TxDOT contract A00206665 bid tabulation

Hazard Elimination & Safety, SL 517 (1.27 MILES EAST OF US 277 to 1.74 MILES EAST OF US 277). Let by Texas DOT on June 5, 2025, Dimmit, Laredo District. 6 bids received; low bid $1,400,125 by Hunter Industries, LTD., -17% against the engineer's estimate of $1,691,050.

Owner
Texas DOT
Letting
05 JUN 2025
Pay items
80
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Hunter Industries, LTD.$1,400,125Low-17%
2LCR Total Transport LLC$1,460,752+4.0%-14%
3Anderson Columbia Co., Inc.$1,498,487+7.0%-11%
4Texas Materials Group, Inc.$1,691,822+21%0.0%
5J. Carroll Weaver, Inc.$1,779,995+27%+5.0%
6CK Newberry, LLC$1,782,173+27%+5.0%
TxDOT contract A00206665: bids by rank

Engineer's estimate: $1,691,050.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Hunter Industries, LTD.2. LCR Total Transport LLC3. Anderson Columbia Co., Inc.4. Texas Materials Group, Inc.5. J. Carroll Weaver, Inc.6. CK Newberry, LLC
1Preparing row (100-7002)STA25$2,000.00$1,605.06$3,335.00$850.00$5,600.00$493.73$1,000.00
2Removing concrete (miscellaneous) (104-7046)SY63$275.00$16.70$28.25$48.00$42.00$44.39$50.00
3Remove (7") TRT/untrt base & asphalt pavement (105-7027)SY254$50.00$14.50$10.00$47.00$30.00$26.12$40.00
4Remove stab base and asphalt pavement (6"-20") (105-7123)SY560$20.00$11.14$17.00$41.00$27.00$26.12$30.00
5Excavation (roadway) (110-7001)CY1,425$20.00$73.48$17.00$34.00$36.00$26.12$30.00
6Backfill (type A) (134-7001)STA25$550.00$161.50$316.00$380.00$800.00$395.05$200.00
7Broadcast seed (permanent_rural_sand) (164-7001)SY2,855$2.00$0.84$0.40$1.00$0.84$3.33$0.85
8Drill seed (temporary_warm_cool) (164-7015)SY2,855$2.00$0.77$0.25$0.85$0.77$3.33$0.77
9FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176)CY733$130.00$83.82$72.50$105.00$131.00$127.54$135.00
10Lime (commercial lime slurry) (260-7004)TON34$400.00$341.00$341.00$490.00$415.00$442.96$400.00
11Lime TRT (existing material)(6") (260-7006)SY2,267$20.00$4.48$6.25$9.00$11.50$11.94$12.00
12Prime coat (MC-30) (310-7004)GAL440$7.00$6.40$6.00$7.00$9.80$8.34$10.00
13D-GR HMA type-B sac-B PG70-22 (341-7007)TON642$150.00$117.30$153.50$120.00$130.00$183.15$175.00
14D-GR HMA type-C sac-A PG76-22 (341-7031)TON368$235.00$132.70$175.00$156.00$186.00$215.34$200.00
15Plane & text asphalt concrete pavement(0" to 2") (354-7002)SY1,983$12.00$3.52$2.25$6.00$5.40$14.46$5.00
16Cut & restoring pavement (400-7006)SY74$280.00$88.56$155.00$300.00$195.00$210.90$150.00
17Cem stabil BKFL (400-7010)CY188$250.00$243.53$255.00$160.00$220.00$163.17$250.00
18Trench excavation protection (402-7001)LF110$15.00$13.28$65.00$14.00$17.00$9.99$50.00
19Temporary special shoring (403-7001)SF740$30.00$27.67$32.50$27.00$25.00$21.09$35.00
20Drilled shaft (roadway illumination pole) (30 in) (416-7040)LF96$350.00$278.18$408.00$330.00$275.00$305.25$300.00
21Riprap (concrete)(CL B) (432-7005)CY4.20$2,500.00$1,921.30$1,195.00$770.00$2,250.00$632.70$1,500.00
22Riprap (mow strip)(4 in) (432-7013)CY59$540.00$862.10$825.00$550.00$840.00$656.01$750.00
