TxDOT contract A00207610 bid tabulation
Hazard Elimination & Safety, FM 372 (0.25 mi W of CR 294 to FM 3496). Let by Texas DOT on February 4, 2026, Cooke, Wichita Falls District. 7 bids received; low bid $5,255,697 by Overland Corporation, -12% against the engineer's estimate of $5,976,727.
- Owner
- Texas DOT
- Letting
- 04 FEB 2026
- Pay items
- 107
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Overland Corporation | $5,255,697 | Low | -12% |
| 2 | Eurovia Atlantic Coast LLC | $6,499,041 | +24% | +9.0% |
| 3 | Jagoe-Public Company | $6,674,167 | +27% | +12% |
| 4 | Foutsco Paving Company, LLC | $6,851,608 | +30% | +15% |
| 5 | Austin Bridge & Road Services, LP | $7,793,459 | +48% | +30% |
| 6 | Garret Shields Infrastructure | $7,857,858 | +50% | +31% |
| 7 | Peachtree Construction, LTD. | $7,981,359 | +52% | +34% |
Engineer's estimate: $5,976,727.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Overland Corporation | 2. Eurovia Atlantic Coast LLC | 3. Jagoe-Public Company | 4. Foutsco Paving Company, LLC | 5. Austin Bridge & Road Services, LP | 6. Garret Shields Infrastructure |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparation row (tree remove) (0"-12" diameter) (100-7003) | EACH | 7 | $400.00 | $725.00 | $500.00 | $1,000.00 | $750.00 | $725.00 | $500.00 |
| 2 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 3 | $800.00 | $1,850.00 | $850.00 | $3,000.00 | $1,500.00 | $1,820.00 | $1,500.00 |
| 3 | Preparation row (tree prune and trim) (100-7010) | STA | 128 | $2,500.00 | $417.00 | $300.00 | $420.00 | $250.00 | $417.00 | $2,000.00 |
| 4 | Removing concrete (riprap) (104-7006) | SY | 21 | $23.75 | $71.00 | $50.00 | $20.00 | $23.75 | $40.00 | |
| 5 | Removing concrete (driveways) (104-7011) | SY | 70 | $31.30 | $34.00 | $32.00 | $25.00 | $31.30 | $40.00 | |
| 6 | Removing concrete (curb) (104-7016) | LF | 820 | $16.20 | $18.00 | $5.00 | $8.00 | $15.00 | $20.00 | |
| 7 | Excavation (roadway) (110-7001) | CY | 1,925 | $20.00 | $37.00 | $43.00 | $75.00 | $6.00 | $40.00 | $30.00 |
| 8 | Excavation (channel) (110-7002) | CY | 18 | $17.00 | $150.00 | $100.00 | $40.00 | $128.11 | $40.00 | |
| 9 | Embankment (final)(OC)(type B) (132-7003) | CY | 9,166 | $25.00 | $25.00 | $45.00 | $55.00 | $13.00 | $50.00 | $50.00 |
| 10 | Backfill (type B) (134-7002) | STA | 78 | $150.00 | $159.00 | $350.00 | $220.00 | $200.00 | $229.76 | $150.00 |
| 11 | Broadcast seed (temporary_warm) (164-7005) | SY | 31,711 | $0.20 | $0.15 | $0.11 | $0.05 | $0.10 | $0.11 | $0.10 |
| 12 | Broadcast seed (temporary_cool) (164-7006) | SY | 31,711 | $0.20 | $0.15 | $0.16 | $0.05 | $0.01 | $0.11 | $0.10 |
| 13 | Drill seed (permanent_rural_sand) (164-7009) | SY | 63,409 | $0.15 | $0.23 | $0.16 | $0.20 | $0.15 | $0.18 | $0.10 |
| 14 | Vegetative watering (168-7001) | TGL | 544.50 | $25.00 | $25.00 | $55.00 | $100.00 | $40.00 | $52.00 | $10.00 |
| 15 | Cement (275-7001) | TON | 411 | $270.00 | $245.00 | $225.00 | $250.00 | $225.00 | $350.15 | $250.00 |
