WSDOT contract XE3755 bid tabulation

Us 12 Eschbach Rd & Ackley Rd/Clover Ln - I/S Safety Improvements. Let by Washington State DOT on July 15, 2026, Yakima, SCR region. 5 bids received; low bid $1,717,172 by Interwest Construction, Inc., -19% against the engineer's estimate of $2,111,619.

Owner
Washington State DOT
Letting
15 JUL 2026
Pay items
65
Data through
07 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Interwest Construction, Inc.$1,717,172Low-19%
2Kerr Contractors Oregon, Inc.$2,105,412+23%0.0%
3Culbert Construction, Inc.$2,176,000+27%+3.0%
4Granite Construction Company$2,181,978+27%+3.0%
5Selland Construction, Inc.$2,201,801+28%+4.0%
WSDOT contract XE3755: bids by rank

Engineer's estimate: $2,111,619.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Interwest Construction, Inc.2. Kerr Contractors Oregon, Inc.3. Culbert Construction, Inc.4. Granite Construction Company5. Selland Construction, Inc.
1MobilizationLS1$192,000$154,146$210,000$270,282$220,000$100,000
2Clearing and grubbingACRE1.60$15,000$2,605.00$20,000$25,433$21,000$6,600.00
3Removal of structures and obstructionsLS1$5,000.00$7,400.00$80,000$82,201$6,000.00$2,100.00
4Removing guardrailLF250$20.00$9.00$10.00$10.25$20.00$12.00
5Removing guardrail anchorEACH1$500.00$330.00$367.00$376.18$2,500.00$450.00
6Removing high tension cable barrier systemLF2,024$10.00$23.25$12.00$15.29$13.00$18.00
7Roadway excavation including haulCY2,190$40.00$31.00$33.50$52.74$69.00$64.00
8Channel excavation including haulCY19$75.00$28.00$70.00$139.86$65.00$200.00
9Grate inlet type 2EACH3$5,000.00$5,630.00$7,600.00$5,139.56$5,500.00$5,500.00
10Drop inlet type 2EACH1$8,000.00$8,000.00$13,100$9,214.80$12,800$9,000.00
11Quarry spallsCY14$150.00$73.00$162.00$186.08$117.00$200.00
12Catch basin type 2 48 inch diameterEACH1$7,500.00$7,500.00$10,500$6,423.44$9,100.00$10,000
13Testing storm sewer pipeLF836$7.50$2.00$2.00$4.99$6.00$6.00
14Schedule A storm sewer pipe 18 inch diameterLF262$150.00$81.00$122.00$234.22$114.00$115.00
15Schedule A storm sewer pipe 24 inch diameterLF109$250.00$150.00$177.00$332.97$261.00$140.00
16High-density polyethylene (HDPE) pipe 12 inch diameterLF465$250.00$54.00$118.00$176.63$113.00$160.00
17Crushed surfacing base courseTON6,030$40.00$29.50$38.00$50.60$49.00$42.50
18Planing bituminous pavementSY2,030$10.00$3.50$6.00$4.26$16.00$7.00
19Hot mix asphalt class 1/2 inch PG 64H-28TON2,500$150.00$117.00$111.00$107.63$145.00$130.00
20Job mix compliance price adjustmentCALC1$11,250$11,250$11,250$11,250$11,250$11,250
21Compaction price adjustmentCALC1$18,750$18,750$18,750$18,750$18,750$18,750
22Asphalt cost price adjustmentCALC1$2,000.00$2,000.00$2,000.00$2,000.00$2,000.00$2,000.00
23Inlet protectionEACH7$200.00$100.00$100.00$147.49$150.00$180.00
24Erosion control and water pollution preventionLS1$20,000$9,800.00$41,000$1,296.29$1,400.00$11,000
25Seeding, fertilizing, and mulchingACRE1.40$25,000$8,750.00$7,350.00$8,200.10$7,900.00$9,700.00
26Medium compostACRE1.40$20,000$33,000$52,000$61,501$6,600.00$65,000
27Roundabout cement concrete curb and gutterLF52$150.00$87.00$70.00$271.70$70.00$98.00
28Extruded curbLF716$25.00$18.00$16.00$16.40$16.00$32.50
