Low bidders on VDOT contracts carried a median of $125.00 per TON for this item, over the 24 months to 28 OCT 2026, across 3 low bids. Half of all 14 bids fell between $85.00 and $240.00.
- Owner
- Virginia DOT
- Item
- 308SD20-0006
- Unit
- TON
- Data through
- 28 OCT 2026
VDOT has bid this work under more than one code: 10099 on lettings from 29 JAN 2002 to 15 DEC 2021 (233 bids); 308SD20-0006 on lettings from 04 FEB 2026 to 22 JUL 2026 (14 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 1 | 1 | $15.00 | 3 | $15.00 |
| 2005 | 1 | 1 | $31.00 | 3 | $32.96 |
| 2008 | 2 | 2 | $25.00 | 5 | $40.00 |
| 2009 | 2 | 2 | $19.43 | 6 | $20.75 |
| 2010 | 4 | 4 | $38.10 | 9 | $41.20 |
| 2011 | 6 | 6 | $41.70 | 12 | $41.09 |
| 2012 | 18 | 18 | $37.75 | 43 | $40.00 |
| 2013 | 9 | 9 | $30.00 | 26 | $30.00 |
| 2014 | 21 | 21 | $35.00 | 48 | $34.00 |
| 2015 | 11 | 11 | $33.00 | 27 | $35.00 |
| 2016 | 12 | 12 | $55.00 | 27 | $45.00 |
| 2017 | 2 | 2 | $84.07 | 3 | $50.00 |
| 2018 | 2 | 2 | $38.00 | 6 | $42.50 |
| 2019 | 2 | 2 | $54.00 | 5 | $53.89 |
| 2020 | 1 | 1 | $35.00 | 2 | $37.50 |
| 2021 | 3 | 3 | $45.00 | 8 | $45.00 |
| 2026 | 3 | 3 | $125.00 | 14 | $150.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Richmond | 46 | $35.25 | 115 | $35.00 |
| Fredericksburg | 15 | $33.00 | 39 | $35.00 |
| Northern Virginia | 11 | $41.20 | 26 | $40.39 |
| Hampton Roads | 8 | $78.82 | 19 | $77.64 |
| Staunton | 8 | $37.50 | 16 | $40.00 |
| Bristol | 6 | $27.23 | 16 | $32.14 |
| Salem | 5 | $35.00 | 14 | $45.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 2 to 90 | 25 | $60.00 |
| 90 to 235 | 25 | $39.52 |
| 238 to 1,184 | 25 | $31.00 |
| 1,427 to 8,183 | 25 | $29.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Branscome Inc. | 33 | 10 (30%) |
| Lee Hy Paving Corporation | 27 | 8 (30%) |
| Colony Construction, Inc. | 17 | 8 (47%) |
| American Infrastructure-Va, Inc. | 17 | 8 (47%) |
| Allan Myers Va, Inc. | 12 | 5 (42%) |
| Curtis Contracting, Inc. | 6 | 4 (67%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 JUL 2026 | C0000120697C01 | Salem | 98.60 | $125.00 | $100.00 | 3 | Crossroads Bridge Inc | VDOT |
| 25 MAR 2026 | C0000121531B68 | Hampton Roads | 51 | $240.00 | $232.22 | 7 | Crofton Construction Services, | VDOT |
| 04 FEB 2026 | C0000127373N01 | Northern Virginia | 30 | $58.00 | $150.00 | 4 | Creative Design Concepts, Inc. | VDOT |
| 15 DEC 2021 | C0000119781N01 | Staunton | 10 | $45.00 | $45.00 | 2 | North Construction, Inc. | VDOT |
| 28 JUL 2021 | C0000000688C02 | Salem | 708 | $30.00 | $30.00 | 3 | Allegheny Construction Company, Inc. | VDOT |
| 26 MAY 2021 | C0000113659C01 | Bristol | 40 | $80.00 | $70.00 | 3 | Makco, Incorporated | VDOT |
| 22 JAN 2020 | C000111370C01B | Salem | 104 | $35.00 | $37.50 | 2 | Allegheny Construction Company, Inc. | VDOT |
| 22 MAY 2019 | C0000110710N01 | Richmond | 100 | $28.00 | $28.00 | 3 | Lee Hy Paving Corporation | VDOT |
| 20 MAR 2019 | C0000111711C01 | Hampton Roads | 6,583 | $80.00 | $66.94 | 2 | Allan Myers Va, Inc. | VDOT |
| 19 DEC 2018 | C0000114191N01 | Staunton | 50 | $45.00 | $60.00 | 3 | M & F Concrete, Inc. | VDOT |
| 26 SEP 2018 | C000105145B671 | Bristol | 380 | $31.00 | $33.00 | 3 | Crossroads Bridge Inc | VDOT |
| 21 JUN 2017 | C000107660N01B | Hampton Roads | 11 | $145.00 | $145.00 | 1 | Branscome Inc. | VDOT |
| 26 APR 2017 | C0000110285N01 | Richmond | 2,384 | $23.14 | $36.57 | 2 | Curtis Contracting, Inc. | VDOT |
| 21 DEC 2016 | C0000108374N01 | Richmond | 247 | $30.00 | $30.00 | 3 | Denton Concrete Services Company | VDOT |
| 28 SEP 2016 | C0000100444B02 | Northern Virginia | 78 | $100.00 | $100.00 | 3 | Fielder'S Choice Enterprises, Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.