Schedule A storm sewer pipe 12 inch diameter, WSDOT
Low bidders on WSDOT contracts carried a median of $147.50 per LF for this item, over the 24 months to 07 OCT 2026, across 2 low bids. Half of all 10 bids fell between $124.75 and $188.25.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- LF
- Data through
- 07 OCT 2026
WSDOT prints this item as “SCHEDULE A STORM SEWER PIPE 12 IN. DIAM.”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2000 | 2 | 2 | $23.16 | 12 | $27.50 |
| 2002 | 2 | 2 | $26.00 | 15 | $22.00 |
| 2003 | 3 | 2 | $16.50 | 12 | $17.88 |
| 2004 | 5 | 5 | $20.00 | 32 | $22.50 |
| 2005 | 5 | 5 | $28.00 | 32 | $27.00 |
| 2006 | 5 | 5 | $20.00 | 25 | $24.00 |
| 2007 | 10 | 10 | $32.50 | 60 | $30.35 |
| 2008 | 5 | 5 | $33.00 | 28 | $34.50 |
| 2009 | 5 | 4 | $25.25 | 32 | $25.25 |
| 2010 | 13 | 13 | $22.75 | 115 | $25.96 |
| 2011 | 6 | 6 | $35.00 | 40 | $30.20 |
| 2012 | 4 | 4 | $37.50 | 28 | $35.50 |
| 2013 | 8 | 8 | $53.79 | 42 | $51.83 |
| 2014 | 3 | 3 | $40.00 | 30 | $42.59 |
| 2016 | 7 | 7 | $45.00 | 40 | $47.00 |
| 2017 | 9 | 9 | $48.00 | 43 | $44.00 |
| 2018 | 2 | 2 | $273.00 | 5 | $80.00 |
| 2019 | 3 | 3 | $142.00 | 10 | $87.50 |
| 2020 | 1 | 1 | $53.00 | 4 | $50.00 |
| 2021 | 4 | 4 | $85.00 | 17 | $85.00 |
| 2022 | 4 | 4 | $115.00 | 12 | $91.25 |
| 2023 | 5 | 5 | $170.00 | 19 | $180.00 |
| 2026 | 2 | 2 | $147.50 | 10 | $147.50 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 59 | $32.12 | 362 | $32.00 |
| OR region | 16 | $40.00 | 114 | $35.00 |
| SWR region | 12 | $31.50 | 85 | $30.00 |
| ER region | 12 | $24.00 | 54 | $25.00 |
| NCR region | 8 | $28.66 | 33 | $35.00 |
| SCR region | 4 | $147.50 | 15 | $145.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 2.30 to 95 | 27 | $75.00 |
| 95 to 504 | 28 | $33.38 |
| 517 to 1,495 | 28 | $24.50 |
| 1,523 to 11,129 | 28 | $27.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Kiewit Pacific Co. | 9 | 8 (89%) |
| Granite Construction Company | 30 | 7 (23%) |
| Wilder Construction Company | 24 | 6 (25%) |
| Tri-State Construction, Inc. | 30 | 5 (17%) |
| Mowat Construction Company | 17 | 5 (29%) |
| Max J. Kuney Company | 16 | 4 (25%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 08 JUL 2026 | XE3751 | SCR region | 27 | $130.00 | $126.50 | $120.00 | 4 | Tapani, Inc. | WSDOT |
| 01 JUL 2026 | XE3756 | SCR region | 32 | $165.00 | $157.50 | $175.00 | 6 | N.A. Degerstrom, Inc. | WSDOT |
| 29 MAR 2023 | 009941 | OR region | 6 | $929.50 | $441.50 | $100.00 | 6 | Johansen Construction Company, | WSDOT |
| 23 FEB 2023 | 009925 | ER region | 1,275 | $170.00 | $135.00 | $39.00 | 2 | Max J. Kuney Company | WSDOT |
| 23 FEB 2023 | 009934 | NCR region | 2.30 | $2,750.00 | $1,500.00 | $1,500.00 | 3 | Central Washington Asphalt, Inc.Interstate Concrete & Asphalt | WSDOT |
| 01 FEB 2023 | 009921 | NCR region | 820 | $134.50 | $117.25 | $50.00 | 4 | Johansen Construction Company, | WSDOT |
| 11 JAN 2023 | 009909 | SWR region | 35 | $150.00 | $115.00 | $60.00 | 4 | Thompson Bros. Excavating, Inc | WSDOT |
| 09 MAR 2022 | 009774 | OR region | 470 | $55.00 | $65.00 | $112.00 | 2 | Kraemer North America, LLC. | WSDOT |
| 24 FEB 2022 | 009767 | NCR region | 115 | $170.00 | $137.50 | $53.00 | 2 | Granite Construction Company | WSDOT |
| 09 FEB 2022 | 009763 | OR region | 1,011 | $60.00 | $77.50 | $50.00 | 7 | Kraemer North America, LLC. | WSDOT |
| 12 JAN 2022 | 009758 | NWR region | 17 | $335.00 | $335.00 | $90.00 | 1 | Award Construction, Inc. | WSDOT |
| 15 DEC 2021 | 009742 | NWR region | 602 | $75.00 | $100.00 | $65.00 | 4 | Granite Construction Company | WSDOT |
| 24 MAR 2021 | 009636 | OR region | 2,050 | $120.00 | $114.00 | $30.00 | 4 | Graham Contracting, LTD. | WSDOT |
| 24 MAR 2021 | 009656 | NWR region | 349 | $95.00 | $90.00 | $85.00 | 4 | Marshbank Construction, Inc. | WSDOT |
| 13 JAN 2021 | 009623 | ER region | 923 | $30.00 | $34.00 | $35.00 | 5 | Max J. Kuney Company | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the WSDOT letting of 07 OCT 2026 and was rebuilt on 26 NOV 2026.