| 16 | Cement TRT (existing material)(8") (275-7003) | SY | 28,335 | $4.00 | $2.50 | $4.50 | $7.00 | $5.00 | $5.59 | $8.00 |
| 17 | Prime coat (MC-30) (310-7004) | GAL | 7,084 | $5.25 | $3.65 | $7.65 | $1.50 | $0.10 | $4.09 | $6.20 |
| 18 | Emuls asphalt (erosion control)(MS-2) (314-7012) | GAL | 6,294 | $3.50 | $2.00 | $3.50 | $1.50 | $0.10 | $1.80 | $6.50 |
| 19 | D-GR HMA type-B PG64-22 (341-7001) | TON | 5,194 | $98.00 | $88.00 | $105.00 | $90.00 | $150.00 | $130.00 | $170.00 |
| 20 | D-GR HMA type-C PG64-22 (level-UP) (341-7018) | TON | 1,668 | $125.00 | $105.00 | $150.00 | $100.00 | $155.00 | $140.00 | $200.00 |
| 21 | D-GR HMA type-C sac-B PG70-28 (341-7028) | TON | 13,310 | $105.00 | $101.50 | $126.00 | $110.00 | $148.00 | $153.00 | $160.00 |
| 22 | Flexible pavement structure repair(5") (351-7004) | SY | 13,524 | $25.00 | $35.00 | $40.50 | $35.00 | $45.00 | $45.00 | $20.00 |
| 23 | Plane & text asphalt concrete pavement(0" to 2") (354-7002) | SY | 3,006 | $2.50 | $5.00 | $7.50 | $7.00 | $3.00 | $2.36 | $8.20 |
| 24 | Cut & restoring pavement (400-7006) | SY | 48 | $75.00 | $152.00 | $255.00 | $210.00 | $55.00 | $108.00 | $350.00 |
| 25 | Flowable backfill (401-7001) | CY | 57 | $175.00 | $302.40 | $280.00 | $500.00 | $250.00 | $302.40 | $200.00 |
| 26 | Trench excavation protection (402-7001) | LF | 91 | $10.00 | $1.08 | $1.00 | $5.00 | $25.00 | $1.08 | $1.00 |
| 27 | Temporary special shoring (403-7001) | SF | 2,551 | $35.00 | $32.40 | $44.00 | $25.00 | $65.00 | $32.40 | $50.00 |
| 28 | Class C concrete (collar) (420-7061) | EACH | 4 | $1,500.00 | $1,944.00 | $1,800.00 | $800.00 | $2,000.00 | $1,944.00 | $1,000.00 |
| 29 | Concrete structure repair (standard) (429-7009) | SF | 7 | $432.00 | $400.00 | $220.00 | $250.00 | $432.00 | $150.00 | |
| 30 | Riprap (mow strip)(5 in) (432-7014) | CY | 48 | $739.80 | $769.00 | $1,000.00 | $650.00 | $848.85 | $600.00 | |
| 31 | Riprap (stone common)(dry)(24 in) (432-7034) | CY | 255 | $225.00 | $253.80 | $329.00 | $190.00 | $383.00 | $253.80 | $200.00 |
| 32 | CMP (gal steel 18 in) (460-7003) | LF | 560 | $95.00 | $59.40 | $55.00 | $70.00 | $75.00 | $59.40 | $80.00 |
| 33 | CMP (gal steel 24 in) (460-7005) | LF | 216 | $115.00 | $75.60 | $70.00 | $90.00 | $85.00 | $75.60 | $120.00 |
| 34 | Concrete box culvert (4 FT X 3 FT) (462-7004) | LF | 127 | $300.00 | $405.00 | $375.00 | $370.00 | $500.00 | $405.00 | $500.00 |
| 35 | Concrete box culvert (3 FT X 2 FT)(extend) (462-7056) | LF | 7 | $1,404.00 | $1,300.00 | $500.00 | $730.00 | $1,404.00 | $500.00 | |
| 36 | RC pipe (CL III)(18 in) (464-7003) | LF | 80 | $91.80 | $85.00 | $80.00 | $90.00 | $91.80 | $80.00 | |
| 37 | RC pipe (CL III)(24 in) (464-7005) | LF | 90 | $104.76 | $97.00 | $100.00 | $105.00 | $104.76 | $120.00 | |
| 38 | Headwall (CH - PW - 0) (diameter= 18 in) (466-7099) | EACH | 1 | $5,540.40 | $5,130.00 | $8,000.00 | $7,250.00 | $6,073.90 | $2,000.00 | |
