7177)EACH1$26,411$25,000$17,390$17,600$22,000$19,000$20,125
31Wingwall (PW - 1) (HW=11 FT) (466-7181)EACH1$66,815$50,000$45,651$46,200$50,000$51,000$30,750
32Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH6$1,269.78$1,700.00$1,033.00$1,045.00$1,250.00$1,200.00$2,140.00
33Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH2$2,218.75$2,700.00$2,717.00$2,750.00$3,000.00$3,000.00$2,950.00
34Removing structure (set) (496-7004)EACH6$500.00$360.00$652.00$660.00$1,500.00$740.00$380.00
35Removing structure (headwall) (496-7006)EACH2$2,635.56$2,800.00$1,630.00$1,650.00$2,500.00$1,900.00$4,600.00
36Removing structure (pipe) (496-7037)EACH4$1,072.50$1,200.00$1,305.00$1,320.00$1,200.00$1,500.00$614.00
37Mobilization (500-7001)LS1$110,000$121,000$142,610$125,000$85,000$139,000$111,970
38Barricades, signs and traffic handling (502-7001)MO5$13,371$3,900.00$4,785.00$5,000.00$2,100.00$7,300.00$25,542
39Portable changeable message sign (503-7002)EACH3$5,700.00$1,200.00$4,367.00$10,250$12,000$2,000.00$2,658.00
40TMA (stationary) (505-7001)DAY65$180.00$250.00$582.00$210.00$350.00$200.00$620.00
41TMA (mobile operation) (505-7003)DAY2$167.50$650.00$943.00$500.00$350.00$400.00$1,090.00
42Rock filter dams (install) (type 2) (506-7002)LF260$39.20$45.00$38.00$38.50$35.00$37.00$43.30
43Rock filter dams (install) (type 3) (506-7003)LF20$90.21$83.00$71.00$71.50$65.00$68.00$81.00
44Rock filter dams (remove) (506-7011)LF280$11.70$13.00$11.00$11.00$10.00$10.50$12.40
45Temporary sediment control fence (install) (506-7039)LF1,250$6.05$4.50$4.00$3.85$3.50$3.70$4.35
46Temporary sediment control fence (remove) (506-7041)LF1,250$2.25$1.25$1.00$1.10$1.00$1.05$1.25
47Intersections (ACP) (530-7002)SY195$35.00$62.00$90.00$65.00$20.00$134.00$93.00
48Driveways (surface treat) (530-7016)SY563$38.18$39.00$47.50$47.00$15.00$30.00$48.75
49Mill rumble strips (asphalt) (shoulder) (533-7001)LF5,395$0.75$0.75$0.60$0.96$1.50$0.85$1.22
50Mill rumble strips (asphalt) (centerline) (533-7002)LF4,024$0.75$1.00$0.60$0.96$1.50$0.85$1.22
51Mailbox install-S (TWW-post) type 4 (560-7008)EACH4$300.00$450.00$636.00$530.20$500.00$371.00$638.00
52In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124)EACH3$5,490.90$7,400.00$8,456.00$7,700.00$8,500.00$8,254.00$9,620.00
53Conduit (PVC) (schedule 40) (2") (618-7030)LF205$20.00$13.00$13.25$16.50$13.00$13.00$15.10
54Conduit (PVC) (schedule 40) (2") (bore) (618-7031)LF210$30.00$23.00$19.00$38.50$19.00$18.50$21.60
55Electrical conductor (no.8) insulated (620-7008)LF1,245$3.00$2.50$2.50$3.85$3.00$2.50$2.90
56Ground box type D (162922)W/apron (624-7008)EACH4$2,600.00$1,600.00$1,340.00$1,760.00$1,500.00$1,300.00$1,525.00
57Elc SRV type D 120/240 070(NS)SS(E)SP(O) (628-7191)EACH1$9,287.50$8,500.00$11,297$7,150.00$15,000$11,000$12,852
58Aluminum signs (type A) (636-7001)SF39$62.15$34.00$34.00$38.50$35.00$33.00$31.00
59Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH10$854.19$670.00$727.00$818.40$800.00$849.00$828.00
60Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031)EACH1$1,174.17$860.00$1,630.00$1,698.40$1,750.00$955.00$1,100.00
61Install small roadside sign support and assembly TYS80(1)SA(U-WC) (644-7035)EACH2$1,260.00$1,500.00$1,630.00$1,486.10$1,550.00$1,060.00$1,903.00
62Remove SM RD SN sup&AM (644-7073)EACH13$141.90$110.00$163.00$194.70$200.00$106.00$160.75
63Install object marker assembly (OM-2Z)(WFLX)GND (658-7058)EACH2$96.50$32.00$120.00$62.70$60.00$106.00$124.00
64Remove delin & object marker assms (658-7078)EACH2$24.50$110.00$120.00$27.50$30.00$5.30$6.20
65Install OM SM RD sign (1-OM-PW)R (658-7318)EACH1$105.00$32.00$120.00$5.78$10.00$40.00$124.00
66Work zone pavement marking non-removing (W)24"(solid) (662-7017)LF20$5.00$14.00$11.00$11.00$20.00$10.61$12.40
67Work zone pavement marking SHT terminal (tab)type Y (662-7113)EACH298$1.50$0.75$1.00$1.50$2.00$2.00$1.55
68Reflectorized pavement marking type I (W)8"(broken)(100MIL) (666-7015)LF250$3.50$2.50$1.60$1.65$2.00$1.60$2.80
69Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF1,356$1.05$1.75$1.60$1.65$1.15$1.60$2.20
70Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF20$7.00$17.00$11.00$11.00$18.00$11.00$8.70
71Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF4,390$1.01$1.50$1.00$1.10$1.00$1.05$0.70
72Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF3,663$1.01$1.50$1.00$1.10$1.00$1.05$1.55
73Prefabricated PM type C (W)(arrow) (668-7091)EACH4$238.60$320.00$272.00$275.00$450.00$265.00$330.00
74Prefabricated PM type C (W)(word) (668-7103)EACH4$261.35$410.00$272.00$275.00$400.00$265.00$394.00
75Reflectorized pavement marker type I-C (672-7002)EACH73$8.00$6.25$6.50$6.60$8.50$6.40$9.90
76Reflectorized pavement marker type II-A-A (672-7004)EACH408$5.98$6.25$6.50$6.60$8.50$6.40$9.90
77Vehicle signal section (12")LED(yel) (682-7003)EACH6$240.55$230.00$462.50$330.00$450.00$451.00$526.00
78Install RDSD FLSH BCN assembly (solar PWRD) (685-7004)EACH3$8,704.42$6,800.00$6,467.00$11,000$6,500.00$6,300.00$7,360.00
TxDOT contract A00206629: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of June 2, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy