Removing stab base & asphalt pavement (0-6"), TxDOT 105-6043
Low bidders on TxDOT contracts carried a median of $8.35 per SY for this item, from 06 FEB 2020 to 07 NOV 2024, across 50 low bids. Half of all 234 bids fell between $4.74 and $15.00.
- Owner
- Texas DOT
- Item
- 105-6043
- Unit
- SY
- Data through
- 19 NOV 2026
TxDOT prints this item as “REMOVING STAB BASE & ASPH PAV (0-6")”.
TxDOT has bid this work under more than one code: 1056043 on lettings from 06 FEB 2020 to 10 JUL 2024 (230 bids); 105-6043 on lettings from 07 NOV 2024 to 07 NOV 2024 (5 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 4 | 4 | $3.48 | 25 | $4.40 |
| 2021 | 10 | 10 | $6.95 | 61 | $10.00 |
| 2022 | 10 | 10 | $8.88 | 40 | $8.00 |
| 2023 | 13 | 13 | $9.90 | 44 | $10.50 |
| 2024 | 13 | 13 | $9.50 | 64 | $10.52 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 11 | $6.00 | 62 | $9.20 |
| San Antonio District | 3 | $14.70 | 22 | $7.15 |
| Bryan District | 5 | $6.11 | 21 | $8.00 |
| Houston District | 3 | $7.90 | 20 | $7.70 |
| Amarillo District | 5 | $21.86 | 18 | $20.66 |
| Wichita Falls District | 3 | $8.80 | 14 | $4.08 |
| Pharr District | 3 | $3.00 | 13 | $10.00 |
| Fort Worth District | 3 | $9.90 | 11 | $7.00 |
| Odessa District | 3 | $7.75 | 8 | $7.88 |
| El Paso District | 3 | $1.50 | 6 | $3.25 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 38 to 985 | 12 | $14.55 |
| 993 to 2,936 | 13 | $9.70 |
| 2,981 to 7,760 | 12 | $6.88 |
| 7,852 to 112,738 | 13 | $3.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Ti-Zack Concrete, LLC | 8 | 3 (38%) |
| Knife River Corporation - South | 6 | 3 (50%) |
| Big Creek Construction, LTD. | 5 | 3 (60%) |
| FNH Construction, LLC | 12 | 2 (17%) |
| Ed Bell Construction Company | 9 | 2 (22%) |
| Altus Construction LLC | 6 | 2 (33%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 07 NOV 2024 | A00082318 | Bryan District | 1,689 | $4.25 | $8.00 | $8.00 | 5 | Larry Young Paving, Inc. | TxDOT |
| 10 JUL 2024 | 07243208 | San Antonio District | 679 | $14.70 | $12.81 | $10.95 | 8 | Acme Bridge Company, Inc. | TxDOT |
| 06 JUN 2024 | 06243205 | Wichita Falls District | 2,747 | $9.50 | $9.50 | $4.50 | 3 | A. L. Helmcamp, Inc. | TxDOT |
| 06 JUN 2024 | 06243226 | Amarillo District | 7,760 | $24.68 | $17.93 | $20.00 | 4 | Ti-Zack Concrete, LLC | TxDOT |
| 06 JUN 2024 | 06243228 | Fort Worth District | 985 | $10.00 | $11.00 | $7.00 | 2 | Ragle Construction, Inc. | TxDOT |
| 05 JUN 2024 | 06243009 | Bryan District | 7,257 | $5.40 | $7.75 | $5.00 | 6 | Knife River Corporation - South | TxDOT |
| 05 JUN 2024 | 06243025 | Dallas District | 14,053 | $5.70 | $5.70 | $9.50 | 3 | Select Maintenance, L.L.C. | TxDOT |
| 05 JUN 2024 | 06243026 | Tyler District | 2,717 | $9.70 | $20.00 | $10.00 | 9 | 3LW Civil LLC | TxDOT |
| 05 JUN 2024 | 06243058 | Amarillo District | 6,098 | $26.17 | $22.46 | $20.00 | 2 | Ti-Zack Concrete, LLC | TxDOT |
| 02 MAY 2024 | 05243017 | Dallas District | 13,990 | $10.00 | $10.00 | $6.00 | 5 | Jagoe-Public Company | TxDOT |
| 04 APR 2024 | 04243030 | Dallas District | 6,221 | $6.00 | $17.50 | $15.00 | 5 | Baker & Company Construction, LLC | TxDOT |
| 01 FEB 2024 | 02243003 | Wichita Falls District | 2,747 | $8.80 | $9.15 | $4.50 | 2 | Jagoe-Public Company | TxDOT |
| 04 JAN 2024 | 01243005 | Houston District | 696 | $7.90 | $10.02 | $5.00 | 10 | Ser Construction Partners, LLC | TxDOT |
| 06 DEC 2023 | 12233207 | Amarillo District | 4,683 | $20.00 | $21.32 | $10.00 | 5 | Ti-Zack Concrete, LLC | TxDOT |
| 05 DEC 2023 | 12233012 | Amarillo District | 1,095 | $21.86 | $44.87 | $15.00 | 4 | Ti-Zack Concrete, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.