| 39 | Headwall (CH - PW - 0) (diameter= 24 in) (466-7101) | EACH | 3 | $15,000 | $7,182.00 | $6,650.00 | $6,000.00 | $9,750.00 | $7,715.49 | $3,000.00 |
| 40 | Wingwall (PW - 2) (HW=4 FT) (466-7188) | EACH | 1 | $15,000 | $13,608 | $12,600 | $20,000 | $16,500 | $18,000 | $8,000.00 |
| 41 | Wingwall (PW - 2) (HW=6 FT) (466-7190) | EACH | 1 | $15,660 | $14,500 | $24,000 | $18,500 | $22,000 | $10,000 | |
| 42 | Wingwall (PW - 2) (HW=9 FT) (466-7193) | EACH | 1 | $38,880 | $36,000 | $50,000 | $45,000 | $50,000 | $20,000 | |
| 43 | Wingwall (PW - 2) (HW=10 FT) (466-7194) | EACH | 2 | $63,720 | $59,000 | $60,000 | $65,000 | $80,000 | $30,000 | |
| 44 | Wingwall (PW - 2) (HW=11 FT) (466-7195) | EACH | 1 | $62,640 | $58,000 | $62,000 | $68,500 | $80,000 | $30,000 | |
| 45 | Set (type I)(S= 4 FT)(HW= 4 FT)(4:1)(C) (467-7072) | EACH | 2 | $15,000 | $11,880 | $11,000 | $26,000 | $10,500 | $15,000 | $10,000 |
| 46 | Set (type II) (18 in) (CMP) (6: 1) (P) (467-7304) | EACH | 49 | $1,500.00 | $1,296.00 | $1,200.00 | $2,600.00 | $1,250.00 | $1,296.00 | $1,000.00 |
| 47 | Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306) | EACH | 1 | $1,166.40 | $1,080.00 | $2,300.00 | $1,400.00 | $1,166.40 | $1,500.00 | |
| 48 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 5 | $1,528.20 | $1,415.00 | $2,800.00 | $1,500.00 | $1,528.20 | $1,500.00 | |
| 49 | Set (type II) (24 in) (CMP) (6: 1) (P) (467-7324) | EACH | 8 | $1,800.00 | $1,771.20 | $1,640.00 | $3,100.00 | $1,650.00 | $1,771.20 | $1,500.00 |
| 50 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 1 | $1,598.40 | $1,480.00 | $2,800.00 | $1,650.00 | $1,598.40 | $1,500.00 | |
| 51 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 2 | $1,846.80 | $1,710.00 | $3,200.00 | $1,650.00 | $1,846.80 | $1,500.00 | |
| 52 | Set (type II) (36 in) (RCP) (4: 1) (C) (467-7366) | EACH | 1 | $3,000.00 | $5,400.00 | $5,000.00 | $9,000.00 | $3,500.00 | $5,400.00 | $2,000.00 |
| 53 | Set (removing & reinstall) (467-7472) | EACH | 3 | $500.00 | $540.00 | $500.00 | $900.00 | $700.00 | $840.00 | $500.00 |
| 54 | Removing & RE - lay pipe (18 in) (472-7004) | LF | 57 | $50.00 | $64.80 | $60.00 | $90.00 | $80.00 | $64.80 | $100.00 |
| 55 | Removing & RE - lay pipe (24 in) (472-7006) | LF | 12 | $75.00 | $97.20 | $90.00 | $100.00 | $90.00 | $97.20 | $120.00 |
| 56 | Clean existing culverts (480-7001) | EACH | 7 | $2,500.00 | $3,340.00 | $3,100.00 | $2,000.00 | $3,500.00 | $3,340.00 | $2,000.00 |
| 57 | Removing structure (set) (496-7004) | EACH | 54 | $750.00 | $216.00 | $200.00 | $1,000.00 | $400.00 | $216.00 | $500.00 |
| 58 | Removing structure (wingwall) (496-7005) | EACH | 4 | $972.00 | $900.00 | $8,000.00 | $1,000.00 | $972.00 | $2,000.00 | |
| 59 | Removing structure (headwall) (496-7006) | EACH | 6 | $1,500.00 | $972.00 | $900.00 | $10,000 | $1,000.00 | $972.00 | $2,000.00 |
| 60 | Removing structure (pipe) (496-7007) | LF | 1,009 | $25.00 | $10.80 | $10.00 | $50.00 | $12.00 | $10.80 | $10.00 |
| 61 | Removing structure (box culvert) (496-7008) | LF | 8 | $50.00 | $864.00 | $800.00 | $1,000.00 | $100.00 | $864.00 | $500.00 |
