Jansen Inc.: WSDOT bid record
Jansen Inc. submitted 10 bids on Washington State DOT contracts in the data, from 25 JAN 2006 to 23 SEP 2026, and was the low bidder on 1 of them (10%). When it was not low, its total sat a median +33% above the low bid.
- Owner
- Washington State DOT
- Low bid volume
- $1,905,460
- Latest bid
- 23 SEP 2026
- Data through
- 07 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2006 | 3 | 0 | 0% |
| 2008 | 1 | 0 | 0% |
| 2009 | 1 | 0 | 0% |
| 2010 | 3 | 0 | 0% |
| 2016 | 1 | 1 | 100% |
| 2026 | 1 | 0 | 0% |
By region
| Region | Bids | Low bids | Win rate |
|---|---|---|---|
| SCR region | 3 | 0 | 0% |
| NWR region | 3 | 1 | 33% |
| OR region | 2 | 0 | 0% |
| SWR region | 1 | 0 | 0% |
| NCR region | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| High visibility fence | LF | 5 | 3 (60%) | $0.80 | $3.09 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Thompson Bros. Excavating, Inc | 4 | 3 of 4 |
| Scarsella Bros., Inc. | 3 | 3 of 3 |
| Granite Construction Company | 3 | 1 of 3 |
| Tapani Underground, Inc. | 3 | 2 of 3 |
| Northwest Construction, Inc. | 2 | 2 of 2 |
| Tri-State Construction, Inc. | 2 | 1 of 2 |
| N.A. Degerstrom, Inc. | 2 | 1 of 2 |
| MRM Construction, Inc. | 2 | 2 of 2 |
| Granite Northwest, Inc. DBA | 2 | 1 of 2 |
| Selland Construction, Inc. | 2 | 2 of 2 |
Latest bids
| Let | Contract | Region | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 23 SEP 2026 | XE3772 | SCR region | Sr 906 Hyak Vicinity Emergency Washout Restoration | 5 of 8 | $1,615,882 | +30% |
| 14 DEC 2016 | 008988 | NWR region | Sr 164 se 408th st to 196th ave se vic pavement repair and ada | 1 of 2 | $1,905,460 | Low, 4.0% under the second |
| 10 MAR 2010 | 007894 | NWR region | Sr 530 skaglund hill slide wetland mitigation | 19 of 22 | $918,893 | +55% |
| 06 JAN 2010 | 007867 | OR region | Sr 520 - pontoon anderson and middleton site restoration | 8 of 13 | $340,045 | +19% |
| 06 JAN 2010 | 007864 | SCR region | Sr 241 dry creek - construct box culvert | 16 of 20 | $468,208 | +56% |
| 11 FEB 2009 | 007659 | NWR region | Sr 542 warnick bluff site | 7 of 17 | $448,683 | +14% |
| 16 JAN 2008 | 007472 | SCR region | Sr 410 rattlesnake creek- stabilize slopes | 6 of 7 | $277,948 | +35% |
| 15 FEB 2006 | 007100 | OR region | I-5 mcallister creek stormwater | 3 of 6 | $232,355 | +38% |
| 26 JAN 2006 | 007087 | NCR region | Sr 26 sand hollow culvert replacement | 5 of 9 | $495,777 | +29% |
| 25 JAN 2006 | 007085 | SWR region | Sr 500 thurston way interchange wetland/planting | 5 of 7 | $478,981 | +33% |
How this record was read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Every bid counted here matched its published total to within one dollar; WSDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.