Selland Construction, Inc.: WSDOT bid record
Selland Construction, Inc. submitted 31 bids on Washington State DOT contracts in the data, from 07 DEC 2000 to 15 JUL 2026, and was the low bidder on 9 of them (29%). When it was not low, its total sat a median +13% above the low bid.
- Owner
- Washington State DOT
- Low bid volume
- $25,856,634
- Latest bid
- 15 JUL 2026
- Data through
- 07 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2000 | 1 | 1 | 100% |
| 2001 | 1 | 0 | 0% |
| 2002 | 1 | 0 | 0% |
| 2007 | 1 | 0 | 0% |
| 2008 | 1 | 0 | 0% |
| 2009 | 2 | 0 | 0% |
| 2010 | 5 | 3 | 60% |
| 2011 | 2 | 1 | 50% |
| 2012 | 3 | 1 | 33% |
| 2013 | 2 | 1 | 50% |
| 2014 | 1 | 0 | 0% |
| 2015 | 1 | 0 | 0% |
| 2017 | 1 | 0 | 0% |
| 2018 | 3 | 1 | 33% |
| 2019 | 1 | 1 | 100% |
| 2020 | 1 | 0 | 0% |
| 2021 | 1 | 0 | 0% |
| 2023 | 2 | 0 | 0% |
| 2026 | 1 | 0 | 0% |
By region
| Region | Bids | Low bids | Win rate |
|---|---|---|---|
| SCR region | 14 | 2 | 14% |
| NCR region | 14 | 5 | 36% |
| ER region | 2 | 1 | 50% |
| Region 0 | 1 | 1 | 100% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Embankment compaction | CY | 18 | 9 (50%) | $1.00 | $3.50 | |
| Shoring or extra excavation class B | SF | 16 | 7 (44%) | $1.00 | $1.00 | |
| Paint line | LF | 21 | 6 (29%) | $0.25 | $0.25 | |
| Flexible guide post | EACH | 24 | 5 (21%) | $31.50 | $33.23 | |
| Construction signs class A | SF | 16 | 4 (25%) | $13.50 | $16.21 | |
| Erosion and sediment control lead | DAY | 14 | 4 (29%) | $90.00 | $100.00 | |
| Crushed surfacing base course | TON | 21 | 3 (14%) | $20.00 | $26.44 | |
| Structure excavation class B including haul | CY | 11 | 3 (27%) | $5.00 | $15.00 | |
| Portable changeable message sign | HR | 11 | 3 (27%) | $3.00 | $5.12 | |
| Grate inlet type 2 | EACH | 11 | 3 (27%) | $2,500.00 | $2,000.00 | |
| Wattle | LF | 10 | 3 (30%) | $3.00 | $4.24 | |
| Painted drainage marking | EACH | 9 | 3 (33%) | $30.00 | $25.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Granite Construction Company | 10 | 5 of 10 |
| Hurst Construction LLC | 9 | 3 of 9 |
| Scarsella Bros., Inc. | 8 | 5 of 8 |
| Apollo, Inc. | 8 | 4 of 8 |
| Strider Construction Co., Inc. | 8 | 4 of 8 |
| Central Washington Asphalt, I | 6 | 1 of 6 |
| Pipkin Inc., DBA Pipkin Constr | 6 | 3 of 6 |
| William Charles Construction, | 6 | 2 of 6 |
| M.A. Deatley Construction, Inc | 5 | 1 of 5 |
| North Central Construction, In | 5 | 1 of 5 |
Latest bids
| Let | Contract | Region | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 15 JUL 2026 | XE3755 | SCR region | Us 12 Eschbach Rd & Ackley Rd/Clover Ln - I/S Safety Improvements | 5 of 5 | $2,201,801 | +28% |
| 19 APR 2023 | 009952 | SCR region | Us 97 jones rd - intersection improvements | 3 of 4 | $4,083,442 | +5.0% |
| 01 FEB 2023 | 009921 | NCR region | Us 2 / 97 easy street roundabout | 3 of 4 | $6,470,275 | +19% |
| 03 FEB 2021 | 009625 | SCR region | Us 395 ridgeline drive construct interchange | 6 of 8 | $13,799,919 | +12% |
| 01 APR 2020 | 009533 | SCR region | Us 12 white pass vicinity - major drainage phase 3 | 4 of 5 | $1,101,038 | +23% |
| 13 MAR 2019 | 009396 | SCR region | Us 12 white pass vicinity major drainage phase 2 | 1 of 3 | $645,588 | Low, 55% under the second |
| 11 APR 2018 | 009236 | NCR region | Us 97 n. of blewett pass culvert replacements | 4 of 6 | $1,496,524 | +38% |
| 07 FEB 2018 | 009205 | Region 0 | I-82 selah creek eb sra - water system improvements phase 2 - scr | 1 of 2 | $360,000 | Low, 8.0% under the second |
| 07 FEB 2018 | 009196 | SCR region | I-182 queensgate dr - interchange improvements | 2 of 6 | $2,445,216 | +2.0% |
| 01 FEB 2017 | 009010 | NCR region | Sr 150 no-see-um road intersection improvements | 2 of 6 | $5,933,072 | +12% |
| 04 MAR 2015 | 008717 | NCR region | Sr 281 / south of quincy at road 9 nw left turn lanes 15b007 | 4 of 4 | $458,903 | +12% |
| 27 FEB 2014 | 008575 | NCR region | Sr 243 mattawa- intersection improvements 14b008 | 4 of 4 | $1,516,851 | +21% |
| 07 MAR 2013 | 008424 | NCR region | Us 97 north of brewster passing lane | 2 of 5 | $1,027,469 | +5.0% |
| 10 JAN 2013 | 008409 | NCR region | Us 97 n of riverside nb passing lane | 1 of 7 | $829,108 | Low, 3.0% under the second |
| 06 DEC 2012 | 008385 | NCR region | Us 2 e. of coles corner box culvert | 1 of 9 | $644,193 | Low, 7.0% under the second |
| 08 FEB 2012 | 008244 | SCR region | Us 97 satus creek vicinity - replace br. 97/106 and paving | 10 of 13 | $10,676,253 | +21% |
| 25 JAN 2012 | 008240 | SCR region | Sr 410 nile valley landslide - re-construct route | 7 of 14 | $4,563,557 | +12% |
| 02 FEB 2011 | 008033 | SCR region | Us 12 sr 124 intersection - build interchange | 1 of 15 | $11,478,643 | Low, 4.0% under the second |
| 06 JAN 2011 | 008058 | NCR region | Ncr major drainage 2011 | 7 of 9 | $617,370 | +17% |
| 15 DEC 2010 | 008049 | SCR region | Us 12 allan road - intersection improvements | 4 of 4 | $426,445 | +12% |
| 09 DEC 2010 | 008045 | NCR region | Sr 28/us 2/97 intersection improvements | 1 of 4 | $3,829,670 | Low, 0.0% under the second |
| 04 FEB 2010 | 007862 | ER region | I-90 spokane port of entry - weigh station relocation | 1 of 8 | $6,704,333 | Low, 1.0% under the second |
| 21 JAN 2010 | 007871 | NCR region | Sr 26 west of othello passing lane | 1 of 7 | $608,774 | Low, 2.0% under the second |
| 06 JAN 2010 | 007864 | SCR region | Sr 241 dry creek - construct box culvert | 2 of 20 | $308,155 | +3.0% |
| 10 DEC 2009 | 007850 | ER region | Sr 27 pine creek bridge - replace bridge | 2 of 11 | $2,331,290 | +1.0% |
How this record was read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Every bid counted here matched its published total to within one dollar; WSDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.