Schedule A storm sewer pipe 18 inch diameter, WSDOT
Low bidders on WSDOT contracts carried a median of $81.00 per LF for this item, over the 24 months to 07 OCT 2026, across 1 low bids. Half of all 5 bids fell between $114.00 and $122.00.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- LF
- Data through
- 07 OCT 2026
WSDOT prints this item as “SCHEDULE A STORM SEWER PIPE 18 IN. DIAM.”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2000 | 1 | 1 | $25.00 | 6 | $31.00 |
| 2002 | 1 | 1 | $32.00 | 6 | $27.00 |
| 2003 | 2 | 2 | $31.50 | 11 | $30.00 |
| 2004 | 2 | 2 | $30.00 | 11 | $30.00 |
| 2005 | 5 | 5 | $33.00 | 26 | $32.00 |
| 2006 | 3 | 3 | $28.00 | 15 | $35.00 |
| 2007 | 9 | 9 | $38.00 | 55 | $38.00 |
| 2008 | 5 | 5 | $36.30 | 39 | $36.00 |
| 2009 | 4 | 4 | $34.25 | 31 | $35.50 |
| 2010 | 10 | 10 | $30.10 | 79 | $36.00 |
| 2011 | 4 | 4 | $51.50 | 35 | $46.00 |
| 2012 | 1 | 1 | $40.00 | 8 | $40.00 |
| 2013 | 2 | 2 | $59.73 | 14 | $59.00 |
| 2014 | 2 | 2 | $37.25 | 10 | $37.00 |
| 2015 | 1 | 1 | $46.00 | 6 | $58.00 |
| 2016 | 2 | 2 | $50.43 | 15 | $52.40 |
| 2017 | 3 | 3 | $42.00 | 16 | $48.00 |
| 2018 | 1 | 1 | $35.00 | 6 | $53.50 |
| 2019 | 2 | 2 | $98.50 | 9 | $110.00 |
| 2020 | 2 | 2 | $77.50 | 12 | $69.08 |
| 2021 | 3 | 3 | $105.00 | 12 | $122.50 |
| 2023 | 2 | 2 | $206.12 | 6 | $156.12 |
| 2026 | 1 | 1 | $81.00 | 5 | $115.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 37 | $35.00 | 247 | $36.30 |
| SWR region | 7 | $39.16 | 58 | $43.00 |
| OR region | 7 | $40.00 | 49 | $44.00 |
| ER region | 8 | $27.15 | 38 | $33.75 |
| SCR region | 5 | $46.00 | 24 | $58.00 |
| NCR region | 4 | $36.00 | 17 | $43.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 14 to 211 | 17 | $39.81 |
| 231 to 554 | 17 | $45.00 |
| 626 to 1,460 | 17 | $35.00 |
| 1,514 to 21,371 | 17 | $30.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Max J. Kuney Company | 16 | 5 (31%) |
| Mowat Construction Company | 11 | 5 (45%) |
| Kiewit Pacific Co. | 9 | 5 (56%) |
| Trimaxx Construction, Inc. | 8 | 5 (63%) |
| Scarsella Bros., Inc. | 29 | 4 (14%) |
| Granite Construction Company | 14 | 4 (29%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 15 JUL 2026 | XE3755 | SCR region | 262 | $81.00 | $115.00 | $150.00 | 5 | Interwest Construction, Inc. | WSDOT |
| 23 FEB 2023 | 009925 | ER region | 1,460 | $250.00 | $200.00 | $55.00 | 2 | Max J. Kuney Company | WSDOT |
| 01 FEB 2023 | 009921 | NCR region | 403 | $162.25 | $146.12 | $70.00 | 4 | Johansen Construction Company, | WSDOT |
| 15 DEC 2021 | 009742 | NWR region | 231 | $80.00 | $110.00 | $100.00 | 4 | Granite Construction Company | WSDOT |
| 24 MAR 2021 | 009636 | OR region | 45 | $105.00 | $118.30 | $100.00 | 4 | Graham Contracting, LTD. | WSDOT |
| 24 MAR 2021 | 009656 | NWR region | 33 | $115.00 | $125.00 | $135.00 | 4 | Marshbank Construction, Inc. | WSDOT |
| 20 FEB 2020 | 009516 | OR region | 360 | $60.00 | $60.00 | $52.00 | 8 | Interwest Construction, Inc. | WSDOT |
| 23 JAN 2020 | 009509 | ER region | 71 | $95.00 | $92.50 | $60.00 | 4 | Garco Construction, Inc. | WSDOT |
| 13 MAR 2019 | 009374 | NWR region | 494 | $73.00 | $110.00 | $100.00 | 7 | Marshbank Construction, Inc. | WSDOT |
| 21 FEB 2019 | 009382 | NWR region | 31 | $124.00 | $107.00 | $150.00 | 2 | SRV Construction, Inc. | WSDOT |
| 07 FEB 2018 | 009196 | SCR region | 551.53 | $35.00 | $53.50 | $60.00 | 6 | Central Washington Asphalt, In | WSDOT |
| 13 DEC 2017 | 009177 | NWR region | 250 | $73.00 | $73.00 | $60.00 | 3 | Tapani, Inc. | WSDOT |
| 01 FEB 2017 | 009010 | NCR region | 761 | $42.00 | $45.50 | $30.25 | 6 | Strider Construction Co., Inc. | WSDOT |
| 25 JAN 2017 | 009011 | ER region | 365 | $36.00 | $41.20 | $60.00 | 7 | Max J. Kuney Company | WSDOT |
| 21 DEC 2016 | 008993 | OR region | 2,175 | $61.05 | $50.00 | $40.00 | 9 | Scarsella Bros., Inc. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the WSDOT letting of 07 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.