| 62 | Mobilization (500-7001) | LS | 1 | $529,366 | $582,000 | $420,000 | $741,000 | $650,000 | $860,000 | $600,000 |
| 63 | Barricades, signs and traffic handling (502-7001) | MO | 19 | $8,000.00 | $2,000.00 | $20,500 | $20,000 | $20,000 | $30,000 | $5,000.00 |
| 64 | TMA (stationary) (505-7001) | DAY | 353 | $250.00 | $183.33 | $350.00 | $50.00 | $1.00 | $1.00 | $300.00 |
| 65 | TMA (mobile operation) (505-7003) | DAY | 20 | $250.00 | $875.00 | $715.00 | $50.00 | $1.00 | $300.00 | $300.00 |
| 66 | Rock filter dams (install) (type 2) (506-7002) | LF | 150 | $45.00 | $44.60 | $42.00 | $42.00 | $42.00 | $42.00 | $20.00 |
| 67 | Rock filter dams (remove) (506-7011) | LF | 150 | $15.00 | $11.00 | $15.00 | $15.00 | $10.00 | $15.00 | $5.00 |
| 68 | Temporary sediment control fence (install) (506-7039) | LF | 11,185 | $3.95 | $3.39 | $4.22 | $4.25 | $1.00 | $4.22 | $5.00 |
| 69 | Temporary sediment control fence (remove) (506-7041) | LF | 11,185 | $1.00 | $0.84 | $0.75 | $0.80 | $0.50 | $0.75 | $1.00 |
| 70 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 2,670 | $4.75 | $3.74 | $5.00 | $5.00 | $1.00 | $5.00 | $5.00 |
| 71 | Biodegradable erosion control logs (remove) (506-7046) | LF | 2,670 | $1.25 | $0.84 | $1.20 | $1.25 | $0.50 | $1.20 | $1.00 |
| 72 | Driveways (concrete) (530-7006) | SY | 109 | $140.40 | $171.00 | $180.00 | $180.00 | $152.41 | $120.00 | |
| 73 | Driveways (ACP) (530-7010) | SY | 3,905 | $55.00 | $39.00 | $42.00 | $60.00 | $50.00 | $65.00 | $140.00 |
| 74 | Driveways (base) (530-7015) | SY | 3,304 | $25.00 | $19.00 | $23.00 | $22.00 | $35.00 | $45.00 | $15.00 |
| 75 | Turnouts (ACP) (530-7018) | SY | 1,405 | $50.00 | $36.00 | $79.00 | $40.00 | $70.00 | $65.00 | $260.00 |
| 76 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 73,931 | $0.25 | $0.20 | $0.20 | $0.15 | $0.20 | $0.20 | $0.20 |
| 77 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 36,966 | $0.30 | $0.20 | $0.20 | $0.15 | $0.20 | $0.20 | $0.20 |
| 78 | Metal W-beam guard fence (timber post) (540-7001) | LF | 1,400 | $20.89 | $23.00 | $20.00 | $23.00 | $20.25 | $40.00 | |
| 79 | Metal beam guard fence trans (T101) (540-7007) | EACH | 4 | $1,025.64 | $780.00 | $1,000.00 | $780.00 | $1,025.00 | $1,500.00 | |
| 80 | Metal beam guard fence (long span system) (540-7027) | EACH | 2 | $1,025.00 | $1,125.00 | $1,000.00 | $1,125.00 | $1,025.00 | $1,500.00 | |
| 81 | Remove metal beam guard fence (542-7001) | LF | 1,375 | $2.00 | $3.00 | $2.00 | $3.00 | $2.00 | $5.00 | |
| 82 | Remove terminal anchor section (542-7002) | EACH | 8 | $200.64 | $200.00 | $200.00 | $200.00 | $200.00 | $500.00 | |
| 83 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $2,850.00 | $2,950.00 | $2,900.00 | $2,950.00 | $2,850.00 | $3,500.00 | |
| 84 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $200.00 | $250.00 | $200.00 | $250.00 | $200.00 | $500.00 | |