29Beam guardrail type 31LF1,075$50.00$44.00$38.00$38.95$54.00$45.00
30Beam guardrail transition section type 21EACH1$8,000.00$11,700$8,750.00$8,968.86$4,550.00$10,000
31Beam guardrail type 31 non-flared terminalEACH1$5,000.00$6,100.00$3,900.00$3,997.55$3,550.00$5,000.00
32Additional high-tension cable barrier componentsLS1$25,000$47,500$16,000$16,400$12,500$20,000
33Modified short radius guardrail system (SRGS)LF150$200.00$144.00$200.00$205.00$130.00$250.00
34Additional modified SRGS componentsLS1$20,000$5,000.00$10,750$11,019$2,700.00$13,500
35Restoring high tension cable barrier systemLF1,974$50.00$90.00$50.00$51.25$88.00$60.00
36Flexible guide postEACH45$100.00$143.00$75.00$128.13$125.00$150.00
37Paint lineLF5,550$1.00$0.56$0.45$0.51$0.50$0.60
38Plastic traffic arrowEACH5$500.00$171.00$400.00$153.75$150.00$185.00
39Plastic drainage markingEACH17$250.00$68.00$80.00$61.50$60.00$75.00
40Permanent signingLS1$5,500.00$7,450.00$7,500.00$6,713.83$6,550.00$8,000.00
41Temporary pavement marking-short durationLF3,750$1.00$0.37$0.45$0.33$1.50$0.50
42Illumination system ackleyLS1$125,000$141,000$139,600$143,092$146,000$210,000
43Directional boringLF110$65.00$170.00$40.00$41.00$40.50$125.00
44Project temporary traffic controlLS1$175,000$90,000$230,000$130,719$176,000$249,000
45Portable changeable message signHR2,400$5.00$4.60$14.00$2.05$4.00$3.00
46Construction signs class ASF627$40.00$22.00$47.00$24.60$32.00$59.00
47Work zone safety contingencyEST1$25,000$25,000$25,000$25,000$25,000$25,000
48WSP reimbursementCALC1-$2.00-$2.00-$2.00-$2.00-$2.00-$2.00
49Plastic wide lineLF3,320$3.50$1.80$7.00$1.64$2.00$2.00
50Project partneringCALC1$2,000.00$2,000.00$2,000.00$2,000.00$2,000.00$2,000.00
51Structure excavation class B including haulCY788$50.00$9.10$10.50$12.70$16.00$25.00
52Shoring or extra excavation class BSF5,230$2.50$0.15$2.00$1.06$1.00$1.00
53Controlled density fillCY120$150.00$253.00$315.00$290.38$300.00$390.00
54Plugging existing pipeEACH1$2,000.00$615.00$425.00$514.56$3,400.00$620.00
55Roadway surveyingLS1$25,000$32,000$30,000$32,755$23,300$40,000
56Adjust inletEACH2$500.00$1,111.00$1,325.00$835.80$1,260.00$2,000.00
57Connection to drainage structureEACH1$1,500.00$1,785.00$3,000.00$2,972.66$6,400.00$5,300.00
58Cleaning existing drainage structureLS1$8,000.00$3,200.00$6,850.00$4,174.12$27,000$2,700.00
59Force account potholing utilitiesEST1$5,000.00$5,000.00$5,000.00$5,000.00$5,000.00$5,000.00
60Roadside cleanupEST1$10,000$10,000$10,000$10,000$10,000$10,000
61Reimbursement for third party damageEST1$5.00$5.00$5.00$5.00$5.00$5.00
62Minor changeCALC1-$2.00-$2.00-$2.00-$2.00-$2.00-$2.00
63Aggregate compliance price adjustmentCALC1-$2.00-$2.00-$2.00-$2.00-$2.00-$2.00
64Spill prevention, control, and countermeasures planLS1$2,000.00$1,000.00$5,000.00$221.01$500.00$2,500.00
65Construction geotextile for permanent erosion controlSY42$30.00$21.00$6.00$28.12$33.00$50.00
WSDOT contract XE3755: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WSDOT's tabulation for this contract. WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.

Every contract let that day: WSDOT letting of July 15, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy