Install bridge identification numbers, TxDOT 4171-6001
Low bidders on TxDOT contracts carried a median of $492.64 per EACH for this item, from 07 JAN 2021 to 07 NOV 2024, across 96 low bids. Half of all 438 bids fell between $306.69 and $800.00.
- Owner
- Texas DOT
- Item
- 4171-6001
- Unit
- EACH
- Data through
- 19 NOV 2026
TxDOT has bid this work under more than one code: 41716001 on lettings from 07 JAN 2021 to 10 JUL 2024 (431 bids); 4171-6001 on lettings from 07 NOV 2024 to 07 NOV 2024 (10 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2021 | 28 | 28 | $250.00 | 162 | $413.75 |
| 2022 | 23 | 22 | $400.00 | 94 | $482.64 |
| 2023 | 26 | 26 | $575.00 | 82 | $542.50 |
| 2024 | 20 | 20 | $839.26 | 100 | $726.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| San Antonio District | 31 | $350.00 | 177 | $450.00 |
| Atlanta District | 11 | $400.00 | 56 | $500.00 |
| Bryan District | 9 | $483.08 | 44 | $491.54 |
| Amarillo District | 12 | $500.00 | 41 | $500.00 |
| Lubbock District | 8 | $768.50 | 25 | $528.22 |
| San Angelo District | 6 | $525.00 | 20 | $580.00 |
| Childress District | 4 | $2,264.72 | 17 | $1,600.00 |
| Wichita Falls District | 4 | $585.00 | 11 | $526.50 |
| El Paso District | 3 | $400.00 | 7 | $650.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 24 | $400.00 |
| 2 to 2 | 24 | $492.64 |
| 2 to 6 | 24 | $500.00 |
| 6 to 50 | 24 | $422.37 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Webber, LLC | 16 | 8 (50%) |
| Texas Materials Group, Inc. | 14 | 7 (50%) |
| Hunter Industries, LTD. | 12 | 6 (50%) |
| Acme Bridge Company, Inc. | 10 | 6 (60%) |
| Hodges and Son Construction Company, Inc. | 18 | 5 (28%) |
| J. Lee Milligan, Inc. | 7 | 5 (71%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 07 NOV 2024 | A00200684 | Tyler District | 18 | $1,000.00 | $662.50 | $550.00 | 10 | Olympus Painting Contractors, Inc. | TxDOT |
| 10 JUL 2024 | 07243216 | Tyler District | 18 | $300.00 | $625.00 | $550.00 | 6 | Cross Plus Construction, LLC | TxDOT |
| 09 JUL 2024 | 07243025 | Childress District | 1 | $3,500.00 | $1,320.00 | $1,000.00 | 6 | Skyline Bridge LLC | TxDOT |
| 06 JUN 2024 | 06243201 | San Antonio District | 10 | $768.53 | $633.57 | $500.00 | 4 | Webber, LLC | TxDOT |
| 05 JUN 2024 | 06243021 | Atlanta District | 6 | $950.00 | $975.00 | $1,000.00 | 6 | True Roads, LLC | TxDOT |
| 05 JUN 2024 | 06243051 | Childress District | 1 | $1,000.00 | $1,000.00 | $1,000.00 | 6 | THK Construction LLC | TxDOT |
| 03 MAY 2024 | 05243215 | San Antonio District | 2 | $350.00 | $500.00 | $447.15 | 7 | Relmco, Inc. | TxDOT |
| 05 APR 2024 | 04243213 | Atlanta District | 4 | $1,000.00 | $1,500.00 | $1,000.00 | 2 | A. K. Gillis & Sons, LLC | TxDOT |
| 04 APR 2024 | 04243017 | El Paso District | 1 | $400.00 | $812.50 | $400.00 | 4 | Dan Williams Company | TxDOT |
| 04 APR 2024 | 04243025 | San Antonio District | 2 | $250.00 | $500.00 | $344.00 | 9 | J3 Company, LLC | TxDOT |
| 05 MAR 2024 | 03243010 | Amarillo District | 2 | $2,111.19 | $1,750.00 | $1,100.00 | 4 | Altus Construction LLC | TxDOT |
| 05 MAR 2024 | 03243017 | San Antonio District | 2 | $500.00 | $500.00 | $500.00 | 6 | J3 Company, LLC | TxDOT |
| 02 FEB 2024 | 02243205 | San Antonio District | 4 | $500.00 | $500.00 | $150.00 | 9 | Dan Williams Company | TxDOT |
| 02 FEB 2024 | 02243239 | Lubbock District | 2 | $2,000.00 | $1,905.00 | $500.00 | 3 | Lone Star Dirt & Paving, LTD. | TxDOT |
| 01 FEB 2024 | 02243002 | Lubbock District | 3 | $910.00 | $1,005.00 | $500.00 | 2 | Duininck, Inc. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.