23RC pipe (CL III)(18 in) (464-7003)LF36$250.00$127.30$91.00$135.00$207.00$103.23$200.00
24RC pipe (CL III)(30 in) (464-7007)LF296$110.00$166.04$158.50$190.00$160.00$155.40$150.00
25Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH2$4,500.00$1,992.53$2,390.00$2,000.00$3,350.00$1,959.15$4,000.00
26Set (type II) (30 in) (RCP) (4: 1) (C) (467-7346)EACH8$2,200.00$3,099.49$5,760.00$4,000.00$3,900.00$3,445.44$5,000.00
27Removing structure (pipe) (496-7007)LF380$30.00$22.14$25.50$24.00$29.00$16.65$50.00
28Mobilization (500-7001)LS1$153,732$157,835$142,000$149,000$169,000$222,238$175,000
29Barricades, signs and traffic handling (502-7001)MO5$12,000$3,136.84$2,590.00$2,000.00$10,000$13,320$10,000
30Portable changeable message sign (503-7002)EACH2$12,000$8,118.75$8,925.00$12,000$13,000$8,325.00$10,000
31TMA (stationary) (505-7001)DAY90$200.00$162.38$305.00$250.00$115.00$210.90$325.00
32TMA (mobile operation) (505-7003)DAY10$500.00$541.25$484.00$800.00$520.00$210.90$350.00
33Rock filter dams (install) (type 1) (506-7001)LF180$85.00$44.60$65.00$48.00$44.60$27.75$50.00
34Rock filter dams (remove) (506-7011)LF180$30.00$12.80$16.50$14.00$12.80$27.75$15.00
35Construction exits (install) (type 2) (506-7021)SY224$75.00$81.90$54.50$82.00$60.00$15.54$15.00
36Construction exits (remove) (506-7024)SY224$25.00$33.55$16.50$34.00$15.00$16.65$5.00
37Temporary sediment control fence (install) (506-7039)LF2,567$7.00$4.00$4.25$5.00$4.00$4.44$10.00
38Temporary sediment control fence (remove) (506-7041)LF2,567$3.50$0.90$1.25$1.00$0.90$2.22$2.00
39One-way traffic control (flagger cont) (510-7001)HR60$100.00$89.60$133.00$80.00$90.00$49.95$100.00
40One-way traffic control (pilot car) (510-7002)HR16$120.00$117.60$150.00$240.00$155.00$160.95$200.00
41One-way traffic control (port traffic signal) (510-7003)MO1$10,000$5,196.00$10,000$14,000$11,000$15,973$15,000
42Portable concrete traffic barrier (des source)(single slope)(type 1) (512-7013)LF2,700$30.00$22.68$19.50$28.00$25.00$33.68$25.00
43PTB (move)(single slope)(type 1) or (steel) (512-7082)LF480$14.00$16.88$12.25$16.00$17.00$33.68$35.00
44PTB (stockpile)(single slope)(type 1) or (steel) (512-7083)LF2,700$18.00$17.26$16.50$15.00$24.00$33.68$25.00
45Driveways (ACP) (530-7010)SY574$100.00$48.84$56.75$120.00$123.00$94.35$100.00
46Mill rumble strips (asphalt) (shoulder) (533-7001)LF2,528$2.50$0.60$0.65$1.00$1.11$1.67$5.00
47Mill rumble strips (asphalt) (centerline) (533-7002)LF2,521$2.50$0.45$0.50$1.00$0.97$1.67$5.00
48Metal W-beam guard fence (timber post) (540-7001)LF825$30.00$23.36$25.40$25.00$38.00$32.19$30.00
49Guardrail end treatment (install) (544-7001)EACH4$3,500.00$3,207.00$3,480.00$3,500.00$3,200.00$3,447.66$4,000.00
50Crash cushion attenuator (move & reset) (545-7002)EACH4$2,000.00$750.00$815.00$900.00$1,050.00$2,081.25$1,000.00
51Crash cushion attenuator (remove) (545-7004)EACH10$1,800.00$750.00$815.00$900.00$800.00$1,166.61$1,000.00
52Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH10$8,500.00$8,300.00$9,025.00$9,000.00$8,800.00$10,112$10,000
53Relocate existing mailbox (560-7012)EACH1$375.00$900.00$705.00$1,000.00$750.00$333.00$1,000.00
54In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124)EACH12$4,250.00$4,956.74$6,850.00$5,400.00$4,900.00$5,439.00$6,000.00
55Conduit (PVC) (schedule 40) (2") (618-7030)LF2,231$13.00$15.17$13.00$20.00$15.00$16.65$20.00
56Conduit (PVC) (schedule 80) (2") (bore) (618-7055)LF207$28.00$40.46$29.50$22.00$40.00$44.40$50.00
57Electrical conductor (no.8) bare (620-7007)LF2,438$2.50$1.67$2.50$2.50$1.65$1.83$2.00
58Electrical conductor (no.8) insulated (620-7008)LF4,876$3.00$1.77$2.90$3.00$1.75$1.94$2.00
59Ground box type A (122311)W/apron (624-7002)EACH1$1,300.00$1,315.05$1,630.50$1,400.00$1,300.00$1,443.00$1,500.00
60Elc SRV type A 120/240 060(NS)SS(E)SP(O) (628-7009)EACH1$8,550.00$6,979.90$10,850$15,000$6,900.00$7,659.00$8,000.00
61Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH2$1,100.00$900.00$978.00$1,000.00$900.00$1,110.00$1,000.00
62Remove SM RD SN sup&AM (644-7073)EACH10$150.00$110.00$120.00$120.00$110.00$83.25$200.00
63Isrsa type 10BWG(1)SA(P) (excluding sign) (644-7088)EACH10$400.00$325.00$355.00$350.00$325.00$888.00$500.00
64Install delineator assembly (D-SW)SZ 1(WFLX)GF2(BI) (658-7002)EACH19$35.00$55.00$60.00$60.00$55.00$24.42$100.00
65Install object marker assembly (OM-2Z)(WFLX)GND (658-7058)EACH6$200.00$125.00$136.00$135.00$125.00$73.26$150.00
66Remove delin & object marker assms (658-7078)EACH4$40.00$45.00$49.00$50.00$45.00$210.90$50.00
67Work zone pavement marking removing (W)6"(solid) (662-7068)LF3,746$2.00$0.78$0.85$0.90$0.78$6.66$2.00
68Work zone pavement marking removing (W)24"(solid) (662-7077)LF24$18.00$50.00$54.00$55.00$50.00$22.20$20.00
69Reflectorized pavement marking type I (Y)12"(solid)(100MIL) (666-7117)LF65$6.00$5.00$5.50$6.00$5.00$16.65$8.00
70Pavement sler 6" (666-7347)LF11,022$0.35$0.54$0.60$0.60$0.54$1.11$0.75
71Pavement sler 12" (666-7350)LF65$4.50$5.00$5.50$6.00$5.00$16.65$2.00
72Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF5,019$1.00$1.55$1.75$1.70$1.55$1.11$1.00
73Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF6,003$1.50$1.55$1.75$1.70$1.55$1.11$1.00
74Reflectorized pavement marker type II-A-A (672-7004)EACH200$8.00$7.50$8.25$9.00$7.50$6.66$6.00
75Eliminating existing PM & markers (6") (677-7002)LF5,140$1.50$0.40$0.50$0.50$0.40$2.61$1.00
76Pavement surface preparation for marking (6") (678-7002)LF11,022$0.15$0.02$0.05$0.05$0.02$0.17$0.50
77Pavement surface preparation for marking (12") (678-7006)LF65$0.12$1.00$1.10$1.00$1.00$0.33$1.00
78Bonding course (3007-7001)GAL645$10.00$3.47$7.00$6.00$4.15$7.77$8.00
79Lead LED chevron (6068-7001)EACH2$3,000.00$3,945.16$2,446.00$2,500.00$2,250.00$4,329.00$5,000.00
80LED chevron (6068-7003)EACH18$3,000.00$2,832.42$2,011.00$2,000.00$1,850.00$3,108.00$5,000.00
TxDOT contract A00206665: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of June 5, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy