VDOT contract C0000119385C01 bid tabulation
Smart scale - turn lane improvements. Let by Virginia DOT on February 25, 2026, Nelson, Lynchburg. 5 bids received; low bid $1,991,223 by Stonewall Bridge, Inc..
- Owner
- Virginia DOT
- Letting
- 25 FEB 2026
- Pay items
- 74
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Stonewall Bridge, Inc. | $1,991,223 | Low |
| 2 | Caton Construction Group, Inc. | $2,367,515 | +19% |
| 3 | A & J Development and Excavation, Inc. | $2,398,881 | +20% |
| 4 | Allegheny Construction Company, Inc. | $2,836,532 | +42% |
| 5 | Independence Excavating, Inc. | $3,275,562 | +64% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Stonewall Bridge, Inc. | 2. Caton Construction Group, Inc. | 3. A & J Development and Excavation, Inc. | 4. Allegheny Construction Company, Inc. | 5. Independence Excavating, Inc. |
|---|---|---|---|---|---|---|---|---|
| 0001-0010 | NS contract construction record documentation of permanent stormwater management facilities (105SX20-0001) | LS | 1 | $20,000 | $2,400.00 | $20,000 | $18,000 | $19,000 |
| 0001-0020 | Clearing and grubbing (301SD20-0001) | LS | 1 | $15,000 | $170,000 | $90,000 | $85,000 | $90,000 |
| 0001-0030 | Bedding matl.aggr.no. 25 or 26 (302SD20-0001) | TON | 37 | $75.00 | $50.00 | $42.00 | $48.00 | $100.00 |
| 0001-0040 | Bedding matl. aggr. no. 57 (302SD20-0002) | TON | 112 | $75.00 | $76.82 | $48.00 | $75.00 | $100.00 |
| 0001-0050 | 15" pipe (302SD20-0023) | LF | 40 | $35.00 | $160.00 | $134.00 | $80.00 | $280.00 |
| 0001-0060 | 15" storm sewer pipe (302SD20-0027) | LF | 340 | $40.00 | $145.00 | $120.00 | $225.00 | $210.00 |
| 0001-0070 | 18" storm sewer pipe (302SD20-0032) | LF | 346 | $70.00 | $185.00 | $130.00 | $230.00 | $230.00 |
| 0001-0080 | 30" storm sewer pipe (302SD20-0051) | LF | 53 | $100.00 | $365.00 | $260.00 | $310.00 | $440.00 |
| 0001-0090 | 48" storm sewer pipe (302SD20-0072) | LF | 190 | $275.00 | $490.83 | $330.00 | $355.00 | $500.00 |
| 0001-0100 | 15" end section ES-1 or 2 (302SD20-0198) | EACH | 2 | $2,500.00 | $2,496.25 | $500.00 | $1,100.00 | $3,900.00 |
| 0001-0110 | Drop inlet DI-5 (302SD20-0446) | EACH | 5 | $8,000.00 | $9,849.62 | $13,500 | $14,000 | $13,000 |
| 0001-0120 | Drop inlet DI-7 (302SD20-0447) | EACH | 2 | $10,000 | $5,311.53 | $6,500.00 | $10,500 | $10,000 |
| 0001-0130 | Regular excavation (303SD20-0001) | CY | 9,100 | $35.00 | $25.00 | $46.00 | $68.00 | $90.00 |
| 0001-0140 | Borrow excavation (303SD20-0007) | CY | 5,852 | $32.00 | $70.09 | $64.00 | $62.00 | $73.00 |
| 0001-0150 | Minor STR. excav. pipe culvert (303SD20-0016) | CY | 632 | $50.00 | $35.75 | $46.00 | $40.00 | $50.00 |
| 0001-0160 | Slope drain (303SD20-0018) | EACH | 10 | $2,000.00 | $2,845.65 | $1,100.00 | $1,200.00 | $3,000.00 |
| 0001-0170 | Check dam rock TY. II (303SD20-0023) | EACH | 33 | $500.00 | $1,245.48 | $120.00 | $840.00 | $1,500.00 |
| 0001-0180 | Siltation control excavation (303SD20-0029) | CY | 1,298 | $1.00 | $13.71 | $2.00 | $0.01 | $25.00 |
| 0001-0190 | Inlet protection type A (303SD20-0030) | EACH | 10 | $500.00 | $357.73 | $120.00 | $660.00 | $980.00 |
| 0001-0200 | Temp. silt fence type B (303SD20-0033) | LF | 933 | $9.00 | $11.61 | $7.00 | $8.00 | $14.00 |
| 0001-0210 | Temp. silt fence type A (303SD20-0034) | LF | 806 | $7.00 | $6.99 | $6.50 | $5.00 | $13.00 |
| 0001-0220 | Aggr. base matl. TY. I no. 21B (308SD20-0012) | TON | 2,189 | $75.00 | $39.40 | $37.00 | $50.00 | $105.00 |
| 0001-0230 | Crusher run aggr. no. 25 or 26 (308SX20-0003) | TON | 86 | $90.00 | $95.00 | $43.00 | $50.00 | $70.00 |
| 0001-0240 | Asphalt concrete TY. IM- 19.0D const (315SD20-0005) | TON | 690 | $145.00 | $136.22 | $130.00 | $148.00 | $135.00 |
| 0001-0250 | Asphalt concrete TY. SM- 9.5D const (315SD20-0008) | TON | 566 | $180.00 | $135.52 | $171.00 | $183.00 | $140.00 |
| 0001-0260 | Asphalt concrete BM-25.0 (315SD20-0010) | TON | 2,330 | $135.00 | $114.81 | $126.00 | $140.00 | $118.00 |
| 0001-0270 | NS saw-cut asph conc full depth (315SX20-0011) | LF | 942 | $12.00 | $10.00 | $10.00 | $7.00 | $6.00 |
| 0001-0280 | NS pavement liquid asphalt coating (pavement marker groove) (316SX20-0004) | SY | 3 | $110.00 | $75.00 | $200.00 | $150.00 | $110.00 |
| 0001-0290 | Underdrain UD-1 (501SD20-0001) | LF | 2,200 | $5.50 | $37.50 | $32.00 | $21.00 | $45.00 |
| 0001-0300 | Outlet pipe (501SD20-0009) | LF | 85 | $30.00 | $98.59 | $32.00 | $36.00 | $210.00 |
| 0001-0310 | Obscuring roadway (508SD20-0001) | UNIT | 0.98 | $5,000.00 | $5,625.00 | $7,500.00 | $4,500.00 | $5,460.00 |
| 0001-0320 | Demo. of pavement flexible (508SD20-0004) | SY | 3,994 | $8.00 | $12.35 | $5.25 | $11.00 | $17.00 |
| 0001-0330 | Flowable backfill (509SD20-0001) | CY | 35.72 | $200.00 | $783.99 | $550.00 | $800.00 | $600.00 |
| 0001-0340 | NS modify exist. inlet (510SX20-0031) | EACH | 1 | $10,000 | $2,402.52 | $3,500.00 | $5,200.00 | $4,230.00 |
| 0001-0350 | Allaying dust (511SD20-0001) | HR | 40 | $1.00 | $383.46 | $25.00 | $90.00 | $150.00 |
| 0001-0360 | Type 3 barricade 8' (512SD20-0013) | EACH | 5 | $300.00 | $499.29 | $480.00 | $700.00 | $1,000.00 |
| 0001-0370 | Temporary sign (512SD20-0014) | SF | 918 | $25.00 | $10.25 | $32.00 | $23.00 | $21.00 |
| 0001-0380 | Truck mounted attenuator (512SD20-0023) | HR | 1,560 | $25.00 | $12.00 | $14.00 | $25.00 | $20.00 |
| 0001-0390 | Group 2 channelizing devices (512SD20-0024) | DAY | 3,315 | $2.00 | $0.25 | $1.25 | $3.00 | $3.00 |
| 0001-0400 | Port.changeable mess. sign (512SD20-0025) | HR | 672 | $5.00 | $16.50 | $12.00 | $10.00 | $9.00 |
| 0001-0410 | Electronic arrow board (512SD20-0026) | HR | 1,560 | $5.00 | $0.70 | $3.00 | $9.00 | $5.00 |
| 0001-0420 | Flagger service (512SD20-0027) | HR | 100 | $65.00 | $52.00 | $90.00 | $40.00 | $90.00 |
| 0001-0430 | Warning light TY. B (512SD20-0029) | DAY | 2,520 | $1.50 | $0.75 | $0.60 | $1.00 | $1.50 |
| 0001-0440 | Temp. PVMT MRKG TY. E, 6" (512SD20-0054) | LF | 1,000 | $4.40 | $3.15 | $5.00 | $7.00 | $3.00 |
| 0001-0450 | Temp. PVMT MRKG TY. D, CL. III, 6" (512SD20-0062) | LF | 2,700 | $4.40 | $3.00 | $5.00 | $6.25 | $3.50 |
| 0001-0460 | Temp. PVMT MRKG TY. D, CL. III, 8" (512SD20-0063) | LF | 760 | $5.50 | $3.15 | $6.00 | $6.25 | $3.00 |
| 0001-0470 | Portable temporary rumble strip array (512SP20-0001) | DAY | 10 | $1,000.00 | $87.50 | $190.00 | $300.00 | $64.20 |
