WSDOT contract XE3755 bid tabulation
Us 12 Eschbach Rd & Ackley Rd/Clover Ln - I/S Safety Improvements. Let by Washington State DOT on July 15, 2026, Yakima, SCR region. 5 bids received; low bid $1,717,172 by Interwest Construction, Inc., -19% against the engineer's estimate of $2,111,619.
- Owner
- Washington State DOT
- Letting
- 15 JUL 2026
- Pay items
- 65
- Data through
- 07 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Interwest Construction, Inc. | $1,717,172 | Low | -19% |
| 2 | Kerr Contractors Oregon, Inc. | $2,105,412 | +23% | 0.0% |
| 3 | Culbert Construction, Inc. | $2,176,000 | +27% | +3.0% |
| 4 | Granite Construction Company | $2,181,978 | +27% | +3.0% |
| 5 | Selland Construction, Inc. | $2,201,801 | +28% | +4.0% |
Engineer's estimate: $2,111,619.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Interwest Construction, Inc. | 2. Kerr Contractors Oregon, Inc. | 3. Culbert Construction, Inc. | 4. Granite Construction Company | 5. Selland Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Mobilization | LS | 1 | $192,000 | $154,146 | $210,000 | $270,282 | $220,000 | $100,000 |
| 2 | Clearing and grubbing | ACRE | 1.60 | $15,000 | $2,605.00 | $20,000 | $25,433 | $21,000 | $6,600.00 |
| 3 | Removal of structures and obstructions | LS | 1 | $5,000.00 | $7,400.00 | $80,000 | $82,201 | $6,000.00 | $2,100.00 |
| 4 | Removing guardrail | LF | 250 | $20.00 | $9.00 | $10.00 | $10.25 | $20.00 | $12.00 |
| 5 | Removing guardrail anchor | EACH | 1 | $500.00 | $330.00 | $367.00 | $376.18 | $2,500.00 | $450.00 |
| 6 | Removing high tension cable barrier system | LF | 2,024 | $10.00 | $23.25 | $12.00 | $15.29 | $13.00 | $18.00 |
| 7 | Roadway excavation including haul | CY | 2,190 | $40.00 | $31.00 | $33.50 | $52.74 | $69.00 | $64.00 |
| 8 | Channel excavation including haul | CY | 19 | $75.00 | $28.00 | $70.00 | $139.86 | $65.00 | $200.00 |
| 9 | Grate inlet type 2 | EACH | 3 | $5,000.00 | $5,630.00 | $7,600.00 | $5,139.56 | $5,500.00 | $5,500.00 |
| 10 | Drop inlet type 2 | EACH | 1 | $8,000.00 | $8,000.00 | $13,100 | $9,214.80 | $12,800 | $9,000.00 |
| 11 | Quarry spalls | CY | 14 | $150.00 | $73.00 | $162.00 | $186.08 | $117.00 | $200.00 |
| 12 | Catch basin type 2 48 inch diameter | EACH | 1 | $7,500.00 | $7,500.00 | $10,500 | $6,423.44 | $9,100.00 | $10,000 |
| 13 | Testing storm sewer pipe | LF | 836 | $7.50 | $2.00 | $2.00 | $4.99 | $6.00 | $6.00 |
| 14 | Schedule A storm sewer pipe 18 inch diameter | LF | 262 | $150.00 | $81.00 | $122.00 | $234.22 | $114.00 | $115.00 |
| 15 | Schedule A storm sewer pipe 24 inch diameter | LF | 109 | $250.00 | $150.00 | $177.00 | $332.97 | $261.00 | $140.00 |
| 16 | High-density polyethylene (HDPE) pipe 12 inch diameter | LF | 465 | $250.00 | $54.00 | $118.00 | $176.63 | $113.00 | $160.00 |
| 17 | Crushed surfacing base course | TON | 6,030 | $40.00 | $29.50 | $38.00 | $50.60 | $49.00 | $42.50 |
| 18 | Planing bituminous pavement | SY | 2,030 | $10.00 | $3.50 | $6.00 | $4.26 | $16.00 | $7.00 |
| 19 | Hot mix asphalt class 1/2 inch PG 64H-28 | TON | 2,500 | $150.00 | $117.00 | $111.00 | $107.63 | $145.00 | $130.00 |
| 20 | Job mix compliance price adjustment | CALC | 1 | $11,250 | $11,250 | $11,250 | $11,250 | $11,250 | $11,250 |
| 21 | Compaction price adjustment | CALC | 1 | $18,750 | $18,750 | $18,750 | $18,750 | $18,750 | $18,750 |
| 22 | Asphalt cost price adjustment | CALC | 1 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 23 | Inlet protection | EACH | 7 | $200.00 | $100.00 | $100.00 | $147.49 | $150.00 | $180.00 |
| 24 | Erosion control and water pollution prevention | LS | 1 | $20,000 | $9,800.00 | $41,000 | $1,296.29 | $1,400.00 | $11,000 |
| 25 | Seeding, fertilizing, and mulching | ACRE | 1.40 | $25,000 | $8,750.00 | $7,350.00 | $8,200.10 | $7,900.00 | $9,700.00 |
| 26 | Medium compost | ACRE | 1.40 | $20,000 | $33,000 | $52,000 | $61,501 | $6,600.00 | $65,000 |
| 27 | Roundabout cement concrete curb and gutter | LF | 52 | $150.00 | $87.00 | $70.00 | $271.70 | $70.00 | $98.00 |
| 28 | Extruded curb | LF | 716 | $25.00 | $18.00 | $16.00 | $16.40 | $16.00 | $32.50 |
| 29 | Beam guardrail type 31 | LF | 1,075 | $50.00 | $44.00 | $38.00 | $38.95 | $54.00 | $45.00 |