| 85 | Wire fence (type C) (552-7003) | LF | 100 | $14.75 | $60.00 | $15.00 | $54.00 | $30.00 | $30.00 | |
| 86 | Wire fence (remove) (552-7011) | LF | 100 | $2.40 | $10.00 | $2.50 | $16.00 | $10.00 | $1.00 | |
| 87 | Mailbox install-D (TWG-post) type 2 (560-7003) | EACH | 17 | $350.00 | $220.00 | $220.00 | $220.00 | $220.00 | $365.57 | $300.00 |
| 88 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 31 | $300.00 | $190.00 | $190.00 | $190.00 | $190.00 | $335.57 | $300.00 |
| 89 | Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009) | EACH | 28 | $825.00 | $520.00 | $520.00 | $500.00 | $520.00 | $520.00 | $800.00 |
| 90 | Install small roadside sign support and assembly type 10BWG(1)SB(T) (644-7012) | EACH | 10 | $800.00 | $565.00 | $565.00 | $600.00 | $565.00 | $565.00 | $800.00 |
| 91 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 103 | $650.00 | $340.00 | $340.00 | $340.00 | $340.00 | $340.00 | $500.00 |
| 92 | Install small roadside sign support and assembly (inst sign only) (644-7064) | EACH | 14 | $350.00 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 | $800.00 |
| 93 | Remove SM RD SN sup&AM (644-7073) | EACH | 74 | $120.00 | $90.00 | $90.00 | $90.00 | $90.00 | $90.00 | $200.00 |
| 94 | Remove SM RD SN sup&AM (sign only) (644-7075) | EACH | 14 | $50.00 | $50.00 | $50.00 | $50.00 | $50.00 | $50.00 | $100.00 |
| 95 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 22 | $61.00 | $45.00 | $31.00 | $25.00 | $50.00 | $12.00 | |
| 96 | Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059) | EACH | 62 | $125.00 | $59.00 | $59.00 | $60.00 | $59.00 | $59.00 | $35.00 |
| 97 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 4,052 | $0.85 | $1.43 | $1.25 | $2.25 | $1.00 | $1.00 | $2.35 |
| 98 | Pavement sler 6" (666-7347) | LF | 460 | $0.20 | $0.17 | $0.17 | $0.20 | $0.20 | $0.25 | |
| 99 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 74,446 | $0.55 | $0.49 | $0.50 | $0.50 | $0.49 | $0.49 | $0.60 |
| 100 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 9,050 | $0.55 | $0.51 | $0.50 | $0.50 | $0.51 | $0.51 | $0.60 |
| 101 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 37,288 | $0.55 | $0.50 | $0.50 | $0.50 | $0.50 | $0.50 | $0.60 |
| 102 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 200 | $15.00 | $11.00 | $12.75 | $13.00 | $11.00 | $11.00 | $13.00 |
| 103 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 752 | $3.50 | $3.55 | $5.00 | $5.00 | $3.55 | $3.55 | $4.20 |
| 104 | Eliminating existing PM & markers (4") (677-7001) | LF | 460 | $1.00 | $0.34 | $0.30 | $1.00 | $1.00 | $1.20 | |
| 105 | Pavement surface preparation for marking (6") (678-7002) | LF | 460 | $0.30 | $0.01 | $0.01 | $0.30 | $0.30 | $0.35 | |
| 106 | Driftwood removal (735-7060) | CY | 45 | $43.00 | $475.00 | $43.00 | $1,000.00 | $43.00 | $100.00 | |
| 107 | Bonding course (3007-7001) | GAL | 7,604 | $5.00 | $4.20 | $3.50 | $1.00 | $1.00 | $4.00 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 4, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.