TxDOT contract A00216831 bid tabulation
Bridge Maintenance, Various (Various Bridge Locations:Georgetown to Williamson, Travis counties). Let by Texas DOT on March 4, 2026, Travis, Austin District. 13 bids received; low bid $769,928 by BK Field Operations LLC, -25% against the engineer's estimate of $1,033,376.
- Owner
- Texas DOT
- Letting
- 04 MAR 2026
- Pay items
- 36
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | BK Field Operations LLC | $769,928 | Low | -25% |
| 2 | Taylor Bridge LLC | $820,942 | +7.0% | -21% |
| 3 | Garret Shields Infrastructure | $872,420 | +13% | -16% |
| 4 | Icos Management, LLC | $1,002,849 | +30% | -3.0% |
| 5 | Structural Integrity Group LLC | $1,073,202 | +39% | +4.0% |
| 6 | Restek, Inc. | $1,111,783 | +44% | +8.0% |
| 7 | SCR Civil Construction, LLC | $1,113,411 | +45% | +8.0% |
| 8 | Beck-Reit & Sons, LTD. | $1,116,790 | +45% | +8.0% |
| 9 | Blacksmith Ventures LLC | $1,184,230 | +54% | +15% |
| 10 | Road Doctors LLC | $1,184,404 | +54% | +15% |
| 11 | Premier Contractors LLC | $1,238,968 | +61% | +20% |
| 12 | MPB, Inc. | $1,243,584 | +62% | +20% |
| 13 | Myers Concrete Construction, LP | $1,422,863 | +85% | +38% |
Engineer's estimate: $1,033,376.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. BK Field Operations LLC | 2. Taylor Bridge LLC | 3. Garret Shields Infrastructure | 4. Icos Management, LLC | 5. Structural Integrity Group LLC | 6. Restek, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 1 | $1,500.00 | $300.00 | $1,000.00 | $1,000.00 | $2,675.00 | $800.00 | $2,493.76 |
| 2 | Preparation row (tree remove) (24"-36" diameter) (100-7005) | EACH | 1 | $1,200.00 | $800.00 | $1,000.00 | $2,000.00 | $3,745.00 | $800.00 | $3,472.93 |
| 3 | Removing concrete (riprap) (104-7006) | SY | 18 | $200.00 | $150.00 | $25.00 | $20.00 | $268.00 | $140.00 | $77.33 |
| 4 | Flowable backfill (401-7001) | CY | 14 | $700.00 | $800.00 | $400.00 | $300.00 | $856.00 | $1,650.00 | $1,256.32 |
| 5 | Concrete structure repair(clean & coat WTH epoxy) (429-7001) | SF | 30 | $132.00 | $75.00 | $175.00 | $150.00 | $150.00 | $65.00 | $84.58 |
| 6 | Concrete structure repair (epoxy mortar) (429-7002) | SF | 48 | $220.00 | $120.00 | $175.00 | $150.00 | $193.00 | $175.00 | $106.39 |
| 7 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 125 | $327.00 | $200.00 | $300.00 | $200.00 | $214.00 | $308.00 | $198.41 |
| 8 | Concrete structure repair (standard) (429-7009) | SF | 2 | $750.00 | $1,000.00 | $1,000.00 | $150.00 | $268.00 | $875.00 | $600.00 |
| 9 | Riprap (concrete)(4 in) (432-7001) | CY | 3 | $460.00 | $2,000.00 | $700.00 | $1,000.00 | $1,070.00 | $2,300.00 | $1,428.25 |
| 10 | Riprap (stone protection)(12 in) (432-7041) | CY | 10 | $280.00 | $185.00 | $400.00 | $200.00 | $214.00 | $224.00 | $412.28 |
| 11 | Riprap (stone protection)(18 in) (432-7043) | CY | 265 | $185.00 | $185.00 | $200.00 | $180.00 | $203.00 | $233.00 | $228.72 |
| 12 | Riprap (stone protection)(24 in) (432-7045) | CY | 356 | $275.00 | $185.00 | $200.00 | $150.00 | $203.00 | $232.00 | $230.78 |
| 13 | Cleaning and sealing existing joints (438-7001) | LF | 494 | $65.00 | $80.00 | $80.00 | $40.00 | $64.00 | $45.00 | $36.14 |
| 14 | Clean and paint existing STR (ref no. 1) (446-7020) | EACH | 1 | $88,000 | $111,000 | $75,000 | $110,000 | $107,000 | $92,500 | $105,714 |
| 15 | Retrofit rail (add HSS) (451-7052) | LF | 348 | $165.00 | $130.00 | $120.00 | $100.00 | $214.00 | $145.00 | $129.09 |
| 16 | Gabion mattresses (galvanized) (24 in) (459-7009) | SY | 90 | $185.00 | $300.00 | $250.00 | $200.00 | $268.00 | $340.00 | $257.56 |
| 17 | CMP (gal steel 72 in) (460-7014) | LF | 260 | $660.00 | $600.00 | $770.00 | $700.00 | $750.00 | $982.00 | $1,134.70 |
| 18 | Clean existing culverts (480-7002) | CY | 175 | $75.00 | $125.00 | $250.00 | $120.00 | $321.00 | $230.00 | $176.21 |
| 19 | Mobilization (500-7001) | LS | 1 | $102,400 | $80,000 | $50,000 | $100,000 | $65,000 | $100,000 | $174,239 |
| 20 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $7,500.00 | $1.00 | $1.00 | $5,000.00 | $1.00 | $7,000.00 | $5,362.81 |
| 21 | Portable changeable message sign (503-7001) | DAY | 33 | $100.00 | $100.00 | $300.00 | $100.00 | $268.00 | $500.00 | $145.84 |
| 22 | TMA (stationary) (505-7001) | DAY | 100 | $100.00 | $1.00 | $1.00 | $300.00 | $268.00 | $1.00 | $315.58 |
| 23 | TMA (mobile operation) (505-7003) | DAY | 1 | $100.00 | $1.00 | $1,000.00 | $300.00 | $856.00 | $1,000.00 | $1,014.29 |
| 24 | Sandbags for erosion control (506-7035) | EACH | 100 | $10.00 | $12.00 | $10.00 | $2.00 | $21.00 | $5.00 | $7.98 |
| 25 | Litter removal (734-7002) | CYC | 10 | $300.00 | $1.00 | $500.00 | $2,000.00 | $428.00 | $400.00 | $92.80 |
| 26 | Driftwood removal (735-7060) | CY | 85 | $300.00 | $60.00 | $500.00 | $120.00 | $214.00 | $400.00 | $75.54 |
| 27 | Tree removal (12" - 18" diameter) (752-7006) | EACH | 1 | $1,500.00 | $600.00 | $1,000.00 | $500.00 | $2,680.00 | $750.00 | $1,160.00 |
| 28 | Drain inlet cleaning (764-7001) | EACH | 5 | $440.00 | $1,200.00 | $1,000.00 | $200.00 | $4,280.00 | $1,000.00 | $278.40 |
| 29 | Concrete rail repair (miscellaneous) (778-7002) | LF | 30 | $1,100.00 | $250.00 | $120.00 | $400.00 | $642.00 | $275.00 | $264.76 |
| 30 | CNC crack repair (flood)(gravity) (780-7005) | SF | 3 | $15.00 | $200.00 | $1,000.00 | $100.00 | $235.00 | $600.00 | $357.67 |
| 31 | Rep steel bridge member (beam) (784-7002) | EACH | 1 | $3,000.00 | $6,000.00 | $500.00 | $10,000 | $16,050 | $1.00 | $1,791.18 |
| 32 | Bridge joint repair (header) (785-7002) | LF | 116 | $440.00 | $300.00 | $400.00 | $300.00 | $300.00 | $280.00 | $306.91 |
| 33 | Bridge joint repair (armor) (785-7004) | LF | 79 | $634.00 | $475.00 | $300.00 | $400.00 | $642.00 | $730.00 | $284.81 |
| 34 | Concrete beam repair (788-7001) | EACH | 4 | $9,000.00 | $3,000.00 | $3,000.00 | $5,000.00 | $6,420.00 | $1.00 | $6,064.83 |
| 35 | Bent cap/abutment cap cleaning (7001-7002) | EACH | 2 | $8,800.00 | $400.00 | $500.00 | $500.00 | $5,350.00 | $745.00 | $1,160.00 |
| 36 | Bridge beam end cleaning (7001-7003) | EACH | 2 | $300.00 | $500.00 | $500.00 | $500.00 | $5,350.00 | $1,500.00 | $1,160.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of March 4, 2026. Compiled by Mirage Metrics.