| 0001-0480 | Mobilization (513SD20-0001) | LS | 1 | $135,000 | $122,190 | $149,000 | $170,000 | $190,000 |
| 0001-0490 | Flexible pave. planing above 2"-4" (515SD20-0005) | SY | 1,114 | $15.00 | $25.18 | $15.00 | $17.00 | $12.00 |
| 0001-0500 | Mailbox post, single (521SD20-0001) | EACH | 1 | $500.00 | $537.50 | $550.00 | $1,000.00 | $1,000.00 |
| 0001-0510 | Topsoil class B 3" (602SD20-0004) | CY | 609 | $65.00 | $127.33 | $105.00 | $100.00 | $40.00 |
| 0001-0520 | Temporary seed (603SD20-0002) | LB | 558 | $5.00 | $4.25 | $14.00 | $15.00 | $13.00 |
| 0001-0530 | Regular seed (603SD20-0003) | LB | 872 | $6.50 | $5.75 | $9.00 | $12.00 | $10.00 |
| 0001-0540 | Overseeding (603SD20-0004) | LB | 698 | $8.50 | $7.61 | $8.00 | $6.00 | $8.00 |
| 0001-0550 | Legume seed (603SD20-0005) | LB | 9 | $7.25 | $6.65 | $25.00 | $20.00 | $15.00 |
| 0001-0560 | Legume overseeding (603SD20-0006) | LB | 7 | $9.50 | $8.51 | $25.00 | $20.00 | $15.00 |
| 0001-0570 | Hydraulic erosion control product type 2 (603SD20-0008) | SY | 14,036 | $0.65 | $0.45 | $1.00 | $1.00 | $0.75 |
| 0001-0580 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 16,347 | $0.75 | $0.65 | $1.20 | $1.10 | $0.75 |
| 0001-0590 | Sediment retention roll 18" min (603SD20-0011) | LF | 1,600 | $10.00 | $16.00 | $10.00 | $16.00 | $16.00 |
| 0001-0600 | Fertilizer nitrogen - N (603SD20-0014) | LB | 279 | $1.25 | $1.15 | $1.75 | $2.00 | $1.00 |
| 0001-0610 | Fertilizer phosphorous - P (603SD20-0015) | LB | 195 | $1.25 | $1.15 | $1.75 | $2.00 | $1.00 |
| 0001-0620 | Fertilizer potassium - K (603SD20-0016) | LB | 195 | $1.25 | $1.15 | $1.75 | $2.00 | $1.00 |
| 0001-0630 | NS lime agricultural lime (603SX20-0018) | TON | 15.35 | $300.00 | $300.00 | $300.00 | $260.00 | $280.00 |
| 0001-0640 | Rolled erosion CTRL product EC-2 type 2 (606SD20-0002) | SY | 10,851 | $1.50 | $1.32 | $3.00 | $3.00 | $1.00 |
| 0001-0650 | Rolled erosion CTRL product EC-3 type 3 (606SD20-0007) | SY | 766 | $5.00 | $4.60 | $5.00 | $8.00 | $7.00 |
| 0001-0660 | Remove existing 1 post sign structure (700SD20-0003) | EACH | 1 | $100.00 | $375.00 | $200.00 | $400.00 | $200.00 |
| 0001-0670 | Relocate EX. 1 post GRND mount SGN panel (700SD20-0012) | EACH | 4 | $555.00 | $321.00 | $600.00 | $400.00 | $540.00 |
| 0001-0680 | Conc. found. STP-1, TY. A (700SD20-0038) | EACH | 2 | $950.00 | $592.00 | $1,000.00 | $650.00 | $940.00 |
| 0001-0690 | Conc. found. STP-1, TY. B (700SD20-0039) | EACH | 2 | $1,725.00 | $897.00 | $1,800.00 | $1,000.00 | $1,680.00 |
| 0001-0700 | Type A PVMT line MRKG 4" (704SD20-0001) | LF | 4,160 | $1.80 | $0.50 | $2.00 | $1.60 | $0.50 |
| 0001-0710 | Type B class I PVMT line MRKG 6" (704SD20-0007) | LF | 1,450 | $3.30 | $2.25 | $4.75 | $3.10 | $2.00 |
| 0001-0720 | Type B class II PVMT line MRKG 24" (704SD20-0015) | LF | 12 | $20.00 | $14.50 | $100.00 | $85.00 | $16.00 |
| 0001-0730 | Inlaid pavement marker asphalt (704SD20-0032) | EACH | 6 | $1,200.00 | $425.00 | $500.00 | $1,100.00 | $450.00 |
| 0001-0740 | PVMT symb MRKG SGL turn arr. TY B CL II (704SD20-0048) | EACH | 5 | $350.00 | $250.00 | $500.00 | $450.00 | $270.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of February 25, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way