TxDOT contract A00214044 bid tabulation
BRIDGE PREVENTATIVE MAINTENANCE, SH0114 (Various BPM maintenance to in the Graham office Area). Let by Texas DOT on October 28, 2025, Archer, Wichita Falls District. 12 bids received; low bid $491,415 by C & W Southern LLC, -23% against the engineer's estimate of $642,276.
- Owner
- Texas DOT
- Letting
- 28 OCT 2025
- Pay items
- 25
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | C & W Southern LLC | $491,415 | Low | -23% |
| 2 | Blacksmith Ventures LLC | $508,754 | +4.0% | -21% |
| 3 | Taylor Contracting LLC | $573,362 | +17% | -11% |
| 4 | Scout 5 Construction LLC | $581,008 | +18% | -10% |
| 5 | Ti-Zack Concrete, LLC | $631,330 | +28% | -2.0% |
| 6 | Structural Integrity Group LLC | $647,702 | +32% | +1.0% |
| 7 | Aad Contracting Inc. | $675,913 | +38% | +5.0% |
| 8 | SCR Civil Construction, LLC | $735,790 | +50% | +15% |
| 9 | Premier Contractors LLC | $744,764 | +52% | +16% |
| 10 | Scott Tucker Construction Company, LLC | $791,610 | +61% | +23% |
| 11 | Ragle Construction, Inc. | $944,736 | +92% | +47% |
| 12 | Pathfield Investments LLC | $1,028,541 | +109% | +60% |
Engineer's estimate: $642,276.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. C & W Southern LLC | 2. Blacksmith Ventures LLC | 3. Taylor Contracting LLC | 4. Scout 5 Construction LLC | 5. Ti-Zack Concrete, LLC | 6. Structural Integrity Group LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7007) | CY | 95 | $30.00 | $35.00 | $100.00 | $100.00 | $30.00 | $17.64 | $200.00 |
| 2 | Excavation (channel) (110-7002) | CY | 195 | $35.00 | $20.00 | $35.00 | $45.00 | $30.00 | $52.92 | $75.00 |
| 3 | Embankment (final)(OC)(type A) (132-7001) | CY | 18 | $35.00 | $20.00 | $100.00 | $60.00 | $100.00 | $135.24 | $140.00 |
| 4 | Cut & restore asphalt paving (400-7008) | SY | 13 | $225.00 | $200.00 | $200.00 | $800.00 | $500.00 | $141.12 | $500.00 |
| 5 | Flowable backfill (401-7001) | CY | 15 | $325.00 | $400.00 | $1,000.00 | $750.00 | $350.00 | $705.60 | $390.00 |
| 6 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 1,463 | $145.00 | $55.00 | $135.00 | $175.00 | $234.00 | $88.20 | $173.00 |
| 7 | Riprap (concrete)(5 in) (432-7002) | CY | 35 | $600.00 | $350.00 | $199.00 | $500.00 | $400.00 | $664.44 | $740.00 |
| 8 | Riprap (concrete)(flume) (432-7012) | CY | 4 | $900.00 | $500.00 | $750.00 | $500.00 | $400.00 | $664.44 | $750.00 |
| 9 | Riprap (stone protection)(12 in) (432-7041) | CY | 458 | $250.00 | $180.00 | $199.00 | $200.00 | $150.00 | $123.48 | $250.00 |
| 10 | Elastomeric bearing (laminated) (434-7002) | EACH | 8 | $2,000.00 | $1,875.00 | $1,500.00 | $1,000.00 | $200.00 | $14,112 | $1,650.00 |
| 11 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 483 | $50.00 | $55.00 | $45.00 | $50.00 | $25.00 | $147.00 | $40.00 |
| 12 | Cleaning and sealing existing joints (CL5) (438-7006) | LF | 120 | $30.00 | $25.00 | $45.00 | $30.00 | $30.00 | $135.24 | $45.00 |
| 13 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 208 | $55.00 | $45.00 | $45.00 | $40.00 | $35.00 | $99.96 | $45.00 |
| 14 | STR steel (pedestal) (442-7010) | LB | 800 | $40.00 | $15.00 | $35.00 | $15.00 | $15.00 | $16.46 | $26.15 |
| 15 | Miscellaneous non-bridge (nbis) (442-7017) | LB | 4.60 | $100.00 | $250.00 | $1.00 | $10.00 | $100.00 | $11,760 | $1,000.00 |
| 16 | Clean existing culverts (480-7001) | EACH | 4 | $2,750.00 | $10,000 | $1.00 | $2,000.00 | $1,000.00 | $1,764.00 | $1,000.00 |
| 17 | Raising existing struct (495-7001) | LS | 1 | $50,000 | $100,000 | $50,000 | $30,000 | $60,000 | $29,400 | $17,000 |
| 18 | Mobilization (500-7001) | LS | 1 | $55,116 | $50,000 | $1.00 | $25,000 | $20,000 | $5,880.00 | $63,000 |
| 19 | Barricades, signs and traffic handling (502-7001) | MO | 4 | $9,000.00 | $1,250.00 | $100.00 | $3,000.00 | $0.01 | $5,880.00 | $2,500.00 |
| 20 | Portable changeable message sign (503-7001) | DAY | 14 | $95.00 | $150.00 | $1,000.00 | $250.00 | $0.01 | $294.00 | $100.00 |
| 21 | TMA (stationary) (505-7001) | DAY | 68 | $200.00 | $350.00 | $375.00 | $100.00 | $0.01 | $176.40 | $1.00 |
| 22 | Driftwood removal (735-7060) | CY | 110 | $80.00 | $30.00 | $10.00 | $100.00 | $50.00 | $64.68 | $200.00 |
| 23 | Cleaning / sweeping (handwork) (738-7105) | SY | 120 | $2.00 | $10.00 | $10.00 | $20.00 | $5.00 | $48.22 | $12.00 |
| 24 | Tree removal (4" - 12" diameter) (752-7005) | EACH | 12 | $450.00 | $150.00 | $1.00 | $450.00 | $100.00 | $529.20 | $600.00 |
| 25 | Concrete CRCK repair(discrete)(rout and seal) (780-7003) | LF | 76 | $50.00 | $50.00 | $75.00 | $66.00 | $50.00 | $47.04 | $50.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 28, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.