| 30 | Beam guardrail transition section type 21 | EACH | 1 | $8,000.00 | $11,700 | $8,750.00 | $8,968.86 | $4,550.00 | $10,000 |
| 31 | Beam guardrail type 31 non-flared terminal | EACH | 1 | $5,000.00 | $6,100.00 | $3,900.00 | $3,997.55 | $3,550.00 | $5,000.00 |
| 32 | Additional high-tension cable barrier components | LS | 1 | $25,000 | $47,500 | $16,000 | $16,400 | $12,500 | $20,000 |
| 33 | Modified short radius guardrail system (SRGS) | LF | 150 | $200.00 | $144.00 | $200.00 | $205.00 | $130.00 | $250.00 |
| 34 | Additional modified SRGS components | LS | 1 | $20,000 | $5,000.00 | $10,750 | $11,019 | $2,700.00 | $13,500 |
| 35 | Restoring high tension cable barrier system | LF | 1,974 | $50.00 | $90.00 | $50.00 | $51.25 | $88.00 | $60.00 |
| 36 | Flexible guide post | EACH | 45 | $100.00 | $143.00 | $75.00 | $128.13 | $125.00 | $150.00 |
| 37 | Paint line | LF | 5,550 | $1.00 | $0.56 | $0.45 | $0.51 | $0.50 | $0.60 |
| 38 | Plastic traffic arrow | EACH | 5 | $500.00 | $171.00 | $400.00 | $153.75 | $150.00 | $185.00 |
| 39 | Plastic drainage marking | EACH | 17 | $250.00 | $68.00 | $80.00 | $61.50 | $60.00 | $75.00 |
| 40 | Permanent signing | LS | 1 | $5,500.00 | $7,450.00 | $7,500.00 | $6,713.83 | $6,550.00 | $8,000.00 |
| 41 | Temporary pavement marking-short duration | LF | 3,750 | $1.00 | $0.37 | $0.45 | $0.33 | $1.50 | $0.50 |
| 42 | Illumination system ackley | LS | 1 | $125,000 | $141,000 | $139,600 | $143,092 | $146,000 | $210,000 |
| 43 | Directional boring | LF | 110 | $65.00 | $170.00 | $40.00 | $41.00 | $40.50 | $125.00 |
| 44 | Project temporary traffic control | LS | 1 | $175,000 | $90,000 | $230,000 | $130,719 | $176,000 | $249,000 |
| 45 | Portable changeable message sign | HR | 2,400 | $5.00 | $4.60 | $14.00 | $2.05 | $4.00 | $3.00 |
| 46 | Construction signs class A | SF | 627 | $40.00 | $22.00 | $47.00 | $24.60 | $32.00 | $59.00 |
| 47 | Work zone safety contingency | EST | 1 | $25,000 | $25,000 | $25,000 | $25,000 | $25,000 | $25,000 |
| 48 | WSP reimbursement | CALC | 1 | -$2.00 | -$2.00 | -$2.00 | -$2.00 | -$2.00 | -$2.00 |
| 49 | Plastic wide line | LF | 3,320 | $3.50 | $1.80 | $7.00 | $1.64 | $2.00 | $2.00 |
| 50 | Project partnering | CALC | 1 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 51 | Structure excavation class B including haul | CY | 788 | $50.00 | $9.10 | $10.50 | $12.70 | $16.00 | $25.00 |
| 52 | Shoring or extra excavation class B | SF | 5,230 | $2.50 | $0.15 | $2.00 | $1.06 | $1.00 | $1.00 |
| 53 | Controlled density fill | CY | 120 | $150.00 | $253.00 | $315.00 | $290.38 | $300.00 | $390.00 |
| 54 | Plugging existing pipe | EACH | 1 | $2,000.00 | $615.00 | $425.00 | $514.56 | $3,400.00 | $620.00 |
| 55 | Roadway surveying | LS | 1 | $25,000 | $32,000 | $30,000 | $32,755 | $23,300 | $40,000 |
| 56 | Adjust inlet | EACH | 2 | $500.00 | $1,111.00 | $1,325.00 | $835.80 | $1,260.00 | $2,000.00 |
| 57 | Connection to drainage structure | EACH | 1 | $1,500.00 | $1,785.00 | $3,000.00 | $2,972.66 | $6,400.00 | $5,300.00 |
| 58 | Cleaning existing drainage structure | LS | 1 | $8,000.00 | $3,200.00 | $6,850.00 | $4,174.12 | $27,000 | $2,700.00 |
| 59 | Force account potholing utilities | EST | 1 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 |
| 60 | Roadside cleanup | EST | 1 | $10,000 | $10,000 | $10,000 | $10,000 | $10,000 | $10,000 |
| 61 | Reimbursement for third party damage | EST | 1 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 62 | Minor change | CALC | 1 | -$2.00 | -$2.00 | -$2.00 | -$2.00 | -$2.00 | -$2.00 |
| 63 | Aggregate compliance price adjustment | CALC | 1 | -$2.00 | -$2.00 | -$2.00 | -$2.00 | -$2.00 | -$2.00 |
| 64 | Spill prevention, control, and countermeasures plan | LS | 1 | $2,000.00 | $1,000.00 | $5,000.00 | $221.01 | $500.00 | $2,500.00 |
| 65 | Construction geotextile for permanent erosion control | SY | 42 | $30.00 | $21.00 | $6.00 | $28.12 | $33.00 | $50.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WSDOT's tabulation for this contract. WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
Every contract let that day: WSDOT letting of